Attachment F DSL Removal-Fill Permit.pdf
PDF 6 MB Posted
- Solicitation number
- S-C00040-00018390
- Issued by
- Clackamas County, Oregon
About this file
This is an Oregon Department of State Lands Removal-Fill Permit (No. 65405-RF) issued to Clatsop County Public Works for the Westport Ferry Road Extension project. The permit authorizes the construction of a new roadway extending approximately 1,250 feet between Highway 30 and the Westport Ferry Terminal, along with approximately 1,900 feet of Highway 30 widening to accommodate a westbound left turn lane and minor intersection improvements. The project will reroute heavy truck and ferry traffic away from residential neighborhoods and the currently failing ferry road. The proposed work includes site improvements such as stormwater management, a new rail crossing with signals, and pedestrian and bicycle traffic rerouting. The permit authorizes impacts to 0.39 acres of wetlands and 100 linear feet of waterway in Tax Lot 100, T8N R6W Section 36BD, Clatsop County, affecting Wetlands A (Depressional PEM), F (Depressional PFO), G (Depressional PSS), H (Riverine RSS), and Ditch A. The application was received December 18, 2025, circulated for public comment from December 24, 2025, to January 22, 2026, and the permit was approved with an expiration date of April 9, 2027. Fill or removal activities below ordinary high water elevation of Columbia River Tributaries must be conducted between July 15 and September 15, unless otherwise coordinated with the Oregon Department of Fish and Wildlife.
The permit includes extensive conditions addressing pre-construction requirements, general construction conditions, erosion control, fish salvage, and compensatory mitigation obligations. Mitigation for unavoidable wetland losses of 0.26 acres will be accomplished through the purchase of 0.26 credits from the Claremont Road Mitigation Bank, with additional on-site creation of a 0.24-acre depressional wetland complex. Temporary impacts to 0.05 acres of wetland and 24 square feet of Ditch A must be rectified according to the approved rehabilitation plan within 24 months of impact initiation. The permittee must obtain National Pollution Discharge Elimination System (NPDES) approval from the Oregon Department of Environmental Quality before construction begins and comply with all water quality standards. Post-construction reporting is required within 90 days of revegetation, with annual monitoring reports required for a minimum of five growing seasons. The mitigation site must be protected in perpetuity through a recorded Declaration of Covenants and Restrictions and Access Easement approved by the Department of State Lands. Any party may request a hearing within 21 calendar days of the permit issuance; failure to do so results in the permit becoming final by default.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of State Lands 775 Summer Street NE, Suite 100
Salem, OR 97301-1279
(503) 986-5200
FAX (503) 378-4844
www.oregon.gov/dsl
State Land Board
Tina Kotek Governor
Tobias Read
Secretary of State
Elizabeth Steiner State Treasurer
BEFORE THE DIRECTOR OF THE DEPARTMENT OF STATE
LANDS OF THE STATE OF OREGON
In the Matter of Removal-Fill Permit ) Application 65405-RF ) Proposed Permit Decision and Order;
) Notice of Right to a Hearing By Clatsop County Public Works )
Short and Plain Statement of the Permitting Decision: The permit application is approved because the Department of State Lands (DSL or the Department) has determined that, when carried out in compliance with all terms and conditions outlined in the permit, the proposed removal-fill activity is consistent with the protection, conservation, and best use of the water resources of this state and will not unreasonably interfere with the paramount policy of this state to preserve the use of its waters for navigation, fishing, and recreation. See ORS 196.825.
I. Applicable Law:
a. ORS Chapter 196 governs removal fill permits in Oregon. The Department administers
Oregon’s Removal-Fill Law, Oregon Revised Statutes (ORS) 196.795 to ORS 196.990, which protects the state’s wetlands and waterways. See ORS 196.805. Unless an exception applies, a person may not remove material from waters of this state or fill waters of this state without a permit from DSL. ORS 196.810. Waters of this state include the all-natural waterways, tidal and non-tidal bays, intermittent streams, constantly flowing streams, lakes, wetlands, the Pacific Ocean that is in the boundaries of this state, and other water bodies.
ORS 196.800; Oregon Administrative Rule (OAR) 141-085-0515; OAR 141-093-0100.
b. Specifically, the statutes that govern removal-fill permits in Oregon, including the permit application at issue in this case, generally include the following:
ORS 196.795 (Administration of State Removal or Fill Permits; General Permits);
ORS 196.800 (Definitions);
ORS 196.805 (Policy);
ORS 196.810 (Removal from Bed or Banks of Waters; Permits; Exceptions);
ORS 196.812 (Removal of Large Woody Debris);
ORS 196.815 (Permit Applications; Fees);
ORS 196.816 (Removal of Materials for Purpose of Maintaining Drainage and Protecting Agricultural Land);
ORS 196.817 (Removal or Fill General Permits);
ORS 196.818 (Wetland Delineation Reports; Fees);
ORS 196.820 (Smith Lake, Bybee Lake Prohibition);
ORS 196.825 (Permit Criteria; Consultation with Other Agencies);
ORS 196.830 (Estuarine Resource Replacement; Other Permit Conditions);
ORS 196.835 (Issuance of Permits; Procedure);
ORS 196.845(Investigations and Surveys of Location); and ORS 196.850 (Waiver of Permit Requirement; Notice; Review).
