BPS BP T13_Head-End Room_Addendum 5_Pre-Bid Mtg 2 Minutes_030618_vF.pdf

PDF 730 KB Posted

Attached to
BOND BID PACKAGE T13_DISTRICT HEAD-END ROOM RENOVATION
Solicitation number
RFP-BPS-180000001665-2
Issued by
Blissfield Village, Michigan

About this file

This document is Pre-Bid Meeting Minutes (Addendum #5) for Birmingham Public Schools' 2015 BOND Bid Package T13 - District Head-End Room Remodel project. The meeting was held on March 6, 2018, at 11:00 AM with representatives from Birmingham Public Schools, Berbiglia Associates Inc. (Project Manager), and fire suppression contractors in attendance. The project involves renovating and constructing District Head End Room Upgrades at Birmingham Covington School, with bid proposals due on March 12, 2018, at 1:00 PM EST. Questions were to be submitted to John Berbiglia by March 8, 2018. The pre-bid meeting was not mandatory, and a post-bid review was scheduled for the week of March 12, 2018.

The meeting addressed technical questions regarding room sealing integrity for fire suppression systems and ceiling tile specifications. Only fire suppression contractors attended the meeting, with electrical contractors (for UPS work) notably absent. The project intends to result in multiple contract awards according to bid categories. Contractors must register on the specified websites to receive updates and addendums, with bid documents available at bids.bpsecatalog.net and milogintp.michigan.gov. The project was prepared by TMP Architecture, Project Number 15105F dated December 15, 2017.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Birmingham Public Schools - Purchasing Department 31301 Evergreen Road, Beverly Hills, MI 48025

Lauren Mbereko – Purchasing Coordinator lmbereko@birmingham.k12.mi.us https://bids.bpsecatalog.net Phone: 248-203-3050

Pre-Bid Meeting (2) Minutes

DATE: Tuesday, March 6, 2018 TIME: 11:00 AM

PROJECT: 2015 BOND Bid Package T13 – District Head-End Room Remodel

JOB NUMBER: T13

PURPOSE: Pre-Bid Meeting #2

ATTENDEES: Birmingham Public Schools:

Lauren Mbereko, Purchasing Coordinator Dwight Levens, Director of Technology Paul Clark, Network Services Manager

Contractors:

See attached sign-in sheet

Project Manager’s Company:

Berbiglia Associates, Inc.

John Berbiglia 248-489-3100 jberbiglia@berbigliaassoc.com

Proposal Due Date and Time: Monday, March 12, 2018 at 1:00 P.M. EST

Submit Proposal to: Lauren Mbereko, Purchasing Coordinator Birmingham Public Schools 31301 Evergreen Road Beverly Hills, MI 48025

Submit Questions to: John Berbiglia Berbiglia Associates, Inc.

248-489-3100 jberbiglia@berbigliaassoc.com

Post-Bid Review: Week of March 12, 2018 – Date/Time TBD

Description of Procurement: BP T13 - Birmingham Covington School - District Head End Upgrades

Housekeeping Overview:

A. We request that you register at the web-site so you will receive additional information that maybe posted regarding this bid; this includes pre-bid meeting minutes and any addendums.

Bid proposal is available on-line at

1. https://bids.bpsecatalog.net; and

2. https://milogintp.michigan.gov/eai/tplogin/authenticate?URL=/uisecure/tpSelfService.

B. Please submit all questions no later than 5:00 PM local time, Thursday March 8, 2018. This is the deadline that we can guarantee the question will be addressed.

C. The pre-bid meeting was not mandatory.

D. Touring the Sites: Please be sure to always check in with main desk at the site/school when making site visits.

E. Scope: Birmingham Public Schools, hereby referred to as Owner, seeks proposals from qualified firms with which to establish a requirements contract for furnishing and install all labor, material and equipment necessary to renovation and construction the District Head End Room Upgrades in accordance to the documents and specifications prepared by TMP Architecture, Project

ADDENDUM #5

mailto:lmbereko@birmingham.k12.mi.us https://bids.bpsecatalog.net/ mailto:jberbiglia@berbigliaassoc.com mailto:jberbiglia@berbigliaassoc.com https://bids.bpsecatalog.net/ https://milogintp.michigan.gov/eai/tplogin/authenticate?URL=/uisecure/tpSelfService

Birmingham Public Schools - Purchasing Department 31301 Evergreen Road, Beverly Hills, MI 48025 https://bids.bpsecatalog.net Phone: 248-203-3050

Number 15105F dated December 15, 2017 (12-15-17). It is the intention of this Request for Bid to result in multiple contractors awarded according to the bid categories set forth in this RFB.

Introductions:

Andy Fountain from Plante Moran Cresa began the meeting by giving an overview of the project, plans and documents and asking if there were questions.

Question & Answer Period / Clarification:

Q: Is there a general contractor overseeing such things as the integrity of the sealing of the room which affects the fire killing gas/agent (sealing pipe fittings, holes, sweep-drop for bottoms of doors, etc). Is room self-contained or is a general contractor going to be in charge of the other air intake/outtake which can affect the sealing of the room/system integrity?

A: The hired contractor will corrdinate such findings with Plante Moran Cresa and request a work order if necessary. We encourage you to tell us what you are designing to in your bid, including qualifying your proposal as needed. Indicate the math/quantity of fire suppression gas when submitting your bid.

Q: Are all the ceiling tiles Gypsum board and clipped down?

A: We will look into ceiling tiles and talk to TMP (architect) about that to address.

Only fire suppression contractors attended today’s meeting. As we did not speak to any electricians regarding the UPS side of the bid, we will need to further address this issue.

Items Included:

Pre-Bid Meeting Minutes

Contractor Sign-In Sheet

Questions and Answers from the Pre-Bid Meeting (included in the meeting minutes).

This addendum will be sent to all email addressed registered. If you do not receive Addendum No. 1 please go to either https://bids.bpsecatalog.net or https://www.buy4michigan.com. It is the contractor’s responsibility to obtain the Addendum; if bid documents were not downloaded from the distribution website, it is the contractor’s responsibility to acquire all the updates/addendums, as you are not on the official plan holders list.

This meeting concluded at: 12:00 PM These minutes constitute our understanding of the proceedings of the meeting, and will be considered correct unless the writer is notified within three (3) days of the date of distribution.

mailto:lmbereko@birmingham.k12.mi.us https://www.buy4michigan.com/

Birmingham Public Schools - Purchasing Department 31301 Evergreen Road, Beverly Hills, MI 48025 https://bids.bpsecatalog.net Phone: 248-203-3050 mailto:lmbereko@birmingham.k12.mi.us

File details come from the government source that posted it. Updated .