Book 2 of 2 - Front and Specs.pdf

PDF 1 MB Posted

Attached to
Invitation to Bid - Westport Road Improvement Project
Solicitation number
S-C00040-00018390
Issued by
Clackamas County, Oregon

About this file

This document is Book 2 of 2 - Front and Specs for the Westport Road Improvement Project, issued by Clatsop County Public Works in Oregon. The project encompasses construction of a new roadway extension approximately 1,250 feet in length connecting Highway 30 to Westport Ferry, along with approximately 1,900 feet of widening on Highway 30 to construct a westbound left turn lane for the new roadway. The scope also includes minor improvements to the existing Westport Road intersection with Highway 30. The specifications document establishes the technical requirements, construction standards, and detailed requirements that bidders must follow in preparing their proposals and executing the work. Bidders are directed to the Clatsop County website at www.clatsopcounty.gov under the Jobs & Bids/RFPs section to access the complete Invitation to Bid documents and project details necessary for bid preparation and submission.

The specifications contained within this document provide the engineering and construction standards governing all materials, workmanship, testing, and quality assurance requirements for the roadway construction and improvement work. This document serves as a binding specification document that will be incorporated into the contract with the successful bidder and establishes the baseline requirements for project performance and completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE ISSUED: November 9, 2026

BOOK 2 OF 2

OF THE BID DOCUMENTS FOR:

WESTPORT ROAD IMPROVEMENT

PROJECT

TYPE OF WORK: GRADING, PAVING, DRAINAGE, GUARD RAIL, ILLUMINATION,

SIGNING, STRIPING, SIGNALS, AND ROADSIDE DEVELOPMENT

PROJECT NUMBER: P10383

A CLATSOP COUNTY

PUBLIC WORKS

PUBLIC IMPROVEMENT PROJECT

BOOK 2 OF 2

OF THE BID DOCUMENTS

FOR:

WESTPORT ROAD IMPROVEMENT

PROJECT

PREPARED BY:

CLATSOP COUNTY

PUBLIC WORKS

1100 OLNEY AVE

ASTORIA, OR 97103

PROJECT NUMBER: P10383

DATE ISSUED: November 9, 2026

BOOK 2

TABLE OF CONTENTS

PROJECT INFORMATION ....................................................................................................... i

PROJECT CONTACTS ............................................................................................................ ii

PREVAILING WAGE RATES ................................................................................................. iii

NON-FIELD TESTED MATERIALS ....................................................................................... iv

SPECIAL PROVISIONS ........................................................................................................... v

ENGINEER OF RECORD CERTIFICATIONS

SPECIAL PROVISIONS

ATTACHMENTS:

A) ODOT ACCESS PERMIT

B) RAILROAD AGREEMENT

C) POWER COMPANY DRAWINGS

D) DEQ 401 WATER QUALITY CERTIFICATION APPROVAL

E) USACE NATIONWIDE PERMIT AUTHORIZATION

F) DSL REMOVAL-FILL PERMIT

Westport Road i Project Number P10383 Hwy 30 to Ferry Terminal

PROJECT INFORMATION

WESTPORT ROAD

Improvement Project

WORK TO BE DONE

The Work to be done under this Contract consists of the following in Clatsop County:

1. All traffic control and protection and direction of traffic necessary for safety of motorists as required by the Oregon Manual on Uniform Traffic Control Devices.

2. WESTPORT BYPASS ROAD CONSTRUCTION

a. Construct approximately 1,250 feet of new roadway with roadside drainage, guardrail, surcharge grading, and constructed wetlands as shown in the construction plans.

3. HWY 30 WIDENING

a. Widen Hwy 30 to the north and restripe approximately 1,900’ to construct a left turn lane into the realigned Westport Road. Install storm drainage and guardrail as shown on the construction plans.

4. HWY 30 AT EXISTING WESTPORT ROAD

a. Construct concrete curb return, sidewalk connection and pedestrian

ADA ramp, reconstruct driveways, and railroad crossing closure.

5. Perform additional and Incidental Work as called for by the Specifications and Plans.

CLASS OF WORK

The Class of Work for this Project is: Earthwork and Paving

APPLICABLE SPECIFICATIONS

The Specifications that are applicable to the Work on this Project is the 2024 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions. All Sections in Part 00100 apply, whether or not modified or referenced in the Special Provisions.

All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.

Westport Road ii Project Number P10383

PROJECT CONTACTS

Questions regarding Bid Documents should be directed to: Terry Hendryx or Dean Keranen at Clatsop County Public Works, 1100 Olney Avenue, Astoria, Oregon 97103, Phone: 503-325-8631 Fax: 503-325-9312. Email addresses are dkeranen@clatsopcounty.gov and thendryx@clatsopcounty.gov.

Westport Road iii Project Number P10383

PREVAILING WAGE RATES

Prevailing Wage Rates are hereby incorporated into these Specifications by reference, and the text for these publications are available on BOLI’s website at:

https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx

The applicable publications are:

• October 5, 2024 – Definitions of Covered Occupations for Public Works Contracts

• July 5, 2026 – Prevailing Wage Rates for Public Works Contracts

• July 5, 2026 – Apprenticeship Rates

You may also request a copy of the rules by calling the Bureau of Labor and Industries directly.

https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx

Westport Road iv Project Number P10383

NON-FIELD TESTED MATERIALS

Non-Field Tested Materials are hereby incorporated into these specifications by reference and are available by visiting the Oregon Department of Transportation website at:

http://www.oregon.gov/ODOT/Construction/Pages/Structure-Services.aspx http://www.oregon.gov/ODOT/Construction/Pages/Structure-Services.aspx

