24 Amendment 47PB0025R0037 0004 2026 05 12.pdf
PDF 687 KB Posted
- Solicitation number
- BLDG107
- Issued by
- Not on record
About this file
This is Amendment 0004 to a federal construction solicitation (47PB0025R0037) issued by the PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division, effective May 12, 2026. The amendment updates the solicitation and extends key deadlines for proposal submission on Building 107 renovation work at a National Park Service facility in Boston.
The primary changes include: (1) extension of the Request for Clarifications and Interpretations deadline from April 27, 2026 to May 20, 2026 by 2:00 PM EST; (2) extension of the proposal due date from May 28, 2026 to June 4, 2026 by 2:00 PM EST; (3) provision of updated Specifications (Addendum 1, 25 documents, 91 pages dated May 12, 2026); (4) provision of updated Drawings (Addendum 1, 26 documents, 55 pages dated May 12, 2026); (5) provision of Supplemental Clarifications document (27, 8 pages dated May 12, 2026); and (6) provision of additional reference documents including a Demo 2nd Floor Masonry Infills report and Roof & Stabilization Field Investigation Report. An additional mandatory site visit is scheduled for May 19, 2026 at 9:30 AM, requiring RSVP to vanessa.colquitt@gsa.gov. The amendment includes 125 RFI responses addressing technical, procurement, scheduling, personnel, insurance, permits, specifications, and design clarification questions regarding scope, responsibilities, material sourcing, LEED Gold certification requirements, security clearances waiver, CUI document handling, and contract performance periods tied to Notice to Proceed issuance. All other terms and conditions remain unchanged.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Description of Modification Continuation Page
3. Provide updated Drawings: 26 Addendum 1 Drawings 2026 05 12 Pages 55.
4. Provide Supplemental Clarifications Document: 27 Supplemental Clarifications 2026 05 12 Pages 8.
5. Provide Document: 28 Demo 2nd Floor Masonry Infills 2025 10 23 Page 1.
6. Provide Document: 29 Roof & Stabilization Field Investigation Report 2022 01 26 Pages 47.
The due date for proposals is extended from May 28th, 2026 to June, 4th, 2026 by 2:00 PM EST.
RFI's have been extended to May 20th, 2026 by 2:00PM EST.
An additional site visit will be provided on Tuesday, May 19th, 2026 at 9:30am. Please email vanessa.colquitt@gsa.gov to RSVP.
All other terms and conditions remain the same.
47PB0025R0037/0004
RFI # RFI Response 01 Item 13.d. is blank on the SF1442. Please provide the bid hold period for this proposal.
60 Days.
02 II.D Technical Proposal: The definition of a similar project for past performance includes projects “completed, or at least 50% complete with construction, within the last 8 years of the proposal due date” (Solicitation, page 9 of 52). Please confirm that the current due date of May 28, 2026 will be considered the “proposal due date” for purposes of this 8-year timeline, even if the proposal due date is extended.
Confirmed.
03 Under the Experience and Past Performance evaluation factors, will the Government consider relevant past performance of affiliated sister companies where the offeror demonstrates that such affiliates will have meaningful involvement in contract performance?
The Government will evaluate past performance in accordance with Factor 3 of the solicitation. Offerors are required to submit up to three (3) Similar Projects performed by the offeror. As stated in the solicitation, the Government may consider past performance information from a variety of sources, including those related to team members, parent companies, subsidiaries, or affiliates identified in the offeror’s proposal. However, the solicitation does not provide for the submission of affiliate projects in lieu of the offeror’s required Similar Projects. The extent to which any such information is considered, and the weight it is given, will be determined by the Government based on its relevance to the effort.
04 Factor 1 – Project Management Plan/Schedule, Submittal Requirements (page 10 of 52): is the CPM schedule excluded from the 45-page limitation for the Technical Proposal?
Factor 1 submittal requirements is not excluded from the page limitation for the technical proposal. The technical proposal page limitation is increased to 60-pages.
05 Will the government accept previously completed Past Performance Questionnaires signed by our customer references for past performance projects submitted on this contract?
Offerors may resubmit questionnaires previously submitted with other proposals or may obtain an updated/new PPQ or CPARS from a client for any submission.
Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.
06 The Solicitation states on page 12 of 52, “The offeror may submit any of the following to satisfy the proposal’s submittal requirement for past performance: 1. the past performance questionnaire (PPQ) (included as an attachment to the RFP), completed by the client/owner reference, for projects the offeror selected to submit for past performance; or 2. a completed evaluation in the Contractor Performance Assessment Reporting System.”
However, the Solicitation states on page 13 of 52 “The Offeror must submit a Past Performance Questionnaire (PPQ) (included in the solicitation as Attachment 7), completed by the applicable client, for each project included in its proposal for Factor 3.” Please confirm that a PPQ is not required when a CPAR is available and can be submitted with our proposal.
Confirmed. The offeror may submit any of the following to satisfy the proposal’s submittal requirement for past performance:
1. the past performance questionnaire (PPQ) (included as an attachment to the RFP), completed by the client/owner reference, for projects the offeror selected to submit for past performance; or
2. a completed evaluation in the Contractor Performance Assessment Reporting System.
