This is a Request for Bids (RFB) document for Clifton T. Perkins Hospital Center, a Maryland Department of Health facility, soliciting contractor services for piping and recirculation pump repair in the central kitchen dietary area. The scope of work includes ceiling access and restoration, piping and insulation repair, recirculation pump replacement, roof drain pitch pocket repair, and debris cleanup and disposal. The contractor must furnish all labor, materials, and equipment, obtain necessary permits and utility markings, and provide coordination with on-site contractors and facility approval before initiating any service disruptions. A mandatory pre-bid conference and site visit is scheduled for July 7, 2026 from 9:30 to 10:30 a.m., requiring pre-registration by July 2, 2026. Written questions are due July 15, 2026 at 12:00 p.m., with bids due July 23, 2026 at 2:00 p.m. through eMMA and a public bid opening on July 24, 2026 at 11:00 a.m. via Google Meet. The contract is fixed-price with a three-month base period and no option periods, commencing upon award and continuing until completion.
This procurement is a Small Business Reserve restricted to businesses certified by the Governor's Office of Small, Minority & Women Business Affairs. Minimum qualifications require Maryland Board mechanical licensing at journeyman or master level with HVACR certification, or Maryland Board of Plumbing licensing, with at least three professional references documenting three years of relevant experience within the last five years. The maximum contract value is $50,000 for the entire term with bid pricing submitted by line item with all costs fully loaded. Commercial General Liability insurance and Workers' Compensation insurance of $1 million per occurrence are required. Contractor personnel must comply with facility security protocols, including badge display, background checks, and adherence to construction guidelines establishing patient safety requirements, tool and material security, smoke-free and drug-free environments, confidentiality, and professional conduct standards. A minimum two-year parts and labor warranty is required. No federal funding is involved.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clifton T. Perkins Hospital Center
Request for Bids for
Piping and Recirculation Pump Repair in Central Kitchen Area
Solicitation #BPM057647
Issue Date: June 18, 2026
A Prospective Bidder that has received this document from a source other than eMarylandMarketplace
Advantage (eMMA) https://procurement.maryland.gov should register on eMMA https://emma.maryland.gov/
NOTICE TO BIDDERS
SMALL BUSINESS RESERVE PROCUREMENT
This is a Small Business Reserve Procurement for which the award will be limited to certified small business vendors. Only businesses that meet the statutory requirements set forth in State Finance and
Procurement Article, §§14-501—14-505, Annotated Code of Maryland, and that are certified by the
Governor’s Office of Small, Minority & Women Business Affairs (GOSBA) Small Business Reserve
Program are eligible for award of a contract. Before awarding a contract under a procurement designated as a small business reserve procurement, the Procurement Officer shall verify that the apparent awardee is certified by the GOSBA as a small business through eMMA. However, if small businesses do not show interest in this solicitation, the Procurement Officer has the right to remove the SBR designation via an
Amendment on eMMA.
MINORITY BUSINESS ENTERPRISES ARE ENCOURAGED TO RESPOND TO THIS
SOLICITATION.
https://procurement.maryland.gov/ https://emma.maryland.gov/ https://gomdsmallbiz.maryland.gov/Pages/sbr-program.aspx https://gomdsmallbiz.maryland.gov/Pages/sbr-program.aspx
KEY INFORMATION SUMMARY SHEET (KISS)
Request for Bids Maintenance – Piping and Recirculation Pump Repair in Central Kitchen
Area
Solicitation
Number:
BPM057647
RFB Issue Date: June 18, 2026
RFB Issuing
Office:
Maryland Department of Health (MDH)
Clifton T. Perkins Hospital Center (CTPHC)
Procurement
Officer:
Victoria F. Bell, Director of Procurement
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd., Jessup, MD 20794
Email:
Phone Number:
Victoria.bell1@maryland.gov
410-724-3104
Bids are to be sent to:
Submit on emma.maryland.gov under Solicitation Number BPM057647
To submit a bid, bidders must first register on emma.maryland.gov. We recommend registering in advance to become acquainted with the site.