Westport Road v Project Number P10383

SPECIAL PROVISIONS

TABLE OF CONTENTS FOR SPECIAL PROVISIONS

RAILROAD CONTRACTOR REQUIREMENTS

SECTION 00110 - ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND

DEFINITIONS

SECTION 00120 - BIDDING REQUIREMENTS AND PROCEDURES

SECTION 00130 - AWARD AND EXECUTION OF CONTRACT

SECTION 00140 - SCOPE OF WORK

SECTION 00150 - CONTROL OF WORK

SECTION 00160 - SOURCE OF MATERIALS

SECTION 00165 - QUALITY OF MATERIALS

SECTION 00170 - LEGAL RELATIONS AND RESPONSIBILITIES

SECTION 00180 - PROSECUTION AND PROGRESS

SECTION 00190 - MEASUREMENT OF PAY QUANTITIES

SECTION 00195 - PAYMENT

SECTION 00196 - PAYMENT FOR EXTRA WORK

SECTION 00197 - PAYMENT FOR FORCE ACCOUNT WORK

SECTION 00199 - DISAGREEMENTS, PROTESTS, AND CLAIMS

SECTION 00210 - MOBILIZATION

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC

CONTROL

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

SECTION 00225 - TEMPORARY PAVEMENT MARKINGS

SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING

SECTION 00236 - AGENCY PROVIDED DISPOSAL SITES

SECTION 00280 - EROSION AND SEDIMENT CONTROL

SECTION 00290 - ENVIRONMENTAL PROTECTION

SECTION 00305 - CONSTRUCTION SURVEY WORK

SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

SECTION 00320 - CLEARING AND GRUBBING

SECTION 00330 - EARTHWORK

SECTION 00331 - SUBGRADE STABILIZATION

SECTION 00350 - GEOSYNTHETIC INSTALLATION

SECTION 00390 - RIPRAP PROTECTION

SECTION 00405 - TRENCH EXCAVATION, BEDDING, AND BACKFILL

SECTION 00406 - TUNNELING, BORING, AND JACKING

SECTION 00415 - VIDEO PIPE INSPECTION

SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION

PIPE

SECTION 00460 - PAVED CULVERT END SLOPES

SECTION 00470 - MANHOLES, CATCH BASINS, AND INLETS

SECTION 00480 - DRAINAGE CURBS

SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES

SECTION 00495 - TRENCH RESURFACING

SECTION 00620 - COLD PLANE PAVEMENT REMOVAL

SECTION 00640 - AGGREGATE BASE AND SHOULDERS

SECTION 00730 - EMULSIFIED ASPHALT TACK COAT

SECTION 00738 - SAFETY EDGE

SECTION 00744 - ASPHALT CONCRETE PAVEMENT

SECTION 00759 - MISCELLANEOUS PORTLAND CEMENT CONCRETE

STRUCTURES

SECTION 00810 - METAL GUARDRAIL

SECTION 00850 - COMMON PROVISIONS FOR PAVEMENT MARKINGS

SECTION 00855 - PAVEMENT MARKERS

SECTION 00857 - RUMBLE STRIPS

SECTION 00865 - LONGITUDINAL PAVEMENT MARKINGS - DURABLE

SECTION 00867 - TRANSVERSE PAVEMENT MARKINGS - LEGENDS AND

BARS

SECTION 00920 - SIGN SUPPORT FOOTINGS

SECTION 00930 - METAL SIGN SUPPORTS

SECTION 00940 - SIGNS

SECTION 00942 - PERMANENT BARRICADES

SECTION 00960 - COMMON PROVISIONS FOR ELECTRICAL SYSTEMS

SECTION 00962 - METAL ILLUMINATION AND TRAFFIC SIGNAL SUPPORTS

SECTION 00970 - HIGHWAY ILLUMINATION

SECTION 01010 - STORMWATER CONTROL, WATER QUALITY STRUCTURES

SECTION 01012 - STORMWATER CONTROL, WATER QUALITY

BIOFILTRATION SWALE

SECTION 01030 - SEEDING

SECTION 01040 - PLANTING

SECTION 01050 - FENCES

SECTION 02001 - CONCRETE

SECTION 02320 - GEOSYNTHETICS

PORTLAND & WESTERN RAILROAD COMPANY

Contractors Access/Occupancy on Railroad Property

The following Portland & Western Railroad Company agreements and exhibits are included in this Project for information and reference only. The actual Contractors Access/Occupancy on Railroad Property will be provided and executed by the Portland & Western Railroad Company.

The Contractor shall obtain all necessary permits and licenses and pay all fees and obtain a fully executed copy of the railway agreement according to 00170.01(e).

In addition, when Railroad flagger services are required, the Agency will pay for the services according to 00170.01(e).

Westport Road Improvement Project

OREGON DEPARTMENT OF TRANSPORTATION

FOR

Grading, Paving, Drainage, Guard Rail, Illumination, Signing, Striping, Signals, and Roadside Development

Clatsop County

PROFESSIONAL OF RECORD CERTIFICATION:

Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project.. Modified Special Provisions were prepared by me or under my supervision.

Section(s): All sections except 00100-00199, 00220, 00221, 00222, 00223, 00224, 00225, 00228, 00850, 00855, 00857, 00865, 00867, 00920, 00930, 00940, 00942, 00960, 00962, & 00970.

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

OREGON DEPARTMENT OF TRANSPORTATION

FOR

Grading, Paving, Drainage, Guard Rail, Illumination, Signing, Striping, Signals, and Roadside Development

Clatsop County

PROFESSIONAL OF RECORD CERTIFICATION:

Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project.. Modified Special Provisions were prepared by me or under my supervision.