07 Please confirm that CPARs submitted for past performance are excluded from the 45-page limitation for the Technical Proposal.
CPARS submitted for past perfromance are not excluded from the page limitation for the technical proposal. The technical proposal page limitation is increased to 60-pages.
08 Can the government provide Attachment 7 (PPQ) in Word format or in fillable PDF format?
Uploaded PPQ word format on 5/7/2026.
09 Please confirm that any “performance recognition documents” (solicitation, page 13 of 52) submitted with our proposal will be excluded from the page limitation for the Technical proposal.
Performance recognition documents under factor 3 is not excluded from the page limitation under the technical proposal submittal requirements. The technical proposal page limitation is increased to 60-pages.
10 Which specific drawings, specifications, or other project documents issued with this solicitation are designated as CUI?
"The following technical documents have been labeled ""CUI"" and uploaded to sam.
gov under Amendment 0003.
Technical Documents 10)Specifications – DATED - 2025 10 31 – 2034 Pages 11)Drawings – DATED - 2025 10 13 – 376 Pages12)Fixed Furniture Book – DATED - 2025 10 13 - 78 Pages13)Lighting Fixture Schedule – DATED - 2025 10 08 - 4 Pages14)Lighting Fixture Schedule BOH (back of house) – DATED - 2025 10 08 - 1 Page15)Wayfinding Signage Concepts – DATED - 2025 10 13 - 111 pages16) Geotechnical Design Memorandum – DATED - 2024 07 30 - 21 pages17) Geotechnical Report – DATED - 2024 03 05
- 59 pages18)Pre-Renovation Hazardous Material Survey – DATED - 2019 03 29 - 63 pages 19) Statement of Structural Tests and Special Inspections – DATED 2025 04 25 - 5 pages
20) Terracon Phase 1 Environmental Site Assessment – DATED 2025 10 23 - 1,608 pages"
11 What CUI category and/or subcategory applies to the designated documents (e.g., Physical Security, Critical Infrastructure, Proprietary Building Information)?
"CUI" Basic
12 Will the Government issue revised documents with the required CUI markings (banners, portion markings, and designation indicators) in accordance with 32 CFR Part 2002 and the CUI Marking Handbook?
Revised documents have been uploaded to sam.gov under amendment 0003 with the required CUI Markings.
13 For the Technical Proposal, do Factors 2 and 3 need to be the same 3 Similar Projects?
Yes. Solicitation page 11 under Factor 2.
"Note: Reference “Definitions” above in the “Technical Proposal” section. Offerors must not submit more than three (3) Similar Projects to satisfy the submittal requirements of both evaluation Factor 2 and Factor 3."
14 In order to effectively review and coordinate with the bidding subcontractor pool, we request the RFI due date be extended from April 27, 2026 to May 29, 2026
No
15 In order to effectively review and coordinate with the bidding subcontractor pool, we request the Proposal Submission due date be extended from May 28, 2026 to June 26, 2026
No
16 SF 1442 Box 10 Performance of Work statement states that the Project will be pursuing LEED Certification (Level TBD). Please confirm what level of certification should be assumed for bidding purposes.
LEED certification is a requirement, and the project is designed to achieve Gold certification. Project team will review the design scoresheet with the GC after award.
17 SF 1442 Box 13d does not specify the window required to hold a bid for Government acceptance. On the Pre-bid call there was a reference to contractors holding their proposal for 60 days. Please confirm this number of calendar days.
60 Days.
18 SF 1442 line items' period of performance is Feb 2026 to Feb 2028. Please confirm dates will align with NTP issuance.
Please see the Agreement I.C. Period of Performance. (1)Commencement. The Contractor shall commence performance within 10 days after the Contractor receives the Notice to Proceed (NTP).
(2)Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 700 calendar days fromissuance of Notice to Proceed (NTP).
(3)Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 30 calendar days of Substantial Completion.
19 Solicitation section II.A Proposal Contents lists a requirement for #5 Subcontracting Plan, whereas Section IV's last paragraph entitled Small Business Subcontracting plan states that A Small Business Subcontracting Plan, as required under FAR 52.219-9, is not required to be submitted with offers. Please confirm whether a Small Business Subcontracting plan is required, and what if any subcontractor participation goals are required.
The plan is required from the apparently successful offeror prior to contract award, not with the initial proposal. Please see GSA's subcontractor small business goals https://www.gsa.gov/small-business/get-started.
20 Document 01, Solicitation Section II.D (Technical Proposal) indicates that “all other pages (including the cover page) are included in the page limitation.” To improve clarity and organization of the response, may the cover page, table of contents, and section tabs be excluded from the page limit?
The technical proposal page limitation is increased to 60-pages inclusive of cover page, table of contents, and section tabs.
21 Solicitation section III.H states that "Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI)".
It is not readily apparent what, if any, documentation is considered CUI. Please confirm the documents designated as CUI, or confirm that this is not applicable, considering that the inclusion of CUI significantly increases the compliance requirements and may limit the pool of contractors able to participate in the project.
Revised documents have been uploaded to sam.gov with the required CUI Markings under Amendment 0003. See question 11 for the revised documents.
