Book 1 of 2 - Bid Docs.pdf

PDF 770 KB Posted

Attached to
Invitation to Bid - Westport Road Improvement Project
Solicitation number
S-C00040-00018390
Issued by
Clackamas County, Oregon

About this file

This document is Book 1 of 2 of the Bid Documents for the Westport Road Improvement Project, a public works public improvement contract issued by Clatsop County Public Works in Oregon on November 9, 2026. The project involves constructing approximately 1,250 feet of new roadway between Highway 30 and Westport Ferry, widening approximately 1,900 feet of Highway 30 to construct a westbound left turn lane, and making minor improvements to the existing Westport Road intersection with Highway 30. The scope of work includes grading, paving, drainage, guard rail, illumination, signing, striping, signals, and roadside development, including constructed wetlands and roadside drainage. Sealed bids are due by 2:00 p.m. on December 15, 2026, at 1100 Olney Avenue, Astoria, Oregon 97103. An optional pre-proposal walk-through is scheduled for November 18, 2026, at 2:00 p.m. on-site. Pre-proposal questions are due by December 8, 2026, at 5:00 p.m., with responses distributed by December 11, 2026. The Board of Commissioners will approve the award on January 13, 2027, with the Notice of Intent to Award issued January 15, 2027, and the Challenge Period expiring January 22, 2027. The contract is estimated to begin February 1, 2027, and end June 30, 2028, with liquidated damages assessed at $500 per day for work remaining incomplete beyond the specified period.

The bidder must submit a Bid Proposal Form, First-Tier Subcontractor Disclosure Form (required within two hours of bid deadline for contracts exceeding $100,000), Non-Collusion Affidavit, and a bid bond equal to 10 percent of the total bid amount. Upon award, the contractor must provide a Performance Bond and Payment Bond each equal to the full contract price, a Public Works Bond of $30,000 filed with the Oregon Construction Contractors Board, proof of workers' compensation insurance with employer's liability of at least $100,000, and general liability insurance of at least $1,000,000 per occurrence. The contract is subject to Oregon prevailing wage requirements under ORS 279C.800 to 279C.870, as detailed in wage rates dated January 2025. The successful contractor must comply with all applicable federal, state, and local laws, including tax compliance certification, non-discrimination requirements, and environmental regulations. The Bid Schedule contains 114 line items including mobilization, traffic control, embankment, drainage, paving, signage, lighting, guardrails, and wetland restoration work, with quantities specified for unit price bidding. The County reserves the right to waive minor informalities and reject any or all bids if deemed in the public interest.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE ISSUED: November 9, 2026

Book 1 of 2

OF THE BID DOCUMENTS

FOR:

WESTPORT ROAD

IMPROVEMENT PROJECT

Grading, Paving, Drainage, Guard Rail, Illumination, Signing, Striping, Signals, and Roadside Development

A CLATSOP COUNTY

PUBLIC WORKS

PUBLIC IMPROVEMENT PROJECT

ANTICIPATED TIME LINE FOR PROPOSAL

Action Location Date Time

Solicitation Advertisement DJC, County Website

November 9, 2026 N/A

Optional Pre-Proposal Walk- Through

On-Site November 18, 2026 2:00 PM

Pre-Proposal Questions Due County Engineer December 8, 2026 5:00 PM

Responses to Pre-Proposal Questions Distributed by City

County Engineer December 11, 2026 5:00 PM

Proposal Due 1100 Olney Avenue

Astoria, Oregon 97103

December 15, 2026 2:00 PM

Commission Approval Board of Commissioners

January 13, 2027 7:00 PM

Notice of Intent to Award Contract County Engineer January 15, 2027 10:00 AM

Challenge Period Expires and Award of Contract

County Engineer January 22, 2027 10:00 AM

Begin Contract (Estimated) On-Site February 1, 2027 8:00 AM

Contract Ends On-Site June 30, 2028 3:00 PM

Table of Contents Westport Road Improvements

SUBJECT PAGE

Table of Contents Bidding Information

Invitation to Bid

Scope of Work

Information for Bidders

Bid Forms Bid Proposal Form

Addendum Receipt

Bid Schedule

First Tier Subcontractor Disclosure Form

Instructions for Non-Collusion Affidavit

Non-Collusion Affidavit

Bid bond

Contract Forms Clatsop county contract for construction

Performance bond

Payment bond

Selection of retainage option

Retainage bond

Bidding Information

Invitation to Bid

Invitation to Bid

Clatsop County, Oregon

Clatsop County Public Works intends to contract for a new roadway extension between Hwy 30 and Westport Ferry (approximately 1,250 feet which also includes approximately 1,900 feet of widening Hwy 30 to construct a westbound left turn lane for the new roadway). The project includes minor improvements to the existing Westport Road intersection with Hwy 30. Plans and specs available on County website at http://www.clatsopcounty.gov, see Jobs & Bids/RFPs. A copy is available for review at 1100 Olney Ave, Astoria, Or 97103, (503) 325-8631. Contractor shall furnish all labor, materials and equipment. Sealed bids will be received by Dean Keranen, County Engineer at 1100 Olney Ave, Astoria, OR 97103 until 2:00 p.m. on December 15, 2026, when they will be opened and publicly read. Any bid received after the time specified will not be considered. Faxed or emailed bids will not be accepted. Bid bond equal to ten percent (10%) of the total bid is required. Project is for Public Works subject to ORS 279C.800 to 279C.870. The County reserves the right to waive minor informalities and reject any or all bids not in compliance with all prescribed public bidding procedures and requirements and may reject for good cause any or all bids if it is deemed to be in the public interest to do so.

Attention: If you are downloading a copy of this Bid packet, please send confirmation of Bid Download to Clatsop County Roads email box at the following email address roads@clatsopcounty.gov or by fax to 503-325-9312. Include the project name, your company name, address, and contact name. This information will be used to compile the Plan Holders List.

Addenda will be published on the County’s website at www.clatsopcounty.gov.

Bidder is responsible for checking website for addenda.

Scope of Work

The work to be completed under this contract consists of the following:

1. All traffic control and protection and direction of traffic necessary for safety of motorists as required by the Oregon Manual on Uniform Traffic Control Devices.