Section(s): 00220, 00221, 00222, 00223, 00224, 00225, 00228, 00850, 00855, 00857, 00865, 00867, 00920, 00930, 00940, 00942, 00960, 00962, & 00970.

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

APPLICABLE SPECIFICATIONS

The Specifications that are applicable to the Work on this Project is the 2024 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions. All Sections in Part 00100 apply, whether or not modified or referenced in the Special Provisions.

All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.

CLASS OF PROJECT

This is a County Project.

SECTION 00110 - ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND

DEFINITIONS

Comply with Section 00110 of the Standard Specifications modified as follows:

00110.00 Organization of Specifications: - Add the following to the end of this subsection:

Certain Sections contain statements under payment subsections to the effect that payment will be made at the contract amounts for the following items. It is intended that payment will be made only for those items listed in the Bid Schedule for a particular project.

00110.05(e) Reference to Websites - Add the following bullet list to the end of this subsection:

• Commission - Delete definition and replace with "Clatsop County Board of Commissioners"

• Add: Commission Services Office - Clatsop County Public Works Department.

• Add: Notice to Contractors-Advertisement for Bids, or Invitation to Bid.

• Add: County - Clatsop County, including employees of the County authorized to administer this contract.

• Engineer - Delete definition and replace with "Clatsop County Engineer and its authorized representatives, acting either directly or indirectly as authorized agents of the County".

Add: Proposal Booklet -Bid forms section of the "Proposal and Special Provisions" document prepared by the County, which includes required information regarding proposals. A separate booklet is not prepared for proposals.

SECTION 00120 - BIDDING REQUIREMENTS AND PROCEDURES

Comply with Section 00120 of the Standard Specifications modified as follows:

00120.00 Prequalification of Bidders – Delete this subsection

00120.01 General Bidding Requirements - Delete this subsection and substitute the following:

Bidders may obtain Bids by paper and/or through the internet (electronic) or both.

Bids must be submitted with paper only.

00120.05 Request for Plans, Special Provisions, and Bid Booklets - Delete this subsection and substitute the following:

Upon request, the Clatsop County Public Works Department will provide prospective bidders with the "Proposal and Special Provisions" and plans for the advertised project. The Oregon Standard Specifications For Construction – 2024 (also a part of these specifications by reference) may be reviewed in the office of the Public Works Department and may be purchased at the Oregon State Department of Transportation Building Plan Center in Salem.

00120.10 Bid Booklet - Delete this subsection.

00120.16 Material, Equipment, and Method Substitutions - Replace this subsection, except for the subsection number and title, with the following:

Bidders shall not submit proposals for substitute Materials or services. Proposals for substituting Materials or services will only be accepted after the Agency has executed the Contract. Substitution after Contract execution is specified in 00180.31(b), 00180.31(c), and 00180.31(d).

00120.40(a) General - Delete this subsection and substitute the following:

Do not alter the bid documents except to complete the certification and statements as required and to insert the bid bond. When the bidder's authorized representative has signed the proposal, the bidder agrees to all certifications and statements contained within the contract documents. Entries in the proposal shall be in ink or typed. Signatures shall be in ink.

When the proposal is submitted, all documents in the proposal section, including a bid bond, shall be properly completed and bound together.

No electronic bis will be accepted.

00120.40(c)(2) – Delete this subsection

00120.40(f) – Replace the paragraph beginning “If no subcontracts subject to the above…” with the following paragraph:

If no subcontracts subject to the above disclosure requirements are anticipated, a Bidder shall so indicate by entering "NONE" or by filling in the appropriate check box.

For each Subcontractor listed, Bidders shall provide all requested information. Failure to submit a form or submission of a form that does not include the information required by ORS 279C.370 for each Subcontractor listed, specifically the name of each Subcontractor, the dollar amount of each subcontract and the category of Work that each Subcontractor will perform, will result in the rejection of the Bid. The Agency is not required to determine the accuracy or the completeness of the Subcontractor disclosure. See ORS 279C.370 and OAR 731-005-0420.

Replace both of the bullets that begin “Using the form provided on the Agency’s website…” with the following bullet:

• Using the form provided with the bid documents

Remove the paragraph and three bullets that start with “The Subcontractor Disclosure Form may be submitted for an electronic bid…”

00120.45 Submittal of Bids –

(a) Paper Bids – Delete and replace subsection with the following:

Paper bids may be submitted by mail, parcel delivery service to the offices and addresses, and at the times given in the Proposal Booklet. Submit paper bids in a sealed envelope provided by the bidder.

Paper bids submitted after the Bid closing time will not be opened and will be returned to the bidder.

(b) Electronic Bids – Delete this subsection

00120.50 Submitting Bids for More than One Contract – Delete this subsection.

00120.60 Revision or Withdrawal of Proposals - Delete this subsection and substitute:

(a) Paper Bids

A bidder may withdraw a proposal after it has been delivered to the County, if the bidder (or his agent) makes the request in person to the County office designated to open the bids before the time set for opening.

(b) Electronic Bids – Delete this subsection

00120.70 Rejection of Nonresponsive Bids - Add the following bullet to the end of the bullet list:

• The Agency determines that any Pay Item is significantly unbalanced to the potential detriment of the Agency.

00120.90 Disqualification of Bidders - Delete "Not been prequalified as required by 120.00."

SECTION 00130 - AWARD AND EXECUTION OF CONTRACT

Comply with Section 00130 of the Standard Specifications supplemented and/or modified as follows:

00130.00 Consideration of Bids - In the third paragraph change 30 calendar days to 60 days.

00130.15 Right to Protest Award – Delete this subsection and substitute ORS 279C.460.

00130.40(a) Performance and Payment Bonds - Delete this subsection and substitute ORS 279C.380.

00130.40(c) Workers’ Compensation - Delete this subsection and substitute the following:

Provide County with a Certificate of Insurance confirming coverage as required by 00170.61(a) and 00170.70(c).

00130.50(a) By the Bidder - In the first paragraph, delete "ODOT Procurement Office

- Construction Contracts Unit" and substitute "the place designated for receipt of bids".

00130.50(b) By the Agency - Delete "seven Calendar Days" and replace with "21 Calendar Days" and delete “legal sufficiency approval from the Attorney General” and substitute “Clatsop County Board of Commissioners”.

00130.70 Release of Bid Guaranties – Delete this subsection and substitute ORS 279C.385(3).

00130.90 Notice to Proceed - Delete this subsection.

SECTION 00140 - SCOPE OF WORK

Comply with Section 00140 of the Standard Specifications.

SECTION 00150 - CONTROL OF WORK

Comply with Section 00150 of the Standard Specifications modified as follows:

00150.15(b) Agency’s Responsibilities - Replace this subsection, except for the subsection number and title, with the following:

The Engineer will perform the Agency responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.5 (see Section 00305).

00150.15(c) Contractor’s Responsibilities - Replace this subsection, except for the subsection number and title, with the following:

The Contractor shall perform the Contractor responsibilities described in the Construction Surveying Manual for Contractors, Chapter 1.6 (see Section 00305).

The Contractor shall perform slope staking including intersections and set stakes defining limits for clearing which approximate Right-of-Way and easements.

00150.50(c) Contractor’s Responsibilities – Replace the bullet that begins “In addition to the notification required…” with the following bullet:

• In addition to the notification required in OAR 952-001-0090(7), notify the Engineer and the Utility as soon as the Contractor discovers any previously unknown Utility conflicts or issues. Contrary to the OAR, stop excavating until directed by the Engineer and allow the Utility a minimum of two weeks to relocate or resolve the previously unknown Utility issues; and

Add the following bullet to the end of the bullet list:

• Hold a Utility scheduling meeting and monthly Utility coordination meetings (see also 00180.42)

• The Contractor shall comply with ORS 757.542 to 757.557, Utility Regulation.

Add the following subsection:

00150.50(g) Utility Information (Anticipated Relocations):

The organizations list in Table 00150-2 may be adjusting Utilities within the limits of the Project during the period of the Contract with relocation Work estimated to be completed by the following dates and times:

Table 00150-2

Subsection Utility

Contact Person's Name, Address, Email, (and) Phone Number (and Work Order Number)

Estimated Completion

Date

00150.50(g)(1) Clatskanie

PUD (CPUD)

Kymber Hughes 495 E. Columbia River Highway Clatskanie, OR 97016 khughes@clatskaniepud.com 503-308-4604

6/1/2027

00150.50(g)(2) Lumen Jordan Connell 4501 NE Minnehaha St.

6/1/2027 mailto:khughes@clatskaniepud.com

Vancouver, WA 98661 Jordan.connell@lumen.com 564-888-2012

The Contractor shall contact the Engineer to view the approved utility relocation Plans.

The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project. Utilities may require an on-site observer, at no cost to the Contractor.

(1) (Clatskanie PUD) - "Power Supplier":

The Contractor shall notify the Power Supplier(s) in writing, with a copy to the Engineer, at least 14 Calendar Days before beginning Work within 10 feet of the power line(s).

The Contractor shall notify the Power Supplier in writing, with a copy to the Engineer, _24_ Calendar Days before the Contractor is scheduled to begin performing _Mass Grading_. After the Power Supplier receives the notification, the Contractor shall then allow the Power Supplier _24_ Calendar Days to schedule and complete the relocation and adjustment work before the Contractor begins performing _Mass Grading__.

(2) (Lumen) - "Telecommunication Utility":

The Contractor shall notify the Telecommunication Utility in writing, with a copy to the Engineer, at least 14 Calendar Days before beginning Work within 10 feet of the Telecommunication Utility facilities.

The Contractor shall notify the Telecommunication Utility in writing, with a copy to the Engineer, _24_ Calendar Days before the Contractor is scheduled to begin performing _Mass Grading__. After the Telecommunication Utility receives the notification, the Contractor shall then allow the Telecommunication Utility _24_ Calendar Days to schedule and complete the relocation and adjustment work before the Contractor begins performing __Mass Grading__.

00150.95 Final Acceptance - Add the following:

The Contractor shall be required to remedy or correct any defects in the completed construction that has been a part of this contract that may appear within two (2) years from the date of completion of the project. The Contractor's acceptance of the supplemented final payment shall in no way relieve him of the responsibility of faulty workmanship furnished by them. The County shall with a reasonable promptness give notice to the Contractor of defects noted. The Public Works Director shall decide all questions arising thereto subject to arbitration.

mailto:Jordan.connell@lumen.com

SECTION 00160 - SOURCE OF MATERIALS

Comply with Section 00160 of the Standard Specifications modified as follows:

00160.20(a) Buy America - Replace this subsection, except for the subsection number and title, with the following:

Buy America for iron and steel does not apply to this Contract.

00160.20(d) Build America Buy America Act Requirements – Replace this subsection, except for the subsection number and title, with the following:

The provisions of the Build America Buy America Act do not apply to this locally funded project.

SECTION 00165 - QUALITY OF MATERIALS

Comply with Section 00165 of the Standard Specifications modified as follows:

00165.03 Testing by Agency – Replace this subsection with the following:

Any check-tests or review tests to be performed by the Agency will be sent to a certified testing firm of their choice. The results of the tests will be made available to the contractor.

00165.40 Statistical Analysis - Delete this subsection.

00165.50 Statistical Acceptance Sampling and Testing - Delete this subsection.

00165.70(c) Contractor Request for Testing Assistance - Delete this subsection.