No Bid Notice
Feedback Form
If you are not submitting a bid for this solicitation, submit Attachment 1 with your reasons why. No Bid/Proposal Notice
Pre-Bid
Conference:
Piping & Recirculation Pump Repair Pre-Bid & Site Visit
Tuesday, July 7 · 9:30 – 10:30am
Time zone: America/New York
Google Meet joining info
Video call link: https://meet.google.com/xuy-psro-kif
Or dial: 3328-299-(US) +1 929 PIN: 346 926 835#
More phone numbers: https://tel.meet/xuy-psro-kif?pin=7073563799786
Scheduled Site
Visit
To attend the site visit please contact the Procurement officer via
Email no later than July 2, 2026 by 12:00 pm. Without pre-scheduling you will not be allowed admittance due to this being a Secure Facility.
Questions Due
Date and Time:
July 15, 2026, by 12:00 pm. Local Time mailto:Victoria.bell1@maryland.gov https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-1.-No-Bid_Proposal-Notice_Vendor-Feedback-Form-1-1.docx https://meet.google.com/xuy-psro-kif https://tel.meet/xuy-psro-kif?pin=7073563799786
Bid Due (Closing)
Date and Time:
July 23, 2026, at 2:00 pm Local Time
Bidders are reminded that a completed Feedback Form is requested if a no-bid decision is made: No Bid/Proposal Notice
Public Bid Opening
Date, Time, and
Location
BPM057647 Piping and Recirculation Pump Repair: Bid Opening
Friday, July 24 · 9:00 – 9:30am
Time zone: America/New York
Google Meet joining info
Video call link: https://meet.google.com/tcv-exws-pzv
Or dial: 3935-578-(US) +1 406 PIN: 419 006 785#
More phone numbers: https://tel.meet/tcv-exws-pzv?pin=6968647837334
MBE
Subcontracting
Goal:
N/A
VSBE
Subcontracting
Goal:
N/A
Procurement
Method:
A Contract will be awarded in accordance with the Small Procurement method under COMAR 21.05.07.
Multiple or
Alternate Bids:
Multiple or alternate Bids will not be accepted.
Contract Type: Fixed Price
Contract Duration: Three (3) Month base period with No option periods.
Primary Place of
Performance:
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd., Jessup, MD 20794
SBR Designation: Yes
Federal Funding: No
The remainder of this page is intentionally left blank.
https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-1.-No-Bid_Proposal-Notice_Vendor-Feedback-Form-1-1.docx https://meet.google.com/tcv-exws-pzv https://tel.meet/tcv-exws-pzv?pin=6968647837334
1. Summary Statement and Background
A. This Request for Bids (RFB) is issued to procure the goods or services, as specified in this section 4, from a contract between the successful bidder(s) and Clifton T. Perkins
Hospital Center (CTPHC) a part of the Maryland Department of Health (MDH).
B. CTPHC is a maximum-security psychiatric hospital that provides a comprehensive program for the evaluation and treatment of mental illness, with emphasis on assessment, treatment and recovery. The hospital program is structured to facilitate recovery through a graduated release process that begins in maximum security and culminates in release into the community.
C. CTPHC has an average daily inpatient population of approximately 285 patients and is accredited by the Joint Commission on the Accreditation of Healthcare Organization
(TJC).
D. The facility is currently undergoing several construction projects. The Contractor awarded MUST work in coordination with other contractors on site.
2. Minimum Requirements
As part of the determination to be considered responsive, the Bidder must submit documentation in its Bid that satisfies the following Minimum Qualifications:
A. The Bidder or its subcontractors shall submit with its bid a list of names of employees who will be performing the work under the scope of work of the contract resulting from this solicitation. For each employee to perform work under the resulting contract the
Bidder must include the following documentation of licensing, certifications and applicable experience:
1) DLLR Maryland Board mechanical licensing as a Journeyman or Master level with a copy of their Certification issued by the Board of Heating, Ventilation, Air Conditioning and Refrigeration Contractors (HVACR).
2) Secondary to (i.) is DLLR Maryland Board of Plumbing licensed journeyman, master plumber that can have an apprentice (not necessary); this licensing or authorization to perform plumbing/construction work if in Howard County, MD
(requirements).
3) A copy of their state or county Business License where they perform business.
B. The Bidder or its subcontractors shall provide at least 3 references that attest to their capabilities and general experience (corroboration of at least 3 years of experience total within the last 5 years) in providing services as applicable to the Scope of Work.
3. The identity of the Procurement Officer Victoria F. Bell, MBA, CMPO
Director of Procurement
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd.
Jessup, MD 20794
410-724-3104
Email: victoria.bell1@maryland.gov mailto:vbell1@maryland.gov
4. Deliverables / Scope of Work The project is intended to prevent leaking and restore operations as intended with original design.
All measurements and components’ makes and models must be field-verified. As stated, the
Contractor awarded this contract MUST work in coordination with other contractors on site. No piping shutdowns or isolations will occur without the knowledge of both the facility and on-site contractors, and MDH/CTPHC advanced approval.
A. Ceiling Access and Restoration:
1) Removal- Carefully remove existing ceiling materials, as required to gain access to the damaged piping and pump. Minimize damage to surrounding ceiling materials to allow for reuse where possible.
2) Protection- Implement measures to prevent debris and dust from contaminating the surrounding area during removal.
3) Installation- Upon completion of repairs and inspection, re-install or replace ceiling materials to match the existing ceiling finish and grid structure.
B. Piping and Insulation Repair:
1) Removal- Remove damaged piping and associated insulation in accordance with federal, state, and local codes.
2) Replacement- Install new piping and insulation, ensuring proper sizing and fit in accordance with all applicable codes.
3) Insulation standards- Apply new insulation to the pipe, ensuring it is dry and clean. Seal all joints, breaks, and voids in the vapor barrier jacket to make it watertight, in accordance with federal, state, and local codes.
C. Recirculation Pump Replacement:
1) Isolation- Isolate the existing pump (manufacturer – Taco) by closing service valves and allowing the system to cool. If no service valves are present, the system must be drained. (See Image.1 Section 18.)
2) Removal- Disconnect the electrical supply and remove the old pump
(manufacturer – Taco).
3) Installation- Install one (1) new recirculation pump (manufacturer – Taco), using new gaskets/O-rings.
4) Commissioning- Ensure proper orientation (arrow pointing in direction of flow), reconnect electrical wiring, open valves, and check for leaks.
D. Roof Drain Pitch Pocket Repair (Anticipated Work):
1) Inspection- Inspect the existing roof drain pitch pocket for damage, leakage, or failed sealant.
2) Replacement- If needed, remove the old pitch pocket material and replace it with new, approved sealant/pitch to ensure a watertight seal.
3) NOTE: This is an anticipated item that may not be required.
E. Cleanup and Disposal:
1) Waste Management- Remove all debris, old pipe, insulation, pump, and packing materials from the site on a daily basis and dispose of in accordance with federal, state and local regulations.
2) Cleaning- Thoroughly clean all affected areas, including removing any dust or debris from the work area caused by operations at all times.
3) The Contractor shall be responsible for removal and disposal of all debris and defective materials removed in performance of the service and in strict accordance with all applicable regulations, codes, laws, and ordinances.
4) If the area is not cleaned by the Contractor upon completion, the sum of $50.00 per hour needed to clean the area shall be deducted from the Contractor’s invoice, not as a penalty but as liquidated damages.
F. The Contractor shall furnish all labor, materials, and equipment (i.e., ladders, etc.), to perform all operations required to complete the total work in accordance with the deliverables. If ACM is encountered, a certified abatement contractor is required. All work must comply with safety regulations, The Joint Commission Hospital Accreditation requirements, NIST, ANSI, applicable codes, and Federal, State, and local laws and regulation, which include, but are not limited to:
1) Basic National Building Code (BOCA);
2) Federal EPA;
3) OSHA;
4) MDE guidelines; and
5) HVAC or Plumbing Code
G. All work shall be approved and coordinated with the CTPHC authorized represented
(Contract Monitor and MDH) for shutdown of water or electrical systems as beginning of
Scope of Work, prior to any work being performed. All work shall be performed to the complete satisfaction of CTPHC. The Contractor shall work until each job is completed and when necessary. The Contractor shall not perform additional work not stated in specifications that may lead to additional costs without written approval from the
Contract Monitor or Designee or CTPHC Procurement Office. The Contractor must have the approval of the Contract Monitor or designee before any modifications or alterations are made.
H. The Contractor shall provide a minimum two (2) year parts and labor warranty.
I. The Contractor shall be responsible for obtaining all necessary permits before work is started, if applicable. The Contractor is also responsible for contacting and obtaining utility markings from Miss Utility, if applicable. The Contractor and all employees must be in possession of a State or Federal issued ID to enter the facility. Any employee that does not have the ID may be denied access to the facility.
J. Contractor must comply with all facility and MDH security requirements to work at facility, including but not limited to: (Attachments) access and escorting, tool inventory, contraband compliance, and all other facility requirements for contractors.
5. State Staff and Roles
A. Contract Monitor
1) The State will provide a Contract Monitor, who may select a designee, with the responsibility for providing authorization for work to be performed and validation of completed work under this solicitation and subsequent contract.
2) The Contract Monitor will designate additional personnel and will provide associated contact information as needed.
3) The Contract Monitor or their designee shall provide access to work areas required to complete assigned tasks pursuant to this solicitation and subsequent contract.
B. Other Staff Responsibilities
1) Problem Escalation Procedure (PEP): Contract Monitor or designee will give written notice of performance issues to the Contractor, clearly describing the problem and delineating remediation requirements(s). The Contractor shall respond with a written remediation plan within three (3) Business Days and implement the plan immediately upon written acceptance of the Contract
Manager. If performance issues persist, the Contractor Manager may request the immediate removal of the person(s) whose performance is at issue and determine whether a substation is required.
6. Contract term
A. The contract resulting from this solicitation shall be a Fixed Price Contract, which shall commence upon Contract Award and continue for a period of approximately Three (3) months or until completion, with No option periods.
B. The total cost of work shall not exceed $50,000.00 for the term of the contract.
7. Procurement method This Contract will be awarded in accordance with the Small Procurement method under COMAR
21.05.07.
8. Bid/Proposal submission information
A. The Bid/Proposal is due on July 23, 2026, at 2:00 p.m. Local Time (Key Information
Sheet)
B. Bids may only be submitted via eMMA (eMaryland Market Place Advantage.
Bidders shall provide their Bids in one submission through eMMA following the
Quick Reference Guides (QRG). Please DO NOT hand deliver any replies to the facility.
C. What must be submitted.
1) The bid form with appropriate pricing.
2) A transmittal letter prepared on the Bidder’s business stationery MUST accompany the bid. The purpose of this letter is to transmit the bid and references; therefore, it should be brief. The letter shall be signed by an individual or corporate officer who is authorized to bind his firm to all statements, including services, material availability, timeliness and prices contained in the bid.
3) At least three (3) references that can attest to the Contractor’s experience in providing services for a similar business entity of this nature.
4) With the transmittal letter, each Contractor is to provide a list of all contracts with any entity of the State of Maryland that it is currently performing, or which have been completed within the last five (5) years. For each identified contract the Contractor is to provide:
i. The State contracting entity.
ii. A brief description of the services/goods provided.
iii. The dollar value of the contract.
iv. The term of the contract.
v. The State employee contact person (name, title, telephone number and e-mail address).
vi. Whether the contract was terminated before the end of the term specified in the original contract, including whether any available renewal option was not exercised.
5) Qualifications documentation that may be required, as set forth in RFB Section
2. Minimum Qualifications. Failure to submit the bid form or documentation as stated in Section 2 will result in the Contractor's offer being deemed ineligible for consideration.
6) Site Visit requirements (see Section 9 and Key Information Summary Sheet).
7) Additional required attachments listed in Section 18.
8) Any Addendum posted after this solicitation with required signatures.
D. Inquiries Statement:
1) Written questions from prospective Bidders will be accepted by the
Procurement Officer and shall be submitted via eMMA to the Procurement
Officer indicated in Section 3 of this document. Questions should be submitted no later than July 15, 2026, by 12:00 p.m. Local Time, (Key
Information Summary Sheet)
2) The Procurement Officer, based on the availability of time to research and communicate an answer, shall decide whether an answer can be given before the Bid due date.
9. Site Visit Requirements
In addition to the Pre-Bid Conference listed on the Key Information Summary Sheet, a site visit will take place at the facility directly following the meeting. The site visit is highly recommended in order to facilitate better preparation of Bids and understand the requirements of the
Deliverables / Scope of Work. The site visit will require pre-registration for attendance.
10. Award Determination
A. The Contract to result from this solicitation will be awarded to the Bidder submitting the
Most Favorable Bid Price (“Most favorable” is defined in COMAR 21.01.02.01.B. (57).
B. The Most Favorable Bid Price, will be determined by the “lowest responsive bid from a responsible bidder”.
11. Payment
The Contractor shall bill the Department on a monthly basis for the work performed the previous month. The total cost of work may not exceed $50,000.00 for the term of the contract.
A. To be considered for payment, submission of a proper invoice must include the following information, without error:
1) Contractor name and address;
2) Remittance address;
3) Federal taxpayer identification (FEIN) number, social security number, appropriate;
4) Invoice period (i.e. time period during which services covered by invoice were performed);
5) Invoice date;
6) Invoice number;
7) State assigned Contract number;
8) State assigned (Blanket) Purchase Order number(s);
9) Goods or services provided;
10) Amount due; and
11) Any additional documentation required by regulation or the Contract.
B. The State reserves the right to reduce or withhold Contract payment in the event the
Contractor does not provide all required deliverables within the time frame specified in the Contract or otherwise breaches the terms and conditions of the Contract until such time as the Contractor brings itself into full compliance with the Contract.
C. The State is generally exempt from federal excise taxes, Maryland sales and use taxes, District of Columbia sales taxes and transportation taxes. The Contractor, however, is not exempt from such sales and use taxes and may be liable for the same. Invoices for final payment shall be clearly marked as “Final” and submitted when all work requirements have been completed, and no further charges are to be incurred under the Contract. In no event shall any invoice be submitted later than sixty (60) calendar days from the Contract termination date. The Contractor shall submit invoices by the 15th of the month in which services were delivered. Invoices must be addressed to:
Chief Financial Officer
Clifton T. Perkins Hospital Center
8450 Dorsey Run Rd.
Jessup, MD 20794
Invoices may be mailed to the address above or electronically submitted to:
dlctphcfiscalservices_MDH@maryland.gov mailto:dlctphcfiscalservices_MDH@maryland.gov
12. Contractor’s Responsibilities Upon Award A. Man/Person-hours paid under this contract shall be only for productive hours at the job site. Time spent for idle time, breaks and lunch is not directly chargeable but is overhead and shall be included in the hourly rate bid for basic labor.
B. All parts and materials used by the contractor shall be billed to CTPHC at actual cost to the Contractor. No mark-up cost in addition to the cost to the Contractor will be accepted. The Contractor shall not markup the sales tax portion of the source materials invoice. CTPHC will reimburse sales tax paid by the contractor on a dollar-for-dollar basis only. CTPHC has the option to purchase any individual part/material for the service/repair. A copy of the Contractor’s source invoice(s) for all parts/materials used for repairs/services must accompany his invoice in order to be reimbursed. Payments shall not be made for any parts/material without the proper documentation attached to the
Contractor’s original invoice.
C. Upon completion of the service, the Contractor must obtain signed verification from the contract monitor or designee that the service has been performed. All inspections shall be coordinated with the contract monitor or designee and any problems which require attention shall be reported to the contract monitor or designee.
D. The Contractor shall be required to evaluate the condition of all equipment and make appropriate recommendations to the Contract Monitor as to what items are in need of repair or replacement. The Contractor shall be required to gather and provide all pertinent product information on the part needing repair or replacement. This information shall be comprehensive enough so that the new repair/replacement parts may be ordered and obtained in a timely fashion. The Contract Monitor shall be consulted, and approval required before any new components are ordered.
E. If the Contractor finds that extra repair work is necessary to return the facilities impacted by the plumbing or plumbing related systems to an acceptable condition prior to assuming the equipment covered under this Contract, the Contractor will so note the problem and the cost of such repair and attach this information to the bid documents. If the additional work is authorized by Clifton T. Perkins Hospital Center, the Contractor shall complete the extra work within thirty (30) days from the initial date of the Contract.
If such written statement is not submitted, this will be construed as the Contractor accepting the condition of the equipment for normal operation.
F. Any failure by the Contractor to become acquainted with available information shall not relieve the Contractor from the responsibility for estimating properly the difficulty or cost of successfully performing the work. Clifton T. Perkins Hospital Center assumes no responsibility for any conclusions or interpretations made by the Contractor on the basis of the information made available by Clifton T. Perkins Hospital Center.
G. Procurement of parts and/or materials needed will be up to the discretion of the Contract
Monitor or designee as to whether they will be purchased through the Contractor or purchased from another supply source. This will be determined as the need arises. If any major equipment failure should occur, the Hospital Center reserves the right to obtain competitive bids for the project.
H. The Contractor shall be able to provide replacement parts and/or devices, as required, within 48 hours of notification to the Contract Monitor or designee that repairs are necessary for the plumbing and plumbing related system components covered by this
Contract.
I. Travel time for service calls shall be the sole responsibility of the Contractor, and the
Contractor shall bear the cost as part of the Contractor’s base bid proposal.
J. Truck inventory (items normally kept in stock on the plumber’s truck) may be invoiced at a regular reasonable rate for all items costing less than $25.00. For any non-truck inventory items (job specific) that the Contractor has to retrieve from their suppliers, CTPHC will require proof of actual cost (source document).
K. Provide mechanical repairs, and new, pre-approved replacement parts for all repairs.
Those repairs recommended to prevent failure must be pre-approved by the Contract
Montor or Designee. Any costs for hardware, components and peripheral devices must be approved by the CTPHC Contract Monitor or designee. All materials are at the
Contractor’s verified costs, which requires the Contractor to submit their supplier’s invoice to CTPHC for reimbursement.
13. Department Obligations
The department agrees to:
A. Provide guidance concerning contract activities, as needed;
B. Evaluation and acceptance when appropriate of deliverable
C. Review and approval for payment of invoices.
14. Small Business Reserve Requirements A. This is a Small Business Reserve Procurement for which award will be limited to certified small business Contractors. Only businesses that meet the statutory requirements set forth in State Finance and Procurement Article, §§14-501 —14-505, Annotated Code of Maryland, and that are certified by the Governor’s Office of Small, Minority &
Women Business Affairs (GOSBA) Small Business Reserve Program are eligible for award of a contract.
15. Insurance Requirements The Contractor shall maintain, at a minimum, the insurance coverages outlined below, or any minimum requirements established by law if higher, for the duration of the Contract:
A. Commercial General Liability - One million dollars ($1,000,000) combined single limit per occurrence for bodily injury, property damage, and personal and advertising injury and three million dollars ($3,000,000) annual aggregate. The minimum limits required herein may be satisfied through any combination of primary and umbrella/excess liability policies.
B. Worker’s Compensation - The Contractor shall maintain such insurance as necessary or as required under Workers’ Compensation Acts, the Longshore and Harbor Workers’
Compensation Act, and the Federal Employers’ Liability Act, to not be less than. one million dollars ($1,000,000) per occurrence (unless a state’s law requires a greater amount of coverage). Coverage must be valid in all states where work is performed.
C. The State shall be listed as an additional insured on the faces of the certificates associated with the coverages listed above, including umbrella policies, excluding
Workers’ Compensation Insurance and professional liability.
D. All insurance policies shall be endorsed to include a clause requiring the insurance carrier to provide the Procurement Officer, by certified mail, not less than 30 days’ advance notice of any non-renewal, cancellation, or expiration. The Contractor shall notify the
Procurement Officer in writing, if policies are canceled or not renewed within five (5) days of learning of such cancellation or nonrenewal. The Contractor shall provide evidence of replacement insurance coverage to the Procurement Officer at least 15 days prior to the expiration of the insurance policy then in effect.
E. Any insurance furnished as a condition of the Contract shall be issued by a company authorized to do business in the State.
F. The recommended awardee must provide current certificate(s) of insurance with the prescribed coverages, limits and requirements set forth in this section within five (5)
Business Days from the notice of the recommended award. During the period of performance for multi-year contracts, the Contractor shall provide certificates of insurance annually, or as otherwise directed by the Contract Monitor.
G. Subcontractor Insurance
The Contractor shall require any subcontractors to obtain and maintain comparable levels of coverage and shall provide the Contract Monitor with the same documentation as is required of the Contractor.
16. Security Requirements The following requirements are applicable to the Contract upon award:
A. Employee Identification:
1) Contractor Personnel shall display his or her company ID badge in a visible location at all times while on State premises. Upon request of authorized State personnel, each Contractor Personnel shall provide additional photo identification.
2) Contractor Personnel shall cooperate with State site requirements, including but not limited to, being prepared to be escorted at all times, and providing information for State badge issuance.
3) Contractor shall remove any Contractor Personnel from working on the Contract where the State determines, in its sole discretion, that Contractor Personnel has not adhered to the Security requirements specified herein.
4) The State reserves the right to request that the Contractor submit proof of employment authorization of non-United States Citizens, prior to commencement of work under the Contract.
B. Persons with a criminal record may not perform services under the Contract unless prior written approval is obtained from the Contract Monitor. The Contract Monitor reserves the right to reject any individual based upon the results of the background check.
Decisions of the Contract Monitor as to acceptability of a candidate are final. The State reserves the right to refuse any individual Contractor Personnel to work on State premises, based upon certain specified criminal convictions, as specified by the State.
17. Verification of Registration and Tax Payment A. Before a business entity can do business in the State, it must be registered with the State
Department of Assessments and Taxation (SDAT). SDAT is located at State Office
Building, Room 803, 301 West Preston Street, Baltimore, Maryland 21201. For registration information, visit https://egov.maryland.gov/BusinessExpress/.
B. It is strongly recommended that any potential Bidder complete registration prior to the
Bid due date and time. The Bidder’s failure to complete registration with SDAT may disqualify an otherwise responsive successful Bidder from final consideration and recommendation for Contract award.
https://egov.maryland.gov/BusinessExpress/
18. Attachments A. Exhibit A-Contractor Construction Guidelines
B. Exhibit B-1 Bid Form
C. Exhibit C-Small Procurement Contract (Example)
D. Exhibit D-Contractor Daily Report
E. Exhibit E-Acknowledgement of Confidentiality
F. Exhibit F-Contractor Safety Reference Sheet
G. Exhibit G-Outside Vendor Tool Inventor Form
H. State Links for Bid Attachments to Include:
Bid/Proposal Affidavit
Bidder/Offer Information Sheet
Conflict of Interest Affidavit
Reference Checks
List of Current or Prior State Contracts
Legal Action Summary
List of All Subcontractors
Non-Disclosure Agreement (Contractor)
Contract Affidavit I. Image.1 https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-F.-Bidder-Offeror-Information-Sheet.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-M.-List-of-Current-or-Prior-State-Contracts.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-N.-Legal-Action-Summary.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-P.-Prime-Contractor-List-of-ALL-Subcontractors.xlsx https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-S.-Non-Disclosure-Agreement-Contractor.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf
File details come from the government source that posted it. Updated .