2. Provide all equipment, material and labor to pave the roadway as specified in the Special Provisions.

3. WESTPORT BYPASS ROAD CONSTRUCTION

a. Construct approximately 1,250 feet of new roadway with roadside drainage, guardrail, surcharge grading, and constructed wetlands as shown in the construction plans.

4. HWY 30 WIDENING

a. Widen Hwy 30 to the north and restripe approximately 1,900’ to construct a left turn lane into the realigned Westport Road. Install storm drainage and guardrail as shown on the construction plans.

5. HWY 30 AT EXISTING WESTPORT ROAD

a. Construct concrete curb return, sidewalk connection and pedestrian

ADA ramp, reconstruct driveways, and railroad crossing closure.

Information for Bidders

Project Name: Westport Road Improvements

Time of Project Completion

• Complete all project work between February 1, 2027 and June 30, 2028.

• Work of the contract shall continue without delay or interruption once it is begun, unless otherwise specified.

Time and Place for Receiving Proposals Sealed proposals for the work described above will be received at the office of Dean Keranen, County Engineer at:

1100 OLNEY AVENUE

ASTORIA, OREGON 97103

UNTIL 2:00 P.M. ON DECEMBER 15, 2026

when they will be opened and publicly read.

Bidders Checklist The bidder's attention is especially called to the following forms, which must be executed in full before the bid is submitted:

(a) Bid Proposal Forms Proposal sheets are to be filled in, either typed or in ink, and signed by the bidder.

Bid Schedule The unit price (if any) must be shown in the space provided. The unit price shall be used as the determining factor in case of error in price extension.

(b) First-Tier Subcontractor Disclosure submitted within two hours of bid deadline. A First Tier Subcontractor Disclosure Form is required for public improvements with an estimated value of more than $100,000.

(c) Non-Collusion Affidavit is to be completed.

(d) Bid Bond

A surety bond, irrevocable letter of credit issued by an insured institution as defined in ORS 706.008, cashier’s check or certified check of bidder for 10% of the amount bid shall be attached to all bids as bid security.

(e) The Bid Forms must be returned on or before the date specified

(f) The County may reject any bid not in compliance with all prescribed public contracting procedures and requirements and may reject for good cause all bids upon a finding of the County that it is in the public interest to do so.

EVENT DATE/TIME & LOCATION

Bid Opening December 15, 2026 at 2:00 p.m. at Clatsop County Public Works 1100 Olney Avenue, Astoria, OR 97103

First-Tier Subcontractor Disclosure form December 15, 2026 at 4:00 p.m. at Clatsop County Public Works 1100 Olney Avenue, Astoria, OR 97103

Preliminary Bid Results Will be published on County’s website at clatsopcounty.gov

Notice of Intent to Award issued Will be published on County’s website at least 7 days prior to Award of Contract

Estimated Award of Contract January 22, 2027

Execution of Contract Following Award of Contract and contractor submission of required documents as per this Invitation To Bid

Time of (Contract) Completion (unless modified by in accordance with contract provisions)

June 30, 2028

Addenda County will not mail notice of Addenda, but will publish notice of any Addenda on County’s Web site. Addenda may be downloaded off the County’s web Site at http://www.clatsopcounty.gov. Offerors should frequently check the County’s web site until closing; at least once daily the week of closing.

Contract Terms The successful bidder for a public improvement contract shall promptly execute and deliver to Clatsop County:

(a) A Performance Bond in an amount equal to the full contract price, conditioned on the faithful performance of the contract in accordance with the plans, specifications and conditions of the contract.

Performance bond must be executed solely by a surety company or companies holding a certificate of authority to transact surety business in the State of Oregon and payable to Clatsop County.

(b) A Payment Bond in an amount equal to the full contract price, solely for the protection of claimants under ORS 279C.600. Payment bond must be executed solely by a surety company or companies holding a certificate of authority to transact surety business in the State of Oregon and must be payable to Clatsop County.

(c) Contractors must have a Public Works Bond in the amount of $30,000 filed with the Oregon Construction Contractors Board before starting work on a contract or a subcontract for a public works project. A http://www.co.clatsop.or.us/ contractor or subcontractor shall file with the Construction Contractors Board a public works bond with a corporate surety authorized to do business in Oregon in the amount of $30,000, unless exempted under ORS 279C.836. Form is available online at the Bureau of Labor.

(d) Clatsop County Contract for Construction to be executed by the successful bidder.

(e) Certificate of Insurance - Property and General Liability Certificates of

Insurance satisfying the requirements as stated herein will be required.

(f) Certificate of Insurance - Workers Compensation Coverage Certificate of Insurance satisfying the requirements as stated herein will be required.

(g) Time for Agency Acceptance – Contractor’s offer must be a Firm Offer, valid and binding on the Offeror for not less than 60 days from closing.

(h) Bidder must promptly execute contract and deliver performance bond, payment bond and proof of insurance, or forfeit the bid security that accompanied the bid.

Bidder acknowledges that he/she is aware of, fully understands and intends to comply with documents and regulations that are hereby made a part of these specifications:

• Prevailing Wage Rates in accordance with ORS 279C.800 to 279C.870.

• Non-discrimination in awarding of subcontracts in accordance with ORS 279A.110.

• ORS 279A.120 regarding local bidder preference.

• Contractor certifies that all subcontractors performing work described in ORS 701.005(2) will be registered with the Construction Contractors Board, or for work as a landscape contractor has a current, valid landscape contractors’ license issued pursuant to ORS 671.560 by the State Landscape Contractors Board.

• Contractor certifies that they are in compliance with the Oregon tax laws in accordance with ORS 305.385.

• ORS 279C.580 regarding contractor’s relations with subcontractors.

• ORS 279C.525 regarding Environment and natural resources regulations.

• ORS 279C.605 regarding notice of claim.

• ORS 279C.510 (1) regarding salvaging and recycling of demolition debris.

• ORS 279C.600 thru ORS 279C.6610 regarding Action on Payment and Public Works Bonds.

• ORS 279C.650 thru ORS 279C.670 regarding Termination of Contract for Public Interest Reasons.

• The County reserves the right to waive minor informalities and reject any or all bids not in compliance with all prescribed public bidding procedures and requirements and may reject for good cause, including Bidder responsibility under ORS 279C.375(c)(b), any or all bids if it is deemed to be in the public interest to do so.

Liquidated Damages:

Liquidated damages shall apply against the successful bidder (the Contractor) and accrue to the Owner at the rate of five hundred dollars ($500) per day for every day that the project remains uncompleted beyond the period outlined above.

Prevailing Wage Rates:

The “Prevailing Wage Rates for Public Works Contracts in Oregon” dated January, 2025, and any amendments are hereby included in these specifications by reference. The wage rates can be accessed at http://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx.

Project Plans:

Contractor will complete the project in accordance with the specifications herein, including:

• Project plans: Westport Road Improvements dated _October 28, 2026. ___

• ODOT Access Permit

• Railroad Agreement

• Power Company Drawings

• DEQ 401 Water Quality Certification Approval

• USACE Nationwide Permit Authorization

• DSL Removal-Fill Permit

• Stormwater Management Report

• Pavement Design Memorandum

• Pavement Design Summary

Questions and requests for interpretations should be directed to:

Dean Keranen or Terry Hendryx at Clatsop County Public Works

1100 Olney Avenue Astoria, Oregon 97103

Phone: 503-325-8631 Fax: 503-325-9312.

Email addresses are dkeranen@clatsopcounty.gov and thendryx@clatsopcounty.gov.

Any Bidder that finds discrepancies in, or omissions from any provision of the ITB, Plans, Specifications, or Contract Documents or has doubt as to the meaning, shall make a request for interpretation in writing, to the contact point listed above. The deadline for the request for interpretations can be found in the project schedule table. An addendum will be issued if a substantial clarification is in order.

http://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx mailto:dkeranen@clatsopcounty.gov mailto:thendryx@clatsopcounty.gov

Bid Forms

Bid Proposal - 1

Bid Proposal Form

The undersigned, as bidder declares:

• That the only person or parties interested in this Proposal as principals are those named therein;

• That this Proposal is made without collusion with any other person, firm or corporation;

• That he has carefully examined and fully understands the bid documents: "Proposal and Specifications for the Westport Road Improvements”, Invitation to Bid, Information for Bidders, General Specifications and Special Provisions, Prevailing Wage Rates, Bid Forms, and Contract, on file in the office of the Public Works Department office at 1100 Olney Avenue, Astoria, and are hereby made a part of this agreement;

• That he submits this Proposal subject to the terms and conditions stated in the Bid Documents;

• That if this bid is accepted, he will contract with said Clatsop County in the approved form of contract, to provide all necessary machinery, tools, apparatus, and other means of construction and to do all work and furnish all the materials specified in the contract in the manner and time therein prescribed and according to the requirements as therein set forth;

• That he will accept as full payment, therefore, the amount earned under the contract in the manner described in the Bid Documents;

• That he will comply with the provisions of ORS 279C.840 regarding prevailing wage rates and all other applicable provisions of Oregon law as well as all Clatsop County ordinances and rules relating to public contracting;

o That he has not discriminated and will not discriminate against minority, women, or emerging small business enterprises or against a business enterprise that is owned or controlled by or that employs a disabled veteran in obtaining any required subcontracts;

o That he is not in violation of any Oregon Tax Law;

o That he is registered with the Construction Contractors Board as required by

ORS 701.055

o That he has an employee drug testing program in place in compliance with ORS

279C.505(2)

• That after having carefully examined the Specifications covering the project, the bidder proposes to furnish all necessary labor, materials, and equipment and to perform the work in full accordance with said Specifications in the quantity(ies) and Price(s) as shown on Schedule of Prices.

Bid Proposal - 2

Addendum Receipt (if any)

The receipt of the following addenda to Specifications is hereby acknowledged.

ADDENDUM NO. ___________________ DATE: _________________________

The names of the president, treasurer, and manager of the bidding corporation, or the names and residences of all persons and parties interested in this Bid as partners or principals are as follows:

Name Address

The names of the surety by which the Performance Bond covering the Contract, if awarded, will be furnished, and the name, address and phone number of the surety’s local agent are as follows:

Name of Surety

Name of Agent

Address

Phone Number _____________________

Bidder acknowledges that he is aware of the provisions of ORS 279C.375. This law requires public contracting agencies, in determining the lowest responsible bidder, to add a percent increase to each out-of-state bidder's bid price which is equal to the percent of preference given to local bidders in that bidder's home state. In other words, if the low bidder is from a state that grants a 10 percent preference to local bidders, the Oregon agency must add 10 percent to that bidder's bid price when evaluating the bid.

Bid Proposal - 3

Bid Schedule

NO. ITEM DESCRIPTION

UNIT OF

MEASURE

QUANTITY

UNIT

PRICE

(IN FIGURES)

TOTAL

(IN FIGURES)

1 Mobilization Lump Sum

All Lump Sum $

Temporary Work

Zone Traffic Control, Complete

Lump Sum

All Lump Sum $

3 Temporary Signs Square

Foot 220 $ $

Flaggers, MINIMUM BID

$63/HR

Hours 320 $ $

Temporary Plastic

Drums Each 88 $ $

Temporary Flexible Pavement Markers

Each 74 $ $

7 Temporary Striping Foot 12,100 $ $

Temporary

Pavement Bars Square

Foot 20 $ $

9 Stripe Removal Foot 13,100 $ $

10 Legend Removal Square

Foot 610 $ $

Pedestrian

Channelizing Devices

Foot 600 $ $

Temporary Curb

Ramp Each 1 $ $

Temporary Construction Work

Zone Fence, Orange

Foot 300 $ $

14 Erosion Control Lump Sum

All Lump Sum $

15 Plastic Sheeting Square Yard

100 $ $

16 Check Dam, Type 3 Each 13 $ $

Concrete Washout

Facility Each 1 $ $

18 Sediment Fence Foot 4,700 $ $

Inlet Protection, Type 3 Each 10 $ $

Inlet Protection, Type 4 Each 5 $ $

Sediment Barrier, Type 8 Foot 950 $ $

22 Straw Bale Each 25 $ $

Temporary Filter

Bag Each 2 $ $

Pollution Control

Plan Lump Sum

All Lump Sum $

Protection of Fish and Fish Habitat

Lump Sum

All Lump Sum $

Construction Survey Work

Lump Sum

All Lump Sum $

Removal of Walks and Driveways Square Yard

150 $ $

Removal of Surfacings

Square Yard

2,600 $ $

29 Removal of Inlets Each 1 $ $

Removal of

Structures and Obstructions

Lump Sum

All Lump Sum $

Clearing and

Grubbing Acre 3.6 $ $

Embankment in

Place Cubic Yard

15,598 $ $

33 Settlement Plates Each 5 $ $

24 Inch Subgrade

Stabilization Square Yard

100 $ $

Subgrade Geotextile

Square Yard

10,000 $ $

Loose Riprap, Class 100 Ton 15 $ $

Keyed Riprap, Class 100 Ton 100 $ $

24 Inch Culvert

Pipe, 10 ft Depth Foot 200 $ $

12 Inch Storm

Sewer Pipe, 5 ft Depth

Foot 500 $ $

Paved Culver End

Slopes Square

Foot 148 $ $

Concrete Inlets, Type CG-2 Each 6 $ $

Concrete Inlets, Type G-2 Each 2 $ $

Filter Inlet, 3

Cartridge Each 1 $ $

Filter Inlet, 4

Cartridge Each 3 $ $

Filter Inlet, 6

Cartridge Each 1 $ $

46 Drainage Curbs Foot 3,350 $ $

47 Adjust Boxes Each 2 $ $

Cold Plane

Pavement Removal Square Yard

3,800 $ $

49 Aggregate Base Cubic Yard

5,100 $ $

Aggregate Shoulders

Cubic Yard

900 $ $

Level 3, ½ Inch

ACP Mixture Ton 4,300 $ $

Extra for Asphalt

Approaches Each 1 $ $

Concrete Curbs, Curb and Gutter

Foot 40 $ $

Concrete Curbs, Standard Curbs

Foot 320 $ $

55 Concrete Walks Square

Foot 1,720 $ $

Truncated Domes on New Surfaces

Each 2 $ $

Extra for New Curb

Ramps Each 2 $ $

Midwest Guardrail System, Type 2A

Foot 2,525 $ $

Guardrail End Pieces, Type B

Each 2 $ $

Guardrail End

Pieces, Type C Each 4 $ $

Guardrail Anchors, Type 1 Modified Each 6 $ $

Guardrail Terminals, Non-

Flared, Type

MSKT-SP-MGS

Each 2 $ $

Extra for Hand Dug

Guardrail Post Holes

Each 9 $ $

64 Delineators, Type 1 Each 2 $ $

Delineators, Type 4

Alternate 1 Each 4 $ $

Facility Field

Markers, Type __ Each 6 $ $

Bi-Directional

Yellow Type 1AR Markers, Recessed

Each 198 $ $

Mono-Directional White Type 1AR

Markers, Recessed Each 16 $ $

Continuous Rumble

Strips Mile 0.11 $ $

Gap Pattern

Rumble Strips Mile 0.22 $ $

Thermoplastic, Extruded, Surface, Non-Profiled

Foot 19,800 $ $

Pavement Legend, Type B-HS: Arrows

Each 7 $ $

Pavement Legend, Type B-HS:

Railroad Crossing

Each 2 $ $

Pavement Bar, Type B-HS Square

Foot 133 $ $

Remove Existing

Signs Lump Sum

All Lump Sum $

Remove and

Reinstall Existing Signs

Lump Sum

All Lump Sum $

Sign Support

Footings Lump Sum

All Lump Sum $

Perforated Steel Square Tube Slip

Base Sign Supports

Lump Sum

All Lump Sum $

Perforated Steel Square Tube Anchor Sign

Support

Lump Sum

All Lump Sum $

Signs, Standard Sheeting, Sheet

Aluminum

Square Foot

160 $ $

Permanent Type III

Barricades Each 2 $ $

82 Pole Foundations Lump Sum

All Lump Sum $

Light Poles and

Arms Lump Sum

All Lump Sum $

Luminaires, Lamps, and Ballasts Lump Sum

All Lump Sum $

Switching, Conduit, and Wiring Lump Sum

All Lump Sum $

Water Quality

Swale, “A” Lump Sum

All Lump Sum $

Water Quality

Swale, “B” Lump Sum

All Lump Sum $

Water Quality

Swale, “C” Lump Sum

All Lump Sum $

89 Permanent Seeding Acre 1.42 $ $

Wetland Seeding, Mix No. 1, River Refuge Custom

Native Wetland Mix

Acre 0.45 $ $

Wetland Seeding, Mix No. 2, Sunmark Seeds Marsh Mix

Acre 0.05 $ $

Wetland Seeding, Mix No. 3, River Refuge Native Wetland Deep

Water Mix

Acre 0.04 $ $

Wetland Seeding, Mix No. 4, Sunmark

Seeds Native Erosion Control Mix

Acre 0.67 $ $

94 Topsoil Cubic Yard

35 $ $

Wetland Plants, Bare Root, Oregon Ash

Each 5 $ $

Wetland Plants, Bare Root, Pacific Willow

Each 5 $ $

Wetland Plants, Bare Root, Sitka

Spruce Each 80 $ $

Wetland Plants, Bare Root, Douglas Spirea

Each 25 $ $

Wetland Plants, Bare Root, Nootka Rose

Each 125 $ $

Wetland Plants, Bare Root, Sitka

Willow Each 75 $ $

Wetland Plants, Bare Root, Pacific Ninebark

Each 15 $ $

Wetland Plants, Bare Root, Cascara Each 50 $ $

Wetland Plants, Bare Root, Red

Alder Each 25 $ $

Wetland Plants, Bare Root, Scouler's Willow

Each 50 $ $

Wetland Plants, Bare Root, Douglas Hawthorne

Each 50 $ $

Wetland Plants, Bare Root, Twinberry

Honeysuckle

Each 50 $ $

Wetland Plants, Bare Root, Common

Snowberry

Each 115 $ $

Wetland Plants, Bare Root, Salmonberry

Each 50 $ $

Wetland Plants, Bare Root, Pacific Crab Apple

Each 50 $ $

Wetland Plants, Bare Root, Tall Oregon Grape

Each 15 $ $

Wetland Plants, Bare Root, Oceanspray

Each 15 $ $

112 Bark Mulch Cubic Yard

5 $ $

113 Type 1-5W Fence Foot 740 $ $

6 Foot Chain Link

Fence Foot 350 $ $

TOTAL BID PRICE $

Bidder Name______________ ______ DATED: ____________________

Bid Proposal - 4

Pursuant to ORS 279A.120 the bidder is directed to complete the following:

YES NO

1. Is bidder a resident bidder? ____ ____

2. Has bidder paid Oregon unemployment and income taxes within the last 12 months immediately preceding this bid? ____ ____

3. Does bidder have a business address in Oregon? ____ ____

4. If you are a non-resident bidder: ____ % is the preference granted by your resident state to local bidders.

Dated: __________________________________________________

Bidder: __________________________________________________

Signature: _______________________________________________

Printed Name: ____________________________________________

Title: ____________________________________________________

Address: _________________________________________________

Phone: __________________________________________________

Email: ___________________________________________________

Federal Tax I.D. No.: _______________________________________

Oregon Contractors Board Registration: ________________________

First Tier Subcontractor Disclosure Form

For Public Improvements with a contract value of more than $100,000

(ORS 279C.370)

Project Name: Westport Road Improvements

Closing Date: December 15, 2026 at 2:00 p.m.

Subcontractor Disclosure Deadline: December 15, 2026 at 4:00 p.m.

This form must be submitted at the location specified within two (2) working hours of the advertised bid closing date and time; no later than the Disclosure Deadline stated above.

List below the Name, Address, Dollar Value, Construction Contractor Bond (CCB) and category of work of each subcontractor that will be furnishing labor or materials that are required to be disclosed. Enter “none” if there are no subcontractors that need to be disclosed. (If needed attach additional sheets).

Name/Address

Dollar Value/CCB#

Category of Work

The above listed first-tier subcontractor(s) are providing labor and/or materials with a Dollar Value equal to or greater than:

• 5% of the Project Bid, but at least $15,000; or

• $350,000, regardless of the percentage.

Failure to submit this form by the disclosure deadline will result in a bid submitted becoming non-responsive, and such bids shall not be considered for award!

Bids that are submitted by bid closing, but for which the separate disclosure submittal has not been made by the specified deadline, are not responsive and shall not be considered for Contract award.

Form submitted by (Bidder Name): _____________________________________________

Instructions for Non-Collusion Affidavit

1. This Non-collusion Affidavit is material to any contract awarded pursuant to this bid. According to the Oregon Public Contracts and Purchasing Laws, a public contracting agency may reject any or all bids upon a finding of the agency that is in the public interest to do so. This agency finds that it is in the public interest to require the completion of this affidavit by potential contractors.

2. This Non-Collusion Affidavit must be executed by the member, officer or employee of the bidder who makes the final decision on prices and the amount quoted in the bid.

3. Bid rigging and other efforts to restrain competition, and the making of false sworn statements in connection with the submission of bids are unlawful and may be subject to criminal prosecution. The person who signs the Affidavit should examine it carefully before signing and assure himself or herself that each statement is true and accurate, making diligent inquiry, as necessary, of all other persons employed by or associated with the bidder with responsibilities for the preparation, approval or submission of the bid.

4. In the case of a bid submitted by a joint venture, each party to the venture must be identified in the bid documents, and an Affidavit must be submitted separately on behalf of each party.

5. The term "complementary bid" as used in the Affidavit has the meaning commonly associated with that term in the bidding process, and includes the knowing submission of bids higher than the bid of another firm, any intentionally high or noncompetitive bid, and any other form of bid submitted for the purpose of giving a false appearance of competition.

6. Failure to file an Affidavit in compliance with these instructions will result in disqualification of the bid.

Non-Collusion Affidavit

STATE OF )

County of )

I state that I am of and that I am authorized to make this affidavit on behalf of my firm, and it owners, directors, and officers. I am the person responsible in my firm for the price(s) and the amount of this bid.

I state that:

(1) The price(s) and amount of this bid have been arrived at independently and without consultation, communication or agreement with any other contractor, bidder or potential bidder, except as disclosed on the attached appendix.

(2) That neither the price(s) nor the amount of this bid, and neither the approximate price(s) nor approximate amount of this bid, have been disclosed to any other firm or person who is a bidder or potential bidder, and they will not be disclosed before bid opening.

(3) No attempt has been made or will be made to induce any firm or person to refrain from bidding on this contract, or to submit a bid higher than this bid, or to submit any intentionally high or noncompetitive bid or other form of complementary bid.

(4) The bid of my firm is made in good faith and not pursuant to any agreement or discussion with, or inducement from, any firm or person to submit a complementary of other noncompetitive bid.

(5) , its affiliates, subsidiaries, officers, directors and employees are not currently under investigation by any governmental agency and have not in the last four years been convicted of or found liable for any act prohibited by State of Federal law in any jurisdiction, involving conspiracy or collusion with respect to bidding on any public contract, except as described on the attached appendix.

I state that understands and acknowledges that the above representatives are material and important, and will be relied on by Clatsop County in awarding the contract(s) for which this bid is submitted. I understand and my firm understands that any misstatement in this affidavit is and shall be treated as fraudulent concealment from Clatsop County of the true facts relating to the submission of bids for this contract.

Sworn to and subscribed before me this day of ___ , 20___ .

NOTARY PUBLIC FOR OREGON

My Commission Expires:

CLATSOP COUNTY

STANDARD PUBLIC IMPROVEMENT CONTRACT

Bid Bond

We, _____________________________________, as “Principal,” (Name of Principal) and ___________________________________, an _________________ Corporation, (Name of Surety) authorized to transact Surety business in Oregon, as “Surety,” hereby jointly and severally bind ourselves, our respective heirs, executors, administrators, successors and assigns to pay unto Clatsop County (“Obligee”) the sum of ($____________________________)

_________________________________________________________________ dollars.

WHEREAS, the condition of the obligation of this bond is that Principal has submitted its proposal or bid to an agency of the Obligee in response to Obligee’s procurement document for the project identified as:

_____________________________________________________________________ which proposal or bid is made a part of this bond by reference, and Principal is required to furnish bid security in an amount equal to ten (10%) percent of the total amount of the bid pursuant to the procurement document and ORS 279C.365(4) for competitive bidding or 279C.400(5) for competitive proposals.

NOW, THEREFORE, if the proposal or bid submitted by Principal is accepted, and if a contract pursuant to the proposal or bid is awarded to Principal, and if Principal enters into and executes such contract within the time specified in the procurement document and executes and delivers to Obligee its good and sufficient performance and payment bonds required by Obligee, as well as any required proof of insurance, within the time fixed by Obligee, then this obligation shall be void; otherwise, it shall remain in full force and effect.

IN WITNESS WHEREOF, we have caused this instrument to be executed and sealed by our duly authorized legal representatives this ________________day of _________________________, 20__.

PRINCIPAL: ______________________________ SURETY: __________________________

By________________________________________ BY ATTORNEY-IN-FACT:

Signature

Official Capacity Name

Attest: ____________________________________ ___________________________________

Corporation Secretary Signature

Address

City State Zip

Phone Fax

CONTRACT FORMS

CLATSOP COUNTY, OREGON

800 Exchange Street, Suite 410

Astoria, OR 97103

An Equal Opportunity Employer

Contract No. Click or tap here to enter text.

CLATSOP COUNTY CONTRACT FOR CONSTRUCTION

This AGREEMENT is by and between Clatsop County (“County”) and Click or tap here to enter text. (“Contractor”). Whereas Contractor has agreed to provide; NOW THEREFORE, in consideration of the sum not to exceed $ Click or tap here to enter text. to be paid to Contractor by County, Contractor agrees to perform between date of execution and Click or tap to enter a date., inclusive, the following specific services: (Attach additional information as Attachment A if appropriate or necessary)

Click or tap here to enter text.

Payment Terms: (lump sum, monthly installments, progress payments, etc. – Attach additional information as Exhibit B if applicable):

Click or tap here to enter text.

1. COMPLETE AGREEMENT. This Agreement contains the entire understanding of the parties and supersedes all prior agreements, oral or written, and all other communication between the parties relating to the subject matter of this Agreement.

2. WRITTEN NOTICE. Any notice of termination or other communication having a material effect on this Agreement shall be served by U.S. Mail on the signatories listed.

3. GOVERNING LAW/VENUE. This Agreement shall be governed by the laws of the State of Oregon. Any action commenced in connection with this Agreement shall be in the District or Circuit Court of Clatsop County. The prevailing party shall be entitled to reasonable attorney fees and costs, including an appeal. All rights and remedies of County shall be cumulative and may be exercised successively or concurrently. The foregoing is without limitation to or waiver of any other rights or remedies of County according to law.

4. COMPLIANCE. Contractor shall comply with all applicable Federal, State and local laws, rules and regulations. All provisions of ORS 279C.505 through 530 (Construction Contracts) are incorporated herein. Specifically, Contractor shall:

a) Promptly pay, as due, all persons supplying labor and material for the performance of the work provided of in such contract. If Contractor fails to pay any such claim, County may pay the claim and charge the payment against the funds due Contractor, pursuant to ORS 279C.515

b) If this contract is for a public improvement, if Contractor or first-tier subcontractor fails, neglects, or refuses to make payment to a person furnishing labor or materials in connection with the public contract for a public improvement within 30 days after receipt of payment from the County, the Contractor or first-tier subcontractor shall owe the person the amount dues plus interest commencing at the end of the 10 day period that payment is due under ORS 279C.580 and ending upon final payment.

c) Pay any required contributions due the Industrial Accident Fund incurred in the performance of the contract.

d) Not permit any line or claim to be filed or prosecuted against County, on account of any labor or material furnished by Contractor.

e) Pay the Department of Revenue all sums withheld from employees pursuant to ORS 316.167.

f) Not employ any person more than 10 hours a day, or 40 hours a week, unless permitted under ORS 279A.055, and any employee working over 40 hours per week shall be paid overtime as provided in ORS 279C.520.

g) Pay promptly, as due, any payment for medical surgical or hospital care furnished to employees of Contractor, pursuant to ORS 279C.530.

h) If Contractor is a subject employer, Contractor will comply with ORS 656.017.

i) If this contract is for a public improvement, Contractor represents and warrants that at the time of the execution of this agreement they have and shall maintain during the term of this agreement an employee drug-testing program for its employees.

j) If this contract is for a public improvement, if Contractor or a subcontractor fails, neglects or refuses to make payment to a person furnishing labor or materials in connection with this contract, the person may file a complaint with the Construction Contractors Board, subject to ORS 279C.515.

k) If this contract is for a public improvement exceeding $50,000, Contractor, subcontractor or other person doing or contracting to do any of the work of this contract will pay workers prevailing wage rates as contained in bid specifications and workers shall be paid not less than the specified minimum hourly rate of wage.

l) Contractor shall comply with all rules, regulations and ordinances of agencies of the State of Oregon, Army Corps of Engineers, Environmental Protection Agency and Clatsop County that deal with the prevention of environmental pollution and the preservation of natural resources.

m) If this contract is for a public improvement exceeding $50,000, and contractor is required to pay prevailing wages under ORS 279C.800 to 279C.870, then contractor must file a $30,000 BOLI bond with the Construction Contractors Board before starting work on a contract or subcontract. Contractor will include in every subcontract a provision requiring the subcontractor to have a public works bond filed with the Construction Contractor’s Board before starting work on the project, unless exempt.

n) If this is for a public improvement exceeding $50,000, a fee is required to be paid to the Commissioner of the Bureau of Labor and Industries as provided in ORS 279C.825. The fee shall be paid to the Commissioner under the administrative rule of the Commissioner.

o) Workers shall be paid not less than the specified minimum hourly rate of wage in accordance with ORS 279C.838 and 279C.840.

p) If this contract includes demolition, the contractor shall salvage or recycle construction and demolition debris if feasible and cost-effective. If contract includes lawn and landscape maintenance, contractor shall compost or mulch yard waste material at an approved site if feasible and cost-effective, per ORS 279C.510.

5. JUDICIAL RULINGS. If any provision of this Agreement as applied to either party or to any circumstances shall be adjudged by a court to be void or unenforceable, the same shall in no way affect any other provision of this Agreement or the validity of enforceability of the Agreement

6. INDEPENDENT CONTRACTOR. Contractor, in carrying out the services to be provided under this Agreement, is acting as an "independent Contractor" and is not an employee of County, and as such accepts full responsibility for taxes or other obligations associated with payment for services under this Agreement. As an Independent Contractor", Contractor will not receive any benefits normally accruing to County employees unless required by applicable law. Furthermore, Contractor is free to contract with other parties, on other matters, for the duration of this Agreement.

7. INDEMNIFICATION. Contractor shall save harmless, indemnify, and defend County for all any and claims, damages, losses and expenses including but not limited to reasonable attorney's fees arising out of or resulting from Contractor's performance of or failure to perform the obligations of this Agreement, to the extent same are caused by the negligence or misconduct of Contractor or its employees or agents.

8. WORKER’S COMPENSATION. Contractor shall comply with ORS 656.017 for all employees who work in the State of Oregon. If the Contractor hires employees, he or she shall provide County with certification of Worker's Compensation Insurance, with employer's liability in the minimum of $100,000.

9. NONDISCRIMINATION. No person shall be subjected to discrimination in receipt of the benefits of any services or activities made possible by or resulting from this Agreement on the grounds of sex, race, color, creed, marital status, age or national origin. Any violation of this provision shall be considered a material violation of this Agreement and shall be grounds for cancellation, termination or suspension in whole or in part by County.

10. TERMINATION OF AGREEMENT. This Agreement may be terminated under the following conditions:

a. By written mutual agreement of both parties. Termination under this provision may be immediate.

b. Upon fifteen (15) calendar days written notice by either Party to the other of intent to terminate.

c. Immediately on breach of the contract.

11. SUBCONTRACTING/NONASSIGNMENT. No portion of this Agreement may be contracted or assigned to any other individual, firm, or entity without the express and prior approval of County.

12. SURVIVAL. The terms, conditions, representations and all warranties contained in this Agreement shall survive the termination or expiration of this Agreement.

13. STANDARD OF SERVICES AND WARRANTY. Contractor agrees to perform its services with that standard of care, skill and diligence normally provided by a professional individual in the performance of similar services. It is understood that the Contractor must perform the services based in part on information furnished by County and that Contractor shall be entitled to rely on such information. However, the Contractor is given notice that County will be relying on the accuracy, competence and completeness of Contractor's services in utilizing the results of such services.

The Contractor warrants that the recommendations, guidance and performance of any person assigned under this Agreement shall be in accordance with professional standards and the requirements of this Agreement.

14. OWNERSHIP AND USE OF DOCUMENTS. All documents, or other material submitted to the County by Contractor shall become the sole and exclusive property of County. All material prepared by Contractor under this Agreement may be subject to Oregon’s Public Records Law.

15. TAX COMPLIANCE CERTIFICATION. Contractor hereby certifies, under penalty of perjury, as provided in ORS 305.385(6), that to the best of Contractor's knowledge, Contractor is not in violation of any of the tax laws of this state or political subdivision of this state, including but not limited to ORS 305.380(4), 305.620 and ORS chapters 316, 317 and 318. Contractor represents that Contract will continue to comply with the tax laws of this state and any applicable political subdivision of this state during the term of the public contract. If Contractor fails to comply with the tax laws of this state or a political subdivision of this during the term of this agreement, the Contractor shall be in default and County may terminate this agreement and pursue its remedies under the agreement and under applicable law.

16. INSURANCE. Contractor shall purchase and maintain at Contractor's expense, Comprehensive General Liability, Automobile Liability, and Professional Liability insurance. This insurance is to provide separate coverage for each of the required types of insurance at a minimum of $1,000,000 for property damage and minimum of $1,000,000 per person for bodily injury and no less than $1,000,000 for each occurrence, $2,000,000 aggregate. In addition, all such insurance, with the exception of Professional Liability, shall name County, its Commissioners, employees and agents, as an Additional Insured. A copy of the policy or certificate of insurance acceptable to County shall be submitted to County

This Agreement will not be effective until approved by the authorized signatory for County.

FOR COUNTY: FOR CONTRACTOR:

Signature Date Signature Date

Title Title

PERFORMANCE BOND

Bond No._______________________________

Solicitation _____________________________

Project Name ___________________________

__________________(Surety #1) Bond Amount No. 1: $______________

__________________(Surety #2)* Bond Amount No. 2:* $______________

* If using multiple sureties Total Penal Sum of Bond: $______________

We, ________________________________________________as Principal, and the above identified Surety(ies), authorized to transact surety business in Oregon, as Surety, hereby jointly and severally bind ourselves, our respective heirs, executors, administrators, successors and assigns firmly by these presents to pay +-unto Clatsop County the sum of (Total Penal Sum of Bond) (Provided, that we the Sureties bind ourselves in such sum “jointly and severally” as well as “severally” only for the purpose of allowing a joint action or actions against any or all of us, and for all other purposes each Surety binds itself, jointly and severally with the Principal, for the payment of such sum only as is set forth opposite the name of such Surety), and

WHEREAS, the Principal has entered into a contract with Clatsop County, the plans, specifications, terms and conditions of which are contained in the above-referenced Solicitation;

WHEREAS, the terms and conditions of the contract, together with applicable plans, standard specifications, special provisions, schedule of performance, and schedule of contract prices, are made a part of this Performance Bond by reference, whether or not attached to the contract (all hereafter called “Contract”); and