SECTION 00170 - LEGAL RELATIONS AND RESPONSIBILITIES

Comply with Section 00170 of the Standard Specifications modified as follows:

Add the following subsection:

00170.01(e) Railroads - An agreement between the Contractor and the Railroad to Work near or within Railroad property is required for this Project. A copy of the PNWR Contractor’s Right of Entry Public Projects and corresponding requirements is included near the front of this Special Provision booklet. The Railroad agreement and requirements are subject to change by the Railroad. The Railroad will provide the actual agreement and requirements for execution. The Contractor shall obtain all necessary permits and licenses and pay all fees. The Contractor shall obtain a fully executed copy of the agreement and requirements between the Contractor and the

Railroad and provide a copy of it to the Engineer before beginning Work near or within the Railroad property or Right-of-Way.

The Railroad contact for this Project is:

Dennis Hannahs Permit Specialist Portland & Western Railroad, Inc.

503-508-7440 dhannahs@gwrr.com

The USDOT Number for this Project is: #938954R Railroad company owning the track: Genesee & Wyoming Railroad Operating Railroad company at track: Portland & Western Railroad Railroad MP: M.P. 71.27 to 71.42 Railroad Subdivision: Astoria Branch City: Westport County: Clatsop County

When Railroad flagger services are required, the flagging services will be considered incidental to the work being performed and no separate payment or reimbursement will be made.

Add the following subsection:

00170.02 Permits, Licenses and Taxes - Add the following:

Contractor will be working as an independent contractor and will be responsible for any federal or state taxes applicable to services rendered by Contractor. Contractor will be responsible to provide for their employees and agents any benefits as a result of payments pursuant to this agreement for Federal Social Security, Unemployment Insurance or Public Employee's Retirement System Benefits.

00170.61(a) Workers’ Compensation - Replace this subsection, except for the subsection number and title, with the following:

The Contractor, its Subcontractors, if any, and all employers working under this contract are subject employers under the Oregon Worker's Compensation Law and shall comply with ORS 656.017, which requires them to provide worker's compensation coverage for all their subject workers.

The Contractor is a sole proprietor or a partner or is an insured employer for purposes of the Oregon Worker's Compensation Law (ORS Chapter 656) and is solely liable for any worker's compensation coverage under this Contract. Contractor agrees that Contractor and other persons retained by Contractor to perform work under this Contract shall be insured according to ORS 656.407 prior to commencement of work under this contract, and that Contractor and such persons shall remain so insured during the term of this Contract. The Contractor shall also comply with the Unemployment Compensation Act of the State of Oregon. The Contractor shall provide the County, before commencing work, a certificate of insurance showing protection for its workers under the Workers' Compensation Act and registration with the State Unemployment Compensation Commission.

00170.65(b)(1) Minimum Wage Rates – Replace the paragraph that begins "The Bureau of Labor and Industries (BOLI) …" with the following paragraph:

The Bureau of Labor and Industries (BOLI) determines and publishes the existing State prevailing wage rates in the publication Prevailing Wage Rates for Public Works Contracts. The Contractor shall pay workers not less than the specified minimum hourly wage rate according to ORS 279C.838 and ORS 279C.840, and shall include this requirement in all subcontracts.

00170.70(a) Insurance Coverages -

Add the following to the end of this subsection:

The following insurance coverages and dollar amounts are required pursuant to this subsection:

Insurance Combined Single Limit Annual Aggregate Coverages per Occurrence Limit

Commercial General Liability $2,000,000 $5,000,000

Commercial Automobile Liability $1,000,000 (aggregate limit not required)

00170.70(d) Additional Insured - Replace the paragraph that begins "The liability insurance coverages of 00170.70(a)…" with the following paragraph:

The liability insurance coverages of 00170.70(a) shall include an Additional Insured Endorsement endorsing “Clatsop County, its agents, officers, elected officials and employees” as Additional Insureds, but only with respect to the Contractor’s activities to be performed under the Contract. Coverage shall be primary and non-contributory with any other insurance and self-insurance. The liability coverages of 00170.70(a) that are permitted by the Agency to be obtained by an appropriate Subcontractor shall include all of the foregoing as Additional Insureds and shall also include the Contractor and its officers and employees as Additional Insureds.

Add the following paragraph and bullet to the end of this subsection:

Add the following as Additional Insureds under the Contract:

• State of Oregon, the Oregon Transportation Commission and the Department of Transportation, and their respective officers, members, agents, and employees

• Clatsop County and its officers, agents, and employees

• Clatsop County Board of Commissioners

• _______(Consultant)_______________________Kittelson & Associates, Inc

00170.70(g) Certificate(s) of Insurance - Replace the bullet that begins “List the “State of Oregon, the Oregon Transportation…” with the following bullet:

• List "Clatsop County, its agents, officers, elected officials and employees" as a

Certificate holder and endorse as an Additional Insured;

00170.72 Indemnity/Hold Harmless - Add the following paragraph and bullets to the end of this subsection:

Extend indemnity, defense and hold harmless to the Agency and the following:

• State of Oregon, the Oregon Transportation Commission and the Department of Transportation, and their respective officers, members, agents, and employees

• Kittelson & Associates, Inc.

00170.80(c) Responsibility for Damage to Work Caused by Public Traffic - Replace the paragraph that begins, "If the Contractor disagrees…" with the following:

If the Contractor disagrees with the Engineer's findings, the Contractor may request a Principal Engineer level review according to 00199.40(b).

SECTION 00180 - PROSECUTION AND PROGRESS

Comply with Section 00180 of the Standard Specifications modified as follows:

00180.20(c) Rental of Operated Equipment - Delete this subsection.

00180.21(a) General – Delete the first 3 paragraphs and add the following:

Unless otherwise provided in the Contract, the Contractor shall not assign, sell, dispose of, or transfer rights, nor delegate duties under the contract, either in whole or in part, without the Agency’s prior written consent. Unless otherwise agreed by the Agency in writing, such consent shall not relieve the Contractor of any obligations under the Contract. Any assignee or transferee shall be considered the agent of the Contractor and be bound to abide by all provisions of the Contract. If the Agency consents in writing to an assignment, sale, disposal or transfer of the Contractor’s rights or delegation of Contractor’s duties, the Contractor and its surety, if any, shall remain liable to the Agency for complete performance of the Contract as if no such assignment, sale, disposal, transfer or delegation has occurred unless the Agency otherwise agrees in writing.

Add the following subsection:

00180.40(c) Specific Limitations - Limitations of operations specified in these Special Provisions include, but are not limited to, the following:

Limitations Subsection

Cooperation with Utilities .................................. 00150.50 Railways ....................................................... 00170.01(e) Contract Time ............................................... 00180.50(h) Maintenance Under Traffic ............................... 00620.43 Opening Sections to Traffic ............................... 00744.51

The Contractor shall be aware of and subject to schedule limitations in the Standard Specifications that are not listed in this subsection.

00180.41 Project Work Schedules -

The Contractor shall submit a project schedule to the County.

The project schedules shall take into account the orderly, timely, and efficient prosecution of the work. The project schedules shall indicate the Contractor's plan of prosecution of the work in sufficient detail to enable both the Contractor and the County to plan, coordinate, appraise, document, and control their respective contract responsibilities.

When completed, the Contractor's approved project schedule shall represent the Contractor's own plans for the project. It shall be the Contractor's responsibility to ensure that all of the work is described in the project schedule and that it represents the sequence and time planned for the work. Review of this and subsequent schedules by the Engineer shall not relieve the Contractor of responsibility for timely and efficient execution of the contract. Slack or float time as expressed in the project schedule does not exist for the exclusive use of either party to the contract and belongs to the project.

Project reporting - The Contractor shall review the project schedule and progress with the Engineer periodically. Upon the request of the Engineer or when the Contractor's approved project schedule no longer represents the contractor's own plans or expected time for the work, the project schedule shall be updated and a joint progress meeting shall be held between the Engineer and the Contractor. At this meeting, project events and changes will be reviewed for their effect on the Contractor's approved project schedule. After any necessary action has been agreed upon, the required changes will be made to the project schedule.

Project schedule costs - There will be no separate payment for developing, furnishing, monitoring, or updating the project schedules as payment therefore will be included in payment for one or another of the listed bid items.

The Contractor's failure to provide the schedules, schedule information, progress reports, or schedule updates at the times required herein shall cause progress payments under this contract to be suspended until the required data is provided to the Engineer unless the Engineer waives the provisions of this subsection in writing.

00180.42 Preconstruction Conference - Replace this subsection, except for the subsection number and title, with the following:

Before any Work is performed under the Contract and within 15 Calendar Days of the Notice to Proceed, unless otherwise approved in writing by the Engineer, meet with the Agency for a preconstruction conference at a time mutually agreed upon with the Agency.

Submit the following during the preconstruction conference unless otherwise directed:

• Project work schedule (see 00180.41)

• Traffic control plans (see 00221.06)

• Erosion control plan (see 00280.00)

• Complete list of subcontractors

• List of utilities affected by the work (see 00150.50(c))

• Submit off-site disposal locations (see 00290.20(c)(3)(f))

00180.50(h) Contract Time - There is one Contract Time on this Project as follows:

(X) The Contractor shall complete all Work to be done under the Contract not later than June 30, 2028.

00180.85(b)(1) Single Contract Time - Replace this subsection, except for the subsection number and title with the following:

The liquidated damages for failure to complete the Work on time required by 00180.50(h) will be $500 per Calendar Day *.

* Calendar Day amounts are applicable when the Contract time is expressed on the Calendar Day or fixed date basis.

Add the following subsection:

00180.85(c) Lane Closures - Lane closures beyond the limits specified will inconvenience the traveling public and will be a cost to the Agency.

It is impractical to determine the actual damages the Agency will sustain in the event Traffic Lanes are closed beyond the limits listed in 00220.40. Therefore, the Contractor shall pay to the Agency, not as a penalty, but as liquidated damages, $500 per 15 minutes, or for a portion of 15 minutes, per lane, for any lane closure beyond the limits listed in 00220.40(e) (or 00220.40(f)).

The Engineer will determine when it is safe to reopen lanes to traffic. Assessment of liquidated damages will stop when all lanes have been safely reopened. Any liquidated damages assessed under these provisions will be in addition to those listed in 00180.85(b).

Add the following subsection:

00180.85(e) Traffic Delays Beyond 20 Minutes - Stopping or holding vehicles beyond the limits specified will inconvenience the traveling public and will be a cost to the Agency.

It is impractical to determine the actual damages the Agency will sustain in the event traffic is stopped or held longer than the 20-minute limit listed in 00220.02. Therefore, the Contractor shall pay to the Agency, not as a penalty, but as liquidated damages, $500 per 20 minutes, or for a portion of 20 minutes, for stopping or holding traffic longer than 20 minutes.

Assessment of liquidated damages will stop when the Engineer determines that traffic is no longer stopped or held beyond the 20-minute limit. Any liquidated damages assessed under these provisions will be in addition to those listed in 00180.85(b).

SECTION 00190 - MEASUREMENT OF PAY QUANTITIES

Comply with Section 00190 of the Standard Specifications modified as follows:

00190.20(f)(2) Scale Without Automatic Printer - Replace the paragraph that begins "The Contractor shall inform…" with the following paragraph:

If the scales require manual entry of gross weight information, the Agency may periodically have a representative weigh witness at the scales to observe the weighing procedures. The Contractor shall inform the Engineer of their intent to use a scale without an automatic printer at least 3 working days before weighing begins or before the Contractor changes to a scale that does not have an automatic printer.

The Contractor shall pay costs for the weigh witness. The hourly cost of the weigh witness will be as stated in the Special Provisions. In addition, the Engineer may periodically check the weight for a load of Materials by directing the haul vehicle to reweigh on a different scale that has been inspected and certified according to 00190.20(b) and 00190.20(d).

Add the following paragraph after the paragraph that begins " If the scales require manual entry…":

Pay costs for the weigh witness at $35.00 per hour.

00190.20(g) Agency-Provided Weigh Technician – Replace this section with the following:

Agency will not provide a Weigh Technician.

SECTION 00195 - PAYMENT

Comply with Section 00195 of the Standard Specifications modified as follows:

00195.10 Payment For Changes in Materials Costs - Replace this subsection with the following subsection:

00195.10 Payment For Changes in Materials Costs - Material Cost Escalation/De- Escalation clause are not applicable to this project.

00195.50 Progress Payments and Retained Amounts - Delete the first sentence and add the following:

At the end of each month the contractor shall submit to the Engineer, an application for partial payment. The County shall make payments on account of the contract, as provided, within thirty (30) days after receipt of the Engineer’s approval of the contractor’s application for partial payment.

00195.50(b) Retainage - Replace this subsection, except for the subsection number and title, with the following:

The amount to be retained from progress payments shall be 5% of the value of Work accomplished, and shall be retained in one of the forms specified in 00195.50(c). The Agency will withhold retainage from all Force Account and Change Order Work.

As provided in 00170.65(b)(3) in addition to any retainage, a withholding of 25% of amounts earned will be withheld and released according to ORS279C.845 when the Contractor fails to file the certified statements required in ORS279C.845, FHWA Form 1273, and 00170.65.

00195.50(c) Forms of Retainage - Replace this subsection, except for the subsection number and title, with the following:

Forms of acceptable retainage are specified below in Subsections (1) through (4).

Select retainage option at the time of execution of contract using the form Selection of Retainage Option in Book 1 of the Bid Documents.

(1) Clatsop County will withhold payment and invest the retainage with the County investment portfolio as the retainage accumulates. Interest on the account will accrue to the contractor. Funds in the account will be released to the Contractor as part of final payment.

(2) Cash, Alternate A - The Contractor will set up an interest-bearing account in a commercial bank or trust company in Oregon in the name of Agency. The Agency will place five percent (5%) retainage, withheld from each progress payment, into the interest-earning account. Funds in the account will be under the control of Agency and will be released to the contractor as part of final payment.

(3) Cash, Alternate B - Before the first progress payment is made, the Contractor will make cash deposit in the amount greater than or equal to five percent (5%) of contract amount in the Agency’s investment portfolio in lieu of retainage. Interest on the account will accrue to the Contractor. Funds in the account will be released to the Contractor as part of final payment.

(4) Bonds and Securities - In accordance with ORS 279C.560, unless the Agency finds in writing that accepting a bond, security or other instrument poses an extraordinary risk that is not typically associated with the bond, security or other instrument, the Agency will approve the Contractor's written request to deposit bonds, securities or other instruments with the Agency or in a custodial account or other account satisfactory to the Agency with an approved bank or trust company, to be held instead of cash retainage for the benefit of the Agency. In such event, the Agency will reduce the cash retainage by an amount equal to the value of the bonds, securities and other instruments. Interest or earnings on the bonds, securities and other instruments shall accrue to the Contractor.

Bonds, securities and other instruments deposited instead of cash retainage shall be assigned to or made payable to the Agency.

Acceptable Bonds and Securities to be Held in Lieu of Retainage:

1. Bills, certificates, notes, bonds or other obligations of the United States, its agencies or its wholly-owned corporations. Indebtedness of the Federal National Mortgage Association.

2. Indebtedness of the Federal National Mortgage Association.

3. General obligation bonds of the State of Oregon or a political subdivision of the

State of Oregon.

4. Irrevocable letters of credit issued by an insured institution, as defined in ORS 706.008.

The Contractor shall execute and provide such documentation and instructions respecting the bonds, securities and other instruments as the Agency may require to protect its interests. When the Engineer determines that all requirements for the protection of the Agency's interest have been fulfilled, the bonds and securities deposited instead of cash retainage will be released to the Contractor.

00195.50(d) Release of Retainage - Replace this subsection with the following:

00195.50(d) Release and Reduction of Retainage - As the Work progresses, the amounts to be retained under (b) of this Subsection are subject to reduction in the Engineer's sole discretion. Retainage reductions will be considered only as follows:

• When the Work is 97.5% or more completed, the Engineer may, without a request from the Contractor, reduce the retained amount to 100% of the value of the Work remaining. The value of the remaining work will be determined by the Engineer and it may or may not equal the Contractor’s bid items value for this work.

• A Subcontractor may request release of retainage for their portion work, when the Subcontractor has satisfactorily completed all of their work. The Contractor shall request reduction of retainage in the amount withheld for the Subcontractor’s Work after certifying to the Agency that the Subcontractor’s Work is complete, and that all contractual requirements pertaining to the Subcontractor’s Work have been satisfied. Within 60 Calendar Days of the end of the month in which the Agency receives the Contractor’s certification regarding the Subcontractor’s Work, the Agency will either notify the Contractor of any deficiencies which require completion before release of retainage, or verify that the Subcontractor’s Work complies with the Contract and release all retainage for that Work with the next scheduled progress payment. Within 10 Calendar Days of receipt of retainage, the Contractor shall pay to the Subcontractor all such retainage released except for latent defects or warranty.

The Agency will only release retainage for satisfactorily completed portions of the Work represented by Pay Items in the Schedule of Items, or by Pay Items added by Change Order. Work not represented by a Pay Item, but which constitutes part of an uncompleted Pay Item, will not be regarded as satisfactorily completed Work for the purposes of this Subsection.

A determination of satisfactory completion of Pay Items or Work or release of retainage shall not be construed as acceptance or approval of the Work and shall not relieve the Contractor of responsibility for defective Materials or workmanship or for latent defects and warranty obligations.

If retainage has been reduced or eliminated, the Agency reserves the right to protect its interests by retaining amounts from further progress payments at the rates provided in 00195.50(b).

00195.50(f) Prompt Payment Policy - Replace this subsection, except for the subsection number and title, with the following:

Payments shall be made promptly according to ORS 279C.560, ORS 279C.570, ORS 279C.580 and other applicable legal requirements.

00195.60(a)(1) Request for Advance Allowance - Add the following:

• The request includes copies of the material invoices that clearly indicate what bid item the quantities and balances are allocated too.

• The request includes the Agency supplied tabulation and shall document current material on hand balances along with any balances relating to quantities installed during the most recent estimate period.

00195.60(d) Monthly Updated Statement - After materials on hand payments are made to the Contractor, the Contractor shall submit a monthly tabulation of all Materials on Hand, as described in 00195.60(a)(1), 5 calendar days before each progress estimate cut-off date.

If this tabulation is not received, received incomplete, or is received late, then the entire Materials on Hand balance will be deducted from the progress estimate.

SECTION 00196 - PAYMENT FOR EXTRA WORK

Comply with Section 00196 of the Standard Specifications.

SECTION 00197 - PAYMENT FOR FORCE ACCOUNT WORK

Comply with Section 00197 of the Standard Specifications modified as follows:

00197.20(e) Standby Time - Replace this subsection, except for the subsection number and title, with the following:

If ordered by the Engineer, standby time will be paid at 50% of the hourly rental rate calculated according to this Subsection, excluding the hourly operating rate. Rates for standby time that are calculated at less than $1 per hour will not be paid. Payment will be limited to not more than 8 hours in a 24-hour period or 40 hours in a 1 week period.

00197.30 Labor - Replace this subsection, except for the subsection number and title, with the following:

00197.30 Labor - The Contractor will be paid for all labor engaged directly on Force Account Work, including Equipment operators and supervisors in direct charge of the specific force account operations.

The cost of labor calculated under this Subsection will also be subject to the applicable markups in 00197.80.

(a) Standard Calculation - The hourly amount paid to the Contractor for each employee engaged on Force Account Work will be two times the actual base hourly wage (excluding fringe benefits, vacation, and all other direct or indirect costs including subsistence) paid to the employee for:

(1) Work under each Force Account Work order, up to an accumulated total value for labor under that order of $10,000; and

(2) Workers whose work class has an industrial accident insurance rate of 25% or less as determined by the National Council on Compensation Insurance (NCCI) for the assigned risk pool for the appropriate worker class.

This amount paid to the Contractor will be full compensation for all costs associated with labor on Force Account Work including wages, fringe benefits, vacation, insurance, markup and other direct or indirect costs except for per diem costs. If per diem is paid to workers for similar Pay Item Work, per diem costs will be paid on an actual-cost basis for the Force Account Work. The markup described in 00197.80 will not be added, except that the supplemental markup for Force Account Work performed by subcontractors will be allowed.

(b) Work Value for Labor over $10,000 or NCCI Rate over 25% - After the accumulated value of labor performed under a Force Account Work order exceeds either 00197.30(a)(1) or 00197.30(a)(2), payment for Force Account Work labor will be calculated as follows:

(1) Wages - The actual wages paid to laborers and supervisors, if those wages are paid at rates not more than those for comparable labor currently employed on the Project, or at the recognized, current, prevailing rates in the locality of the Project.

(2) Required Contributions - The actual cost of industrial accident insurance, unemployment compensation contributions, payroll transit district taxes, and social security for old age assistance contributions incurred or required under statutory law and these Specifications. The actual cost of industrial accident insurance is the NCCI rate for the assigned risk pool for the appropriate work class multiplied by the experience modification factor for the Contractor.

(3) Required Benefits - The actual amount paid to, or on behalf of, workers as per diem and travel allowances, health and welfare benefits, pension fund benefits, or other benefits, when such amounts are required by a collective bargaining agreement or other employment contract generally applicable to the classes of labor employed on the Project.

SECTION 00199 - DISAGREEMENTS, PROTESTS, AND CLAIMS

Comply with Section 00199 of the Standard Specifications, supplemented and/or modified as follows:

00199.20(b) Written Notice – Substitute “in writing” for “on form 734-2887”

00199.40(b) Step 1: Region Level Review - substitute Public Works Director for Region-level reviewer.

00199.40(c) Step 2: Agency Level Review - substitute Public Works Director for Contract Administration Engineer.

At the request of the Contractor, the Public Works Director shall, upon presentation to him, make prompt decisions in writing on all claims of the County or the Contractor and on all other matters relating to the execution and progress of the work or the interpretation of the Contract Documents.

00199.40(d) Step 3 Arbitration; Claims Review Board - Delete this subsection and substitute the following:

Demand for Arbitration: Any dispute or any decision of the Public Works Director which is subject to arbitration shall be submitted to arbitration upon the demand of either party to the dispute.

The…

This is the start of the file's text. The full file is on GovTribe.