The full text of these statutes may be viewed online at:
https://www.oregonlegislature.gov/bills_laws/ors/ors196.html.
The full text of these statutes may also be inspected in person during normal business hours at:
Oregon Department of State Lands 775 Summer St NE STE 100 Salem, OR 97301.
c. OAR Chapter 141, Division 85 implement the above statutory scheme and govern removal-fill permits in Oregon. The rules that govern removal-fill permits in Oregon, including the permit application at issue in this case, generally include the following:
Div. 85 Removal-Fill Authorizations:
OAR 141-085-0500 (General);
OAR 141-085-0506 (Policy);
OAR 141-085-0510 (Definitions);
OAR 141-085-0515 (Removal-Fill Jurisdiction by Type of Water);
OAR 141-085-0520 (Removal-Fill Jurisdiction by Volume of Material);
OAR 141-085-0525 (Measuring and Calculating Volume of Removal and Fill);
OAR 141-085-0530 (Exemptions for Certain Activities and Structures);
OAR 141-085-0534 (Exemptions for Certain Voluntary Habitat Restoration Activities):
OAR 141-085-0535 (Exemptions Specific to Agricultural Activities);
OAR 141-085-0540 (Types of Authorizations);
OAR 141-085-0545 (Fees; Amounts and Disposition);
OAR 141-085-0550 (Application Requirements for Individual Permits);
OAR 141-085-0555 (Individual Removal-Fill Permit Application Review Process);
OAR 141-085-0560 (Public Review Process for Individual Removal - Fill Permit Applications);
OAR 141-085-0565 (Department Determinations and Considerations in Evaluating Individual Permit Applications);
OAR 141-085-0575 (Permit Appeals);
OAR 141-085-0580 (Discovery in Contested Cases);
OAR 141-085-0585 (Permit Conditions, Permit Expiration Dates and Permit Transfer);
OAR 141-085-0590 (Renewal and Extension of Individual Removal-Fill Permits);
OAR 141-085-0595 (Permit Requirements and Interagency Coordination for Department of Environmental Quality Approved Remedial Action, Corrections Facilities, Solid Waste Land Fills and Energy Facilities);
OAR 141-085-0665 (Expedited Process for Industrial or Traded Sector Sites);
OAR 141-085-0676 (Emergency Authorizations);
OAR 141-085-0680 (Compensatory Mitigation (CM); Applicability and Principal Objectives);
OAR 141-085-0685 (Functions and Values Assessment);
OAR 141-085-0690 (Eligibility Requirements for CM);
OAR 141-085-0692 (Mitigation Accounting);
OAR 141-085-0694 (Special Requirement for CM);
OAR 141-085-0695 (Administrative Protection of CM Sites);
https://www.oregonlegislature.gov/bills_laws/ors/ors196.html
OAR 141-085-0700 (Financial Security for CM Sites);
OAR 141-085-0705 (Requirements for CM Plans);
OAR 141-085-0710 (Monitoring Requirements for CWM);
OAR 141-085-0715 (Mitigation for Temporary Impacts);
OAR 141-085-0720 (Mitigation Banking Purpose, Applicability and Policies);
OAR 141-085-0725 (Process for Establishing Mitigation Banks);
OAR 141-085-0730 (Establishment of Mitigation Credits);
OAR 141-085-0735 (Release, Use and Sale of Mitigation Credits);
OAR 141-085-0740 (Authorization for Mitigation Banks);
OAR 141-085-0745 (In-Lieu Fee Mitigation);
OAR 141-085-0750 (Payments to and Expenditures from the Oregon Removal-Fill Mitigation Fund);
OAR 141-085-0755 (Advance Mitigation); and OAR 141-085-0768 (Advance Aquatic Resource Plans).
The full text of these rules may be viewed online at:
https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=15700.
The full text of these rules may also be inspected in person during normal business hours at:
775 Summer St NE STE 100
II. Findings of Fact and Findings of Ultimate Fact:
1. The Department received a complete, written application from applicant on December 18, 2025 for the proposed removal-fill activity consisting of a new road for the Westport Ferry Terminal that will re-route heavy truck and ferry traffic away from residential neighborhoods and the currently failing ferry road. Site improvements will include a turn lane off Highway 30, stormwater improvements, a new rail crossing and signals, pedestrian and bicycle traffic rerouting. A total of 0.41 acres of permanent impact will take place in jurisdictional Wetlands A (Depressional PEM), F (Depressional PFO), G (Depressional PSS), H (Riverine RSS), and Ditch A. Mitigation will be accomplished through purchase of 0.26 credits from Claremont Road Mitigation Bank and onsite creation of a 0.24 depressional wetland complex.
2. The Department circulated the complete application for 30-day public comment period December 24, 2025 to January 22, 2026 to parties including, affected local, state and federal agencies, affected tribal governments, adjacent landowners, and other parties requesting notification.
3. Public comments were received from Oregon Department of State Lands and David Havens and forwarded to applicant on January 23, 2026. There were no comments that required a response to the Department.
4. Based on all the information in the agency file in this matter, including the complete application, comments received, applicant response to comments, and the agency’s own investigations, the Department concludes as to the determinations in ORS 196.825(1) and (4), OAR 141-085-0565(3), and OAR 141-093-0115:
a. The project described in the permit application and as conditioned in the proposed permit, is consistent with the protection, conservation, and best use of the water resources of this state as specified in ORS 196.600 to 196.905;
https://secure.sos.state.or.us/oard/viewSingleRule.action?ruleVrsnRsn=15700
b. The project described in the permit application and as conditioned in the proposed permit would not interfere with the paramount policy of this state to preserve the use of its waters for navigation, fishing, and public recreation.
5. Based on all the information in the agency file in this matter, including the complete application, comments received, applicant response to comments, and the agency’s own investigations, the Department concludes, as to the considerations in ORS 196.825(3), OAR 141-085-0565(4), OAR 141-093-0115.
a. The applicant is a public body, and the Department has relied upon the public body’s findings as to local public need and local public benefit.
b. There is not an identified economic cost to the public if the proposed fill or removal is not accomplished. However, the following is from the application: “The Westport Corridor and Community Plan, developed in 2010, identified the need for a new road to remove anticipated heavy truck traffic from the Westport community’s residential neighborhoods and reroute it to the industrial area north of Highway 30. Westport Ferry Road is currently 15 to 21 feet wide and was designed to carry residential traffic. The road is beginning to fail due to increased heavy truck traffic, and the narrowness of the road also poses a safety issue.”
c. The application describes four (4) alternatives to the project for which the fill or removal is proposed. There are no practicable alternatives with lesser impact to waters of this state.
d. The application describes two (2) alternative sites for the proposed removal or fill. There are no practicable alternative sites with lesser impact to waters of this state.
e. The proposed project conforms to sound policies of conservation because adverse effects to the aquatic resources have been reduced to the extent practicable and the proposed permit contains operating conditions for best management practices to further minimize adverse effects. No interference with public health and safety was identified in the application evaluation and public review processes.
f. There is not a conflict with existing public uses of the affected waters or adjacent land uses identified in the application evaluation and public review processes.
g. The proposed fill or removal is compatible with the governing comprehensive plan and land use regulations as described in the Land Use Compatibility Statement
h. The proposed fill and removal is not for streambank protection.
i. The application describes compensatory mitigation in the form of purchase of 0.26 credits from Claremont Road Mitigation Bank and on-site permittee responsible creation of a 0.24 depressional wetland complex. The mitigation is sufficient to offset anticipated spatial and function attribute losses resulting from the proposed fill or removal.
III. Conclusions of Law:
Based on the factors laid out in ORS Chapter 196 and OAR Chapter 141, Division 85, including ORS 196.825, OAR 141-085-0565, and OAR 141-093-0115, DSL should approve the permit application as conditioned in the proposed permit.
IV. Proposed Order:
The Department proposes approving the permit application with conditions and based on the factors laid out in ORS Chapter 196 and OAR Chapter 141, Division 85, including ORS 196.825, OAR 141-085-0565 and OAR 141-093-0130.
As described below, you have the right to request a hearing within 21 days. Prior to the expiration of the 21-day period, this proposed permit decision is not the final agency order on the matter, and the permittee should be aware that the decision could be changed prior to the expiration of the 21-day appeal period—either because the permittee requests a contested case hearing, or as otherwise allowed under the removal fill law. A permittee who begins work under a permit prior to issuance of a final order does so with acceptance of this risk.
V. Hearing:
You are entitled to request a hearing based on this Proposed Order as provided by the Oregon Administrative Procedures Act (ORS chapter 183) and the administrative rules implementing the Administrative Procedures Act, OAR Chapter 137, Division 3. See ORS 196.825(7);
OAR 141-001-0005; OAR 141-001-0010; OAR 141-085-0575; OAR 141-093-0130.
If you want a hearing, you must file a written request for a hearing with the Department no later than 21 calendar days from the date of the permit decision. See ORS 196.825(7);
OAR 141-085-0575; OAR 141-093-0130. If you are a corporation, partnership, limited liability company, unincorporated association, trust, or government body, you must either have an attorney licensed to practice law in Oregon submit a request for a contested case hearing on your behalf or ratify your hearing request within 28 days. See OAR 137-003-0550.
The Department has determined that due to the complexity of removal-fill permitting, a general denial of the matters or a general objection to all permit conditions in the request for a contested case proceeding does not provide sufficient information for a fair and efficient contested case and a more specific request is warranted. OAR 141-085-0575. All requests for a contested case proceeding under this section shall include a specific list of issues for the contested case proceeding. OAR 141-085-0575. The requester may amend their request to include additional issues or clarify existing issues within 15 days of the date that the case is referred to the Office of Administrative Hearings. OAR 141-085-0575.
You may mail a request for a hearing to:
Aquatic Resource Management Program 775 Summer Street NE STE 100
If you request a hearing, you will be notified of the time and the place of the hearing. See OAR 137-003-0525. You may be represented by legal counsel at the hearing. ORS 183.417; OAR 137-003-0550. Corporations, partnerships, limited liability companies, unincorporated associations, trusts and government bodies must be represented by an attorney except as provided in OAR 137-003-0555 or as otherwise authorized by law. OAR 137-003-0550. Legal aid organizations may be able to represent you if you have limited financial resources. You will be given information on the procedures, right of representation, and other rights of parties relating to the substance and conduct of the hearing before commencement of the hearing.
See ORS 183.413.
VI. Jurisdiction and Authority to Hold a Hearing:
The Department has jurisdiction over the issuance of removal-fill permits pursuant to ORS Chapter 196, and specifically, ORS 196.810. A permit decision constitutes an order in a contested case. See ORS 183.310(2)(a); ORS 196.825(7). If timely requested, a hearing is held as laid out in ORS 183.411 to ORS 183. 471, OAR Chapter 137, Division 3, ORS Chapter 196, and OAR Chapter 141, Division 85. ORS 196.825(7).
VII. Final Order and Defaults:
If a request for a hearing is not received by the Department within this 21-day period, your right to a hearing shall be waived and this Proposed Order shall become the Final Order by default.
See ORS 196.825(7); OAR 141-085-0575; OAR 141-093-0130.
If you request a hearing and then either withdraw your hearing request, notify the Department or administrative law judge that you will not appear, or fail to appear at a scheduled hearing, the Department may issue a final order by default. See ORS 183.417.
If the Department issues a final order by default, it designates its file on this matter, including any materials submitted by you that relate to this matter, as the record for purposes of supporting its decision.
If you proceed to a contested case hearing, a Final Order will not be issued until after the hearing concludes. See ORS 183.464; OAR 141-085-0575; OAR 141-093-0130.
VIII. Federal Servicemembers Civil Relief Act:
Active duty servicemembers have a right to stay contested case proceedings under the federal Servicemembers Civil Relief Act. See generally 50 USC 3901 et seq. For more information, contact the Oregon State Bar (800-452-8260), the Oregon Military Department (503-584-3571), or the nearest United States Armed Forces Legal Assistance Office (http://legalassistance.law.af.mil). The Oregon Military Department does not have a toll-free telephone number.
775 Summer Street, Suite 100 Salem, OR 97301-1279 503-986-5200
Permit No.: 65405-RF Permit Type: Removal/Fill Waters: Wetlands A, F, G, H
Ditch A County: Clatsop Expiration Date: April 9, 2027
CLATSOP COUNTY PUBLIC WORKS
IS AUTHORIZED IN ACCORDANCE WITH ORS 196.800 TO 196.990 TO PERFORM THE
OPERATIONS DESCRIBED IN THE REFERENCED APPLICATION, SUBJECT TO THE SPECIAL
CONDITIONS LISTED ON ATTACHMENT A AND TO THE FOLLOWING GENERAL CONDITIONS:
1. This permit does not authorize trespass on the lands of others. The permit holder must obtain all necessary access permits or rights-of-way before entering lands owned by another.
2. This permit does not authorize any work that is not in compliance with local zoning or other local, state, or federal regulation pertaining to the operations authorized by this permit. The permit holder is responsible for obtaining the necessary approvals and permits before proceeding under this permit.
3. All work done under this permit must comply with Oregon Administrative Rules, Chapter 340;
Standards of Quality for Public Waters of Oregon. Specific water quality provisions for this project are set forth on Attachment A.
4. Violations of the terms and conditions of this permit are subject to administrative and/or legal action, which may result in revocation of the permit or damages. The permit holder is responsible for the activities of all contractors or other operators involved in work done at the site or under this permit.
5. Employees of the Department of State Lands (DSL) and all duly authorized representatives of the Director must be permitted access to the project area at all reasonable times for the purpose of inspecting work performed under this permit.
6. Any permit holder who objects to the conditions of this permit may request a hearing from the Director, in writing, within twenty-one (21) calendar days of the date this permit was issued.
7. In issuing this permit, DSL makes no representation regarding the quality or adequacy of the permitted project design, materials, construction, or maintenance, except to approve the project’s design and materials, as set forth in the permit application, as satisfying the resource protection, scenic, safety, recreation, and public access requirements of ORS Chapters 196, 390, and related administrative rules.
8. Permittee must defend and hold harmless the State of Oregon, and its officers, agents and employees from any claim, suit, or action for property damage or personal injury or death arising out of the design, material, construction, or maintenance of the permitted improvements.
9. Authorization from the U.S. Army Corps of Engineers may also be required.
NOTICE: If removal is from state-owned submerged and submersible land, the permittee must comply with leasing and royalty provisions of ORS 274.530. If the project involves creation of new lands by filling on state-owned submerged or submersible lands, you must comply with ORS 274.905 to 274.940 if you want a transfer of title; public rights to such filled lands are not extinguished by issuance of this permit. This permit does not relieve the permittee of an obligation to secure appropriate leases from DSL, to conduct activities on state-owned submerged or submersible lands. Failure to comply with these requirements may result in civil or criminal liability. For more information about these requirements, please contact Department of State Lands, 503-986-5200.
Brandy Bryant, Operations Manager Aquatic Resource Management
Authorized Signature Date
ATTACHMENT A
Permit Holder: Clatsop County Public Works
Project Name: Westport Ferry Road Extension
Special Conditions for Removal/Fill Permit No. 65405-RF
READ AND BECOME FAMILIAR WITH CONDITIONS OF YOUR PERMIT.
The project site may be inspected by the Department of State Lands (DSL) as part of our monitoring program. A copy of this permit must be available at the work site whenever authorized operations are being conducted.
1. Responsible Party: By signature on the application, Terry Hendryx is acting as the representative of Clatsop County Public Works. By proceeding under this permit, Clatsop County Public Works agrees to comply with and fulfill all terms and conditions of this permit, unless the permit is officially transferred to another party as approved by DSL. In the event information in the application conflicts with these permit conditions, the permit conditions prevail.
2. Authorization to Conduct Removal and/or Fill: This permit authorizes 0.39 acres of wetland and 100 linear feet of waterway impact(s) with associated removal and fill of material in T8N R6W Section 36BD, Tax Lot 100, ROW, in Clatsop County, as referenced in the application, map and drawings (See Attachment B for project location(s)), dated December 18, 2025. This permit also authorizes removal and fill activities necessary to complete the required compensatory mitigation.
3. Work Period in Jurisdictional Areas: Fill or removal activities below the ordinary high water elevation of Columbia River Tributaries must be conducted between July 15 and September 15, unless otherwise coordinated with Oregon Department of Fish and Wildlife and approved in writing by DSL. If fish eggs are observed within the project area, work must cease, and DSL contacted immediately.
4. Changes to the Project or Inconsistent Requirements from Other Permits: It is the permittee’s responsibility to ensure that all state, federal and local permits are consistent and compatible with the final approved project plans and the project as executed. Any changes made in project design, implementation or operating conditions to comply with conditions imposed by other permits resulting in removal-fill activity must be approved by DSL prior to implementation.
5. DSL May Halt or Modify: DSL retains the authority to temporarily halt or modify the project or require rectification in case of unforeseen adverse effects to aquatic resources or permit non-compliance.
6. DSL May Modify Conditions Upon Permit Renewal: DSL retains the authority to modify conditions upon renewal, as appropriate, pursuant to the applicable rules in effect at the time of the request for renewal or to protect waters of this state.
Steffanie Highlight
Attachment A
65405-RF
Pre-Construction
7. Stormwater Management Approval Required Before Beginning Work: Prior to the start of construction, the permittee must obtain a National Pollution Discharge Elimination System (NPDES) permit from the Oregon Department of Environmental Quality (DEQ), if one is required by DEQ.
8. Pre-construction Resource Area Fencing or Flagging: Prior to any site grading, the boundaries of the avoided wetlands, waterways, and riparian areas adjacent to the project site must be surrounded by noticeable construction fencing or flagging. The marked areas must be maintained during construction of the project and be removed immediately upon project completion.
General Construction Conditions
9. Water Quality Certification: The Department of Environmental Quality (DEQ) may evaluate this project for a Clean Water Act Section 401 Water Quality Certification (WQC). If the evaluation results in issuance of a Section 401 WQC, that turbidity condition will govern any allowable turbidity exceedance and monitoring requirements.
10. Erosion Control Methods: The following erosion control measures (and others as appropriate) must be installed prior to construction and maintained during and after construction as appropriate, to prevent erosion and minimize movement of soil into waters of this state.
a. All exposed soils must be stabilized during and after construction to prevent erosion and sedimentation.
b. Filter bags, sediment fences, sediment traps or catch basins, leave strips or berms, or other measures must be used to prevent movement of soil into waterways and wetlands.
c. To prevent erosion, use of compost berms, impervious materials or other equally effective methods, must be used to protect soil stockpiled during rain events or when the stockpile site is not moved or reshaped for more than 48 hours.
d. Unless part of the authorized permanent fill, all construction access points through, and staging areas in, riparian and wetland areas must use removable pads or mats to prevent soil compaction. However, in some wetland areas under dry summer conditions, this requirement may be waived upon approval by DSL. At project completion, disturbed areas with soil exposed by construction activities must be stabilized by mulching and native vegetative plantings/seeding. Sterile grass may be used instead of native vegetation for temporary sediment control. If soils are to remain exposed more than seven days after completion of the work, they must be covered with erosion control pads, mats or similar erosion control devices until vegetative stabilization is installed.
e. Where vegetation is used for erosion control on slopes steeper than 2:1, a tackified seed mulch must be used so the seed does not wash away before germination and rooting.
f. Dredged or other excavated material must be placed on upland areas having stable slopes and must be prevented from eroding back into waterways and wetlands.
g. Erosion control measures must be inspected and maintained as necessary to ensure their continued effectiveness until soils become stabilized.
h. All erosion control structures must be removed when the project is complete, and soils are stabilized and vegetated.
11. Fuels, Hazardous, Toxic, and Waste Material Handling: Petroleum products, chemicals, fresh cement, sandblasted material and chipped paint, material treated with leachable preservatives or other deleterious waste materials must not be allowed to enter waters of this state. Machinery and equipment staging, cleaning, maintenance, refueling, and fuel storage must be at least 150 feet from OHW or HMT and wetlands to prevent contaminates from entering waters of this state.
Refueling is to be confined to a designated area to prevent spillage into waters of this state.
Barges must have containment system to effectively prevent petroleum products or other deleterious material from entering waters of this state. Project-related spills into waters of this state or onto land with a potential to enter waters of this state must be reported to the Oregon Emergency Response System (OERS) at 1-800-452-0311.
12. Archaeological Resources: If any archaeological resources, artifacts or human remains are encountered during construction, all construction activity must immediately cease. The State Historic Preservation Office must be contacted at 503-986-0674. You may be contacted by a Tribal representative if it is determined by an affected Tribe that the project could affect Tribal cultural or archeological resources.
13. Construction Corridor: There must be no removal of vegetation or heavy equipment operating or traversing outside the designated construction corridor or footprint (Sheet(s) 1-13, A01-A02, BA01, BB01-BB03, BC01-BC03, BD01-BD03, C01, C01A, C02, C02A, C03, C03A, C04, C04A, C05, C05A, C06, C06A, FB01-FB08).
14. Operation of Equipment in the Water: Heavy equipment may be positioned below ordinary high water or highest measured tide if the area is isolated from the waterway and aquatic organism salvage is completed, as described in Block 4B of the application.
All machinery operated below ordinary high water (OHW) or highest measured tide (HMT) elevation must use vegetable-based hydraulic fluids, be steam cleaned and inspected for leaks prior to each use, and be diapered to prevent leakage of fuels, oils, or other fluids below OHW or HMT elevation. Any equipment found to be leaking fluids must be immediately removed from and kept out of OHW or HMT until repaired.
15. Work Area Isolation: The work area must be isolated from the water during construction by using a coffer dam or similar structure. All structures and materials used to isolate the work area must be removed immediately following construction and water flow returned to pre-construction conditions.
16. Fish Salvage Required: Fish must be salvaged from the isolation area. Permits from NOAA
Fisheries and Oregon Department of Fish and Wildlife, Fish Research are required to salvage fish.
Fish salvage permit information may be obtained by contacting ODFW Fish Research at 503-947-6254 or Fish.Research@state.or.us.
17. Raising or Redirecting Water: The project must not cause water to rise or be redirected and result in damage to structures or property on the project site as well as adjacent, nearby, upstream, and downstream of the project site.
Rectification of Temporary Impacts
18. Site Rectification Required for Temporary Wetland Impacts: Site rectification for temporary impacts to 0.05 acres of wetland and 24 square feet of Ditch A must be conducted according to mailto:Fish.Research@state.or.us the rehabilitation plan in the application, as described in Block 9B. Failure to rectify the site may result in additional compensatory mitigation.
19. Pre-construction Elevations Must Be Restored Within the Same Construction Season:
Construction activities within areas identified as temporary impact must not exceed two construction seasons and rectification of temporary impacts must be completed within 24 months of the initiation of impacts. However, if the temporary impact only requires one construction season, re-establishment of pre-construction contours must be completed within that same construction season, before the onset of fall rains.
Compensatory Mitigation
Bank Credits, Payment-in-Lieu or In-Lieu Fee
20. Mitigation Bank Credit Purchase: Mitigation for the unavoidable loss of 0.24 acres of riverine flow-through, Palustrine Scrub-shrub (PSS) wetland, and 0.02 acres of wooded tidal wetland has been accomplished via purchase of 0.26 credits from the Claremont Road Mitigation Bank Wetland Mitigation Bank, per the proof of purchase.
The following conditions apply to the actions proposed in the application received December 18, 2026.
21. Notice of Business Entity Changes Required: The permittee must make all reasonable efforts to maintain the business entity in active status until all mitigation obligations have been satisfied.
The permittee must notify DSL 60 days prior to dissolution, bankruptcy, or changes in the shareholders or stockholders, limited partners, members, trustees, current beneficiaries or other principals of the business.
22. Acreage and Type: Mitigation must be conducted according to the minimum acreages and methods described in the table below.
Acres Credits Cowardin, HGM Class Method 0.02* riverine flow-through, Riverine Intermittent (R4) creation
0.02 depressional, Palustrine Forested (PFO) creation
0.03 depressional, Palustrine Scrub-shrub (PSS) creation
0.14 depressional, Palustrine Emergent (PEM) creation
*Swale D will be created to mitigate for Ditch A impacts, at least 0.02 acres must be below 10.03 feet. Documentation of acreage and seeding required in post-construction as-built.
23. Mitigation Site Location: The mitigation must be conducted on-site. The center-point of the mitigation site is 46.13448 degrees Latitude, -123.3777 degrees Longitude. The current legal description is Township T8N R6W Section 36BD, Tax Lot 100, ROW, Clatsop County, as shown on Sheet(s) 4-5 of the application.
24. Timing of Mitigation Site Grading: Mitigation site grading must be completed prior to or within the same construction season as the commencement of the wetland impacts.
25. Timing of Mitigation Site Planting: Mitigation site plantings must be completed as described in the Compensatory Mitigation Plan, dated December 18, 2025.
26. Signs Required: Signs must be posted along the mitigation site perimeter stating that the area behind the sign is a protected site.
27. Long-term Protection of the Mitigation Site - Deed Restriction: The mitigation site must be protected in perpetuity by recording the approved Declaration of Covenants and Restrictions and Access Easement (Protection Instrument) on the deed of the property. The protection instrument must be approved and signed by DSL prior to recording with Clatsop County. A copy of the recorded instrument must be sent to DSL with the post-construction report.
28. GIS Data: A georeferenced shapefile (.shp) must be submitted to DSL prior to mitigation site release that documents the spatial extent of the mitigation site(s), including buffers. The shapefile must conform to the Oregon Lambert (Intl. Feet) projection.
29. Long-term Maintenance Required: Long-term site maintenance is required as described in the Compensatory Mitigation Plan in the application.
Monitoring and Reporting Requirements
30. Post-Construction Report Required: A post-construction report demonstrating as-built conditions and discussing any variation from the approved plan must be provided to DSL within 90 days of revegetation, which shall occur during the fall, winter, or spring immediately following the completion of grading within the required planting areas. The post-construction report must include:
a. A scaled drawing, accurate to 1-foot elevation, clearly showing the following:
i. Finished contours of the site.
ii. Current tax lot and right-of-way boundaries.
iii. Photo point locations.
iv. Permanently and temporarily impacted wetland and waterway boundaries identified separately, with square foot listed.
b. Photos from fixed photo points. This should clearly show the site conditions, and any signage, and fencing required.
c. A narrative that describes any deviation from the approved plan.
d. A copy of the recorded deed restriction or conservation easement.
31. Annual Monitoring Reports Required: Monitoring is required until DSL has officially released the site from further monitoring. The permittee must monitor the site to determine whether the site is meeting performance standards for a minimum period of 5 growing seasons after completion of all the initial plantings. Annual monitoring reports are required and are due by December 31.
Failure to submit the required monitoring report by the due date may result in an extension of the monitoring period, forfeiture of the financial security and/or enforcement action.
32. Extension of the Monitoring Period: The monitoring period may be extended, at the discretion of DSL, for failure of the site to meet performance standards for the final two consecutive years without corrective or remedial actions (such as irrigation, significant weed/invasive plants treatment or replanting) or when needed to evaluate corrective or remedial actions.
33. Contents of the Annual Monitoring Report: The annual monitoring report must include the following information:
a. Completed Monitoring Report Cover Sheet, which includes permit number, permit holder name, monitoring date, report year, performance standards, and a determination of whether the site is meeting performance standards.
b. Site location map(s) that clearly shows the impact site and mitigation site boundaries.
c. Site Plan that clearly shows at least the following:
i. The area seeded, with the square foot area listed.
ii. The area planted with trees and shrubs, with the square foot area listed.
iii. Current tax lot and right-of-way boundaries.
iv. Permanent monitoring plot locations that correspond to the data collected and fixed photo-points. These points should be overlaid on the as-built map.
v. PEM, PSS, PFO, and waterways (Swale D), clearly identified separately and the area
(square foot or acreage) of each noted.
vi. Creation areas identified separately, with the square foot area of each listed.
d. A brief narrative that describes maintenance activities and recommendations to meet success criteria. This includes when irrigation occurred and when the above ground portion of the irrigation system was or will be removed from the site.
e. Data collected to support the conclusions related to the status of the site relative to the performance standards listed in this permit (include summary/analysis in the report and raw data in the appendix). Data should be submitted using the DSL Mitigation Monitoring Vegetation Spreadsheet or presented in a similar format as described in DSL’s Routine Monitoring Guidance for Vegetation.
f. Photos from fixed photo points (include in the appendix).
g. Other information necessary or required to document compliance with the performance standards listed in this permit.
h. A post-construction functional assessment by the end of the monitoring period.
34. Corrective Action May Be Required: DSL retains the authority require corrective action in the event the performance standards are not accomplished at any time within the monitoring period.
Performance Standards
To be deemed successful, the mitigation areas including buffers must meet the following performance standards, as determined by DSL:
35. Establishment of Permanent Monitoring Locations Required: Permanent plot locations must be established during the first annual monitoring in sufficient number and locations to be representative of the site. The permanent plot locations must be clearly marked on the ground.
36. Wetland Acreage Required: The site will have a minimum acreage as shown in the Acreage and
Type table above, as determined by a Wetland Delineation Light with data collected during spring of a year when precipitation has been near normal, vegetation has been established, and irrigation has been removed for at least two years. Acreage must be documented on a printed map and in a GIS shapefile (.shp) including attribute information for each unique wetland polygon identifying the size as well as HGM and Cowardin classes.
Herbaceous Wetlands
37. Native Species Cover: The cover of native species, as defined in the USDA Plants Database, in the herbaceous stratum is at least 60%.
38. Invasive Species Cover: The cover of invasive species is no more than 10%. A plant species should automatically be labeled as invasive if it appears on the current Oregon Department of Agriculture noxious weed list, plus known problem species including Phalaris arundinacea, Mentha pulegium, Holcus lanatus, Anthoxanthum odoratum, and the last crop plant if it is non-native. Non-native plants should be labeled as such if they are listed as non-native on the USDA Plants Database. Beginning in Year 2 of monitoring, DSL will consider a non-native plant species invasive if it comprises more than 15% cover in 10% or more of the sample plots in any habitat class and increases in cover or frequency from the previous monitoring period. Plants that meet this definition will be considered invasive for all successive years of monitoring.
39. Bare Substrate Cover: Bare substrate represents no more than 20% cover.
40. Species Diversity: By Year 3 and thereafter, there are at least 6 different native species. To qualify, a species must have at least 5% average cover in the habitat class and occur in at least 10% of the plots sampled.
41. Moisture Prevalence Index: Prevalence Index is <3.0.
Shrub-dominated and Forested Wetlands
42. Native Species Cover: The cover of native species, as defined in the USDA Plants Database, in the herbaceous stratum is at least 60%.
43. Invasive Species Cover: The cover of invasive species is no more than 10%. A plant species should automatically be labeled as invasive if it appears on the current Oregon Department of Agriculture noxious weed list, plus known problem species including Phalaris arundinacea, Mentha pulegium, Holcus lanatus, Anthoxanthum odoratum, and the last crop plant if it is non-native. Non-native plants should be labeled as such if they are listed as non-native on the USDA Plants Database. Beginning in Year 2 of monitoring, DSL will consider a non-native plant species invasive if it comprises more than 15% cover in 10% or more of the sample plots in any habitat class and increases in cover or frequency from the previous monitoring period. Plants that meet this definition will be considered invasive for all successive years of monitoring. After the site has matured to the stage when desirable canopy species reach 50% cover, the cover of invasive understory species may increase but may not exceed 30%.
44. Bare Substrate Cover: Bare substrate represents no more than 20% cover.
45. Woody Vegetation: The density of woody vegetation is at least 1,600 live native plants (shrubs) and/or stems (trees) per acre OR the cover of native woody vegetation on the site is at least 50%. Native species volunteering on the site may be included, dead plants do not count, and the standard must be achieved for 2 years without irrigation.
46. Species Diversity: By Year 3 and thereafter, there are at least 6 different native species. To qualify, a species must have at least 5% average cover in the habitat class and occur in at least 10% of the plots sampled.
47. Moisture Prevalence Index: Prevalence Index total for all strata is <3.0.
Monitoring and Reporting Schedule
Report Requirements Schedule Post-Construction Post-construction report
Recorded Protection Instrument
90 days after completion of revegetation
First Annual Report Establishment of permanent monitoring locations
Vegetation performance standards
Demonstration that wetland hydrology has been accomplished
After one growing season of all proposed plantings
Second Annual Report Vegetation performance standards
After two growing seasons
Third and Fourth Annual Reports
Vegetation performance standards
Actual acreage achieved by HGM and Cowardin class1.
After three and four growing seasons, respectively.
One “light delineation” should be completed during spring of a year when precipitation has been near normal and no irrigation has been in use during the previous two years
Fifth Annual Report (or final report if the monitoring period has been extended)
Vegetation performance standards
Functional assessment1,2
After five growing seasons
1These requirements may be fulfilled any time during the monitoring period but must be received by DSL no later than the fifth annual monitoring.
2Functional assessments must meet the standards and requirements in OAR 141-085-0685. The same assessment method used for the pre-mitigation site functional assessment should be used for monitoring purposes, unless otherwise approved by DSL.
ATTACHMENT B
Permit Holder: Clatsop County Public Works
Project Name: Westport Ferry Road Extension
Maps and Drawings for Removal/Fill Permit No. 65405-RF
Attachment B
| Pre-Construction |
| General Construction Conditions |
| Rectification of Temporary Impacts |
| Bank Credits, Payment-in-Lieu or In-Lieu Fee |
| Monitoring and Reporting Requirements |
| Performance Standards |
| Herbaceous Wetlands |
| 2BSchedule |
| 1BRequirements |
| 0BReport |
| 2026-04-09T09:29:41-0700 | |
| Brandy Bryant |