WHEREAS, the Principal has agreed to perform the Contract in accordance with the terms, conditions, requirements, plans and specifications, and all authorized modifications of the Contract which increase the amount of the work, the amount of the Contract, or constitute an authorized extension of the time for performance, notice of any such modifications hereby being waived by the Surety:

NOW, THEREFORE, THE CONDITION OF THIS BOND IS SUCH that if the Principal herein shall faithfully and truly observe and comply with the terms, conditions and provisions of the Contract, in all respects, and shall well and truly and fully do and perform all matters and things undertaken by Contractor to be performed under the Contract, upon the terms set forth therein, and within the time prescribed therein, or as extended as provided in the Contract, with or without notice to the Sureties, and shall indemnify and save harmless Clatsop County, its Commissioners and Clatsop County (name of institution and any other Owner agency), and members thereof, its officers, employees and agents, against any direct or indirect damages or claim of every kind and description that shall be suffered or claimed to be suffered in connection with or arising out of the performance of the Contract by the Principal or its subcontractors, and shall in all respects perform said contract according to law, then this obligation is to be void; otherwise, it shall remain in full force and effect.

Nonpayment of the bond premium will not invalidate this bond nor shall Clatsop County, or the above-referenced agency(ies), be obligated for the payment of any premiums.

This bond is given and received under authority of ORS Chapter 279C, the provisions of which hereby are incorporated into this bond and made a part hereof.

IN WITNESS WHEREOF, WE HAVE CAUSED THIS INSTRUMENT TO BE EXECUTED AND

SEALED BY OUR DULY AUTHORIZED LEGAL REPRESENTATIVES.

Dated this __________________ day of ___________________, 20__.

PRINCIPAL: __________________________

By____________________________________

Official Capacity

Attest: ________________________________

Corporation Secretary

SURETY: _____________________________

[Add signatures for each surety if using multiple bonds]

BY ATTORNEY-IN-FACT:

[Power-of-Attorney must accompany each surety bond]

Name

Signature

Address

City State Zip

Clatsop County Standard Public Improvement Contract

PAYMENT BOND

Bond No. __________________________________

Solicitation _________________________________

Project Name _______________________________

__________________(Surety #1) Bond Amount No. 1: $ ___________

__________________(Surety #2)* Bond Amount No. 2:* $ __________

* If using multiple sureties Total Penal Sum of Bond: $ ___________

We, ________________________________________________, as Principal, and the above identified Surety(ies), authorized to transact surety business in Oregon, as Surety, hereby jointly and severally bind ourselves, our respective heirs, executors, administrators, successors and assigns firmly by these presents to pay unto Clatsop County the sum of (Total Penal Sum of Bond) _ (Provided, that we the Sureties bind ourselves in such sum “jointly and severally” as well as “severally” only for the purpose of allowing a joint action or actions against any or all of us, and for all other purposes each Surety binds itself, jointly and severally with the Principal, for the payment of such sum only as is set forth opposite the name of such Surety), and

WHEREAS, the Principal has entered into a contract with the Clatsop County, the plans, specifications, terms and conditions of which are contained in above-referenced Solicitation;

WHEREAS, the terms and conditions of the contract, together with applicable plans, standard specifications, special provisions, schedule of performance, and schedule of contract prices, are made a part of this Payment Bond by reference, whether or not attached to the contract (all hereafter called “Contract”); and

WHEREAS, the Principal has agreed to perform the Contract in accordance with the terms, conditions, requirements, plans and specifications, and schedule of contract prices which are set forth in the Contract and any attachments, and all authorized modifications of the Contract which increase the amount of the work, or the cost of the Contract, or constitute authorized extensions of time for performance of the Contract, notice of any such modifications hereby being waived by the Surety:

NOW, THEREFORE, THE CONDITION OF THIS BOND IS SUCH that if the Principal shall faithfully and truly observe and comply with the terms, conditions and provisions of the Contract, in all respects, and shall well and truly and fully do and perform all matters and things by it undertaken to be performed under said Contract and any duly authorized modifications that are made, upon the terms set forth therein, and within the time prescribed therein, or as extended therein as provided in the Contract, with or without notice to the Sureties, and shall indemnify and save harmless Clatsop County, its Commissioners, and Clatsop County (name of any other Owner agency), and members thereof, its officers, employees and agents, against any claim for direct or indirect damages of every kind and description that shall be suffered or claimed to be suffered in connection with or arising out of the performance of the Contract by the Contractor or its subcontractors, and shall promptly pay all persons supplying labor, materials or both to the Principal or its subcontractors for prosecution of the work provided in the Contract; and shall promptly pay all contributions due the State Industrial Accident Fund and the State Unemployment Compensation Fund from the Principal or its subcontractors in connection with the performance of the Contract; and shall pay over to the Oregon Department of Revenue all sums required to be deducted and retained from the wages of employees of the Principal and its subcontractors pursuant to ORS 316.167, and shall permit no lien nor claim to be filed or prosecuted against the County on account of any labor or materials furnished; and shall do all things required of the Principal by the laws of this State, then this obligation shall be void; otherwise, it shall remain in full force and effect.

Nonpayment of the bond premium will not invalidate this bond nor shall Clatsop County, or the above-referenced agency(ies), be obligated for the payment of any premiums.

This bond is given and received under authority of ORS Chapter 279C, the provisions of which hereby are incorporated into this bond and made a part hereof.

IN WITNESS WHEREOF, WE HAVE CAUSED THIS INSTRUMENT TO BE EXECUTED

AND SEALED BY OUR DULY AUTHORIZED LEGAL REPRESENTATIVES:

Dated this ___________________day of _____________________, 20__.

PRINCIPAL: _________________________

By __________________________________

Official Capacity

Attest: _______________________________

Corporation Secretary

SURETY: ____________________________

[Add signatures for each if using multiple bonds]

BY ATTORNEY-IN-FACT:

[Power-of-Attorney must accompany each bond]

Name

Signature

Address

City State Zip

SELECTION OF RETAINAGE OPTION

(ORS 279C.560)

WHEREAS, the Contractor either intends to enter or has entered into a certain contract with the Clatsop County for Westport Road Improvements Project.