Boykin Springs Parking Lot and Roadway Improvement Specifications.pdf
PDF 351 KB Posted
- Solicitation number
- 12445121B0002
- Issued by
-
Department of Agriculture Forest Service
About this file
This invitation for bid solicits offers for the Boykin Springs Parking Lot and Roadway Repairs project located on the Angelina National Forest in Texas. The scope of work includes repairing asphalt pavement along Forest Service Road 313 including spot repairs, milling, and overlay. It also involves replacing three culverts, removing and replacing an entire parking lot, removing two cattle guards, and installing traffic and parking signage. Offerors must provide materials, equipment, and labor to complete ditch reconditioning, clearing, excavation, base and pavement installation, concrete work, and other items listed in the schedule of items and specifications. The bid submission deadline is September 3, 2021. The Forest Service will open bids on that same date at 1:15 pm Central Time. The contract has a 240-day completion period after notice to proceed. The solicitation sets aside this procurement entirely for service-disabled veteran-owned small businesses. The value is between $1 million and $5 million. The Forest Service seeks to award a firm-fixed-price contract to the lowest priced responsive and responsible bidder.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04
104.06 Use of Roads by Contractor
105 - Control of Material
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.02 Visual Inspection
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05
108 - Prosecution and Progress
Delete Section 108
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09
109.01 Measurement of Work
109.02 Measurement Terms and Definitions
109.03 Weighing Procedures and Devices
117 – Spot Premix Patching, Paved Surfaces
117.01 Maintenance Requirements
117.02 Material ‐Hot Mix‐Cold Laid Asphaltic Concrete Pavement
117.03 Method of Measurement
117.04 Basis of Payment
155 - Schedules for Construction Contracts
Delete Section 155
213 - Subgrade Stabilization
213.05 General
301 - Untreated Aggregate Courses
301.03 General
301.05 Compacting
303 - Road Reconditioning
303.07 Roadway Reconditioning
411 - Asphalt Prime Coat
411.05 Weather Limitations
412 - Asphalt Tack Coat
412.05 Weather Limitations
413 - Asphalt Pavement Milling
413.01 Description
413.03 Milling
413.05 Measurement
413.06 Payment
Preface Preface_wo_06_09_2021
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.
101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016
Add the following paragraph to Subsection 101.01:
101.01 Meaning of Terms.
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_National_11_9_2016
Add the following to Subsection 101.03:
101.03 Abbreviations.
(a) Acronyms.
AGAR — Agriculture Acquisition Regulations
AFPA — American Forest and Paper Association
FSAR — Forest Service Acquisition Regulations
MSHA — Mine Safety and Health Administration
NESC — National Electrical Safety Code
WCLIB — West Coast Lumber Inspection Bureau
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume
STA station location
101.04_National_1_22_2020
Make the following changes to Subsection 101.04:
101.04 Definitions.
Delete these definitions and replace the following:
Bid Schedule — The Schedule of Items.
Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.
Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.
Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236‐21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.
Right‐of‐Way — A general term denoting (1) the privilege to pass over land in some particular line
(including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2)
Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Add the following definitions:
Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service — The United States of America, acting through the Forest Service, U.S. Department of
Agriculture.
Neat Line — A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road — Temporary construction access built along the route of the project.
Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road
Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP‐14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.
Utilization Standards —
The minimum size and percent soundness of trees described in Public Works contract specifications or
Timber Sale and IRTC contract provisions to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101‐1—Illustration of road structure terms.
102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016
Delete Section 102 in its entirety.
Delete Section 102.
103 - Scope of Work 103.00_National_11_9_2016
Delete all of Section 103 except Subsection 103.01 Intent of Contract.
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work 104.00_National_11_9_2016
Delete Subsections 104.01, 104.02, and 104.04.
Delete Subsections 104.01, 104.02, 104.04.
104.06_National_11_9_2016
Add the following to Subsection 104.06:
104.06 Use of Roads by Contractor.
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road
Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.05_National_6_29_2020
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government‐approved location, at no additional cost to government.
106 - Acceptance of Work 106.01_National_7_18_2017
Delete Subsection 106.01 and replace with the following:
106.01 Conformity with Contract Requirements.
Follow the requirements of FAR Clause 52.246‐12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross‐sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project.
When the Government tests work, copies of test reports are furnished to the Contractor upon request.
Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive.
The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work;
providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
1. Sampling method;
2. Number of samples;
3. Sample transport;
4. Test procedures;
5. Testing laboratories;
6. Reporting;
7. Estimated time and costs; and
8. Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the
Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non‐conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
1. Have the work accepted at a reduced price; or
2. Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.02_National_11_9_2016
Delete Subsection 106.02 and replace with the following:
106.02 Visual Inspection.
Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.
107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017
Delete Subsection 107.05.
Delete Subsection 107.05.
108 - Prosecution and Progress 108.00_National_11_9_2016
Delete Section 108 in its entirety.
Delete Section 108.
109 - Measurement and Payment 109.00_National_11_9_2016
Delete Subsections 109.06, 109.07, 109.08, and 109.09:
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.01_National_2_22_2019
Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:
109.01 Measurement of Work.
Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement
Subsection of the section controlling the work being performed. Table 109‐1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.
Table 109‐1
Decimal Accuracy of Quantities for Final Payment
Pay Item Level of Precision Linear Foot 1
Exception--Timber, Steel, and concrete Piles 0.1 Station 0.1 Mile 0.01 Square Foot 0.1 Square Yard 0.1 Each 1 Acre 0.01 Gallon 1 M-Gals. 0.1 Cubic Yard 1
Exception--Structure Excavation; Sheathing Materials; Bedding, Bed Course, and Backfill Materials; Gabions;
0.1
Exception--Concrete; Masonry 0.01 Pound 1 Ton 0.1
Exception--Calcium Chloride;
Sodium Chloride; Hydrated Lime;
Bituminous Materials; Pavements;
Bed Course Materials
0.01
Hour 0.1
MFBM 0.01
Station Yard 1 Cubic Yard Mile 1 Ton Mile 1
109.02_National_11_9_2016
Add the following sentence to Subsection 109.02(b):
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
109.03_National_11_1_2016
Add the following to Subsection 109.03(c):
109.03 Weighing Procedures and Devices.
(c) Project weighing system.
For aggregates weighed for payment, adjust scale weights of material to deduct the daily average moisture content in excess of 2 percentage points over optimum moisture as determined by
AASHTO T 99 or the designated compaction method. If moisture determination is necessary, determine the daily average moisture content in accordance with AASHTO T 255, from not less than three representative samples of aggregate taken at random intervals each day that aggregate is being weighed.
Manual scales may be used if approved in writing by the CO and if the method of weighing meets all other contract requirements.
117 – Spot Premix Patching, Paved Surfaces
117.01 Maintenance Requirements
Work under this activity includes using hot mix‐cold laid asphaltic concrete material for patching, depressions, potholes, edges, upheavals, and other potentially detrimental or hazardous paved surface conditions as marked on the ground by the Contracting Officer's Representative or Inspector. This work shall be performed in accordance with procedures outlined in the Asphalt Institute's Manual Series No.
16 (MS‐16) entitled "Asphalt in Pavement Maintenance." Material requirements are given in Section 250‐C of the Technical Specifications. Skin patching will not be allowed unless specifically authorized by the Contracting Officer's Representative.
117.02 Material ‐Hot Mix‐Cold Laid Asphaltic Concrete Pavement
The paving mixture shall consist of a uniform mixture of coarse aggregate, fine aggregate and asphaltic material as described by the Texas Highway Department as "Hot Mix‐Cold Laid Asphaltic Concrete Pavement", Type "D" (Fine Graded Surfaced Course).
Type "D" (Fine Graded Surface Course) Grading Requirements:
Percent aggregate Passing by weight or Volume ½ inch 3/8 inch .................................. 85 to 100 No. 4 ..................................... 50 to 70 No. 10 .................................... 32 to 42 No. 40 .................................... 11 to 26 No. 80 .................................... 4 to 14 No. 200 .................................. 1 to 6 VMA & mass % min
The asphaltic material shall form from 4 to 8 percent of the mixture by weight or from 9 to 19 percent of the mixture by volume.
117.03 Method of Measurement
Hot mix‐cold laid asphaltic material shall be measured by the metric ton as indicated in the bid schedule.
Measurement shall be to the nearest one‐tenth ton based on weight tickets from state approved scales, furnished by the Contractor and showing material type, source, gross, tare, and net weights. Preparation of defected area, disposal of waste, and liquid asphalt will not be measured for payment but will be subsidiary to the patching activity.
117.04 Basis of Payment
Payment shall be made for all work of this activity, inspected and accepted, in accordance with the following pay item and the bid unit price.
Pay Item Description Pay Unit 117(01) Spot Premix Patching, Paved Surfaces Ton
155 - Schedules for Construction Contracts 155.00_National_11_9_2016
Delete Section 155 in its entirety.
Delete Section 155.
213 - Subgrade Stabilization 213.05_National_11_2_2016
Delete the second paragraph in Subsection 213.05 and replace with the following:
213.05 General.
Prepare the subgrade according to Subsection 303.05. Scarify or pulverize the subgrade to the required depth. Adequately blend the material to produce a homogeneous mixture within 2 percent of the optimum moisture content.
301 - Untreated Aggregate Courses 301.03_National_7_17_2017
Add the following to Subsection 301.03:
301.03 General.
Written approval of the roadbed is required before placing aggregate.
For pit run or grid‐rolled material, furnish material smaller than the maximum size, no gradation will be required otherwise. After processing on the road, remove all oversize material from the road and dispose as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpile according to Section
314.
301.05_National_7_17_2017
Delete Subsection 301.05 and replace with the following:
301.05 Compacting.
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.
Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
(a) Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
(b) Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
(c) Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
(d) Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
(e) Compaction E. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
303 - Road Reconditioning 303.07_National_7_18_2017
Add the following to Subsection 303.07:
303.07 Roadway Reconditioning.
Remove cattleguard decks. Clean the deck and the area beneath the cattleguard of soil and other material to the bottom of the original foundation over the entire width of the installation. Dispose of waste at designated sites or according to Subsection 204.14. Reinstall the cattleguard deck.
411 - Asphalt Prime Coat 411.05_National_7_17_2017
Delete Subsection 411.05(d) and replace with the following:
411.05 Weather Limitations.
(d) Weather is not forecasted to be foggy or rainy 24 hours following application.
412 - Asphalt Tack Coat 412.05_National_11_4_2016
Delete Subsection 412.05(b) and replace with the following:
412.05 Weather Limitations.
(b) Ambient air temperature is above 40 °F (5 °C) and rising; and
413 - Asphalt Pavement Milling 413.00_National_7_17_2017
Add the following to Subsection 413.01:
413.01 Description.
This work also includes cutting asphalt pavement.
Make the following changes to Subsection 413.03:
413.03 Milling.
Add the following to the end of the first paragraph:
Prior to milling, cut existing asphalt pavement at the locations and to the extent shown on the plans.
Cut the asphalt pavement to form a vertical face in unfractured asphalt surfacing.
Delete the first sentence of paragraph five and replace with the following:
Remove and completely recover all loose milled material.
Delete the second paragraph of Subsection 413.05and replace with the following:
413.05 Measurement.
Do not measure asphalt pavement milling or asphalt pavement cutting.
Delete the first sentence of Subsection 413.06 and replace with the following:
413.06 Payment.
Payment is indirect to Section 403 pay items listed in the Schedule of Items.