22 Please confirm whether previously completed CPARS and PPQs may be submitted, or if new ones must be obtained.
If a CPARS has already been completed for a project, would that be sufficient to satisfy the Factor 3 – Company Past Performance submittal requirement?
Offerors may resubmit questionnaires previously submitted with other proposals or may obtain an updated/new PPQ or CPARS from a client for any submission.
Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.
23 Please confirm whether the Future Building 108 Development site, plan west of the building on sheet G8, is available for Contractor use. If not, please confirm locations designated by park staff as defined in 01 11 00 1.6.C.
Yes. NPS and BPD are developing a license agreement to allow contractor use of the 108 parcel. The license will include a 60 day notice to vacate should the developer holding the option on the site obtains financing to proceed with their development plan
24 What does UCI mean on the docs uploaded to SAM.Gov? Controlled Unclassified Information (CUI) is sensitive, non-classified federal information requiring safeguarding or dissemination controls. It is created or possessed by the government (or contractors) and, while not classified under Executive Order 13526, must be protected according to laws and policies, often managed via NIST SP 800- 171.
25 Unclassified Control Information? Can I send these docs to my subs who are bidding? Do the subs need to sign non disclosure form provided? I believe we have to sign (the offerer) and send to you prior to submission, correct?
Yes, contractors registered on SAM.gov are authorized holders and may share solicitation documents marked as Controlled Unclassified Information (CUI) with potential subcontractors for a lawful government purpose, such as bidding.
Please adhere to the following security requirements:
- Email Distribution: Any documents sent via email must be password protected.
- Physical Copies: Documents must be kept in a secured location and protected by a physical barrier, such as a folder or a locked cabinet, when left unattended. Any printed documents must be shredded after use.
- Direct Access: Alternatively, subcontractors may register to access the documents directly via SAM.gov.
Please note that CUI replaces former designations such as "For Official Use Only" (FOUO) and "Sensitive But Unclassified" (SBU). A non disclosure form is not required to share CUI marked documents for this solicitation.
26 Also, provided checklist says submit subcontracting plan, however in the solicitation under subcontracting section states not needed at this time. Please clarify if we should submit one with this submission or wait until after award.
The plan is required from the apparently successful offeror prior to contract award, not with the initial proposal.
27 Please identify lay down areas that will be available for contractor use throughout the project.
See response to RFI #23
28 The solicitation states a Subcontracting Plan is required under Section II.A. Proposal Contents but page 31 of the solicitation states A Small Business Subcontracting Plan is not required to be submitted with offers. Please confirm a Subcontracting Plan is not required with proposal submission. If a plan is required please identify the percentage goals for each category?
The plan is required from the apparently successful offeror prior to contract award, not with the initial proposal. Please see GSA's subcontractor small business goals https://www.gsa.gov/small-business/get-started.
29 Please advise if the existing service elevator is operational and can it be used for start of construction? When is MA State Elevator Certificate valid to and will owner keep it valid until required to be taken out of service by the project?
Yes. NPS is not required to have a MA cert.
GC will assume all responsibility for use once NTP is provided.
30 Is land at 108 third ave available for laydown area on the exterior if any disruption is repaired and brought back to original state by the general contractor?
See response to RFI #23
31 Confirm no restriction on property labeled as Charlestown Ropewalk, LLC available to use for laydown area beyond construction zone as long as pedestrian walk way is maintained along Bldg 58.
Yes. NPS and BPD are developing a license agreement to allow contractor use of the Ropewalk parcel. Please be advised that any subsurface work in this area will be limited due to the presense of underground utilities. Ropewalk parcel owner will retain right of review for laydown plans.
32 Please confirm whether it is the intent that all construction personnel be required to obtain a GSA Access Card in accordance with the Personal Identity Verification Requirements clause referenced on page 27 of the Contractor Agreement.
GSA will not be requiring HSPD-12 clearances or issuing PIV cards for this project. Once the site is turned over to the GC, site secutiry will be contractor responsibility. Post-occupancy security review, if necessary for punchlist work, will be handled locally by NPS. The contractor will be expected to maintain a daily log of personnel accessing the site and provide access for review by the CMa if requested.
33 Archaeological Protection. Are any of the areas to be disturbed as part of the project considered Archaeologically Sensitive Areas requiring an archaeological monitor. If monitoring required will it be furnished by the government or indpendent contractor hired by the general contractor and if required what are requirements? ie daily?
No. If monitoring is required, this will be provided by the government. See specs Section 01 34 13.22
34 Please clarify scope to be priced for Solicitation Item No.
0003. Planting schedule and/or landscape / hardscape details have not been provided.
Planting schedule and landscape/hardscape details to be provided by GC. Landscape contractor to provide Design Build services.
35 There is a note on the bottom left that says that doors “WD-W” are to be by ‘Interior Glazed Partition Contractor”.
We do not find any doors marked “WD-W”?
No drawing indicated in RFI - A/E assumes the question is regarding this note on sheet
A6.8, "NOTE: WOOD DOORS WITH
VENEER FINISH (E.G. WD-W) SHALL BE
PROVIDED BY THE INTERIