Brickyard_Road_FEMA_Drainage_Improvements_-_Cost_Estimate_-_02-11-2026.pdf
PDF 7 KB Posted
- Solicitation number
- PD 25-26.053
- Issued by
- Escambia County, Florida
About this file
Brickyard Road FEMA Drainage Improvements Cost Estimate
This cost estimate document from Escambia County, Florida details the probable construction costs for the Brickyard Road Drainage Improvements project, a Hurricane Sally recovery initiative funded through the Community Development Block Grant-Disaster Recovery (CDBG-DR HS005) program. The project encompasses replacement of a damaged 36-inch culvert pipe beneath Brickyard Road near Barth Road, extension of the new culvert beneath CSX Railroad right-of-way, roadway reconstruction with shoulder armoring, headwall installation, and rip rap placement at the outfall. The cost estimate, updated February 11, 2026, itemizes 26 pay items including mobilization ($70,000), erosion control and environmental compliance ($25,000), removal and replacement of unsuitable materials ($82,500), dewatering ($125,000), maintenance of traffic ($12,500), earthwork and grading operations, asphalt removal and replacement, pipe installation (including a 50-inch jack and bore operation for 36-inch RCP pipe installation at $670,000), concrete endwalls, guardrail installation, and removal of existing infrastructure elements. The estimated total project cost is $1,454,800.
The cost estimate reflects detailed quantity takeoffs and unit pricing for all construction line items necessary to complete the drainage improvements project. Major cost drivers include the 50-inch jack and bore plus 36-inch RCP pipe installation at 134 linear feet ($670,000), earthwork fill operations at 2,067 cubic yards ($103,350), articulated concrete block construction at 182 square yards ($56,875), and utility endwall installations. The estimate provides a comprehensive foundation for budgeting, procurement of Construction Engineering and Inspection (CE&I) services, and contractor bidding, with CE&I service costs anticipated not to exceed 7.5 percent of the estimated construction cost per the related RFQ issued by Escambia County.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pay
Item # DESCRIPTION QUANTITY UNITS UNIT PRICE EXT.
1 Mobilization 1 LS $ 70,000.00 $ 70,000.00
Erosion Control (Silt Fence Type IV, Hay Bales, Floating Turbidity Barrier, SWPPP, NPDES Permit, & Monitoring)
1 LS $ 25,000.00 $ 25,000.00
3 Remove and Replace Unsuitable Materials (Approximately 2,200 CY) 1 LS $ 82,500.00 $ 82,500.00
4 Dewatering 1 LS $ 125,000.00 $ 125,000.00
5 Maintenance of Traffic 1 LS $ 12,500.00 $ 12,500.00
Clearing and Grubbing (Including Trees UNDER 12" dia.), per County Specifications 2230
4420 SY $ 6.25 $ 27,625.00
5 Earthwork Excavation by machine 494 CY $ 25.00 $ 12,350.00
6 Earthwork Fill 2067 CY $ 50.00 $ 103,350.00
7 Earthwork Establishing Grade 4420 SY $ 5.00 $ 22,100.00
8 Centipede Sod, Staked 3913 SY $ 6.25 $ 24,456.25
9 Remove Existing Asphalt 3"-6" Thick 325 SY $ 10.00 $ 3,250.00
10 2" Type SP 12.5 Asphalt, over 1500sy 325 SY $ 18.75 $ 6,093.75
6" Graded aggregate Base "Min. LBR 100 at 100% Modified Proctor", over 1000sy
358 SY $ 62.50 $ 22,375.00
12 12" Stabilized Subgrade, over 1000sy 390 SY $ 12.50 $ 4,875.00
13 Construct Articulated Concrete Block 182 SY $ 312.50 $ 56,875.00
14 Rubble Riprap w/Filter Fabric & Bedding Stone (18" thick) 30 SY $ 250.00 $ 7,500.00
15 24" RCP Pipe 29 LF $ 200.00 $ 5,800.00
16 36" RCP Pipe 76 LF $ 343.75 $ 26,125.00
17 50" Jack & Bore + 36" RCP Pipe Installation 134 LF $ 5,000.00 $ 670,000.00
18 24" Mitered End Section (FDOT Index No 430-022) 1 EA $ 5,625.00 $ 5,625.00
19 36" U-Type Concrete Endwall (FDOT Index No 430-012) 1 EA $ 25,000.00 $ 25,000.00
20 Type "D" DBI (FDOT Index No 425-052) 1 EA $ 10,000.00 $ 10,000.00
21 Doghouse Type "D" DBI (72" Ex Pipe) >6' in depth 1 EA $ 31,250.00 $ 31,250.00
22 W Beam Guardrail with Posts per FDOT Index No 536-001 260 LF $ 62.50 $ 16,250.00
23 End Anchorage Assembly per FDOT Index No 536-001 4 EA $ 6,875.00 $ 27,500.00
24 Remove Existing Stand Pipe 1 LS $ 2,500.00 $ 2,500.00
25 Remove Existing Brick Wall 1 LS $ 25,000.00 $ 25,000.00
26 Remove Existing Storm Pipe (Over 24" Diameter) 78 LF $ 50.00 $ 3,900.00
Grand Total =
BRICKYARD ROAD FEMA - DRAINAGE IMPROVEMENTS
FEBRUARY - PROBABLE COST ESTIMATE
$1,454,800.00
]Brickyard Road - Cost Estimate - 02-11-2026 Updated 2/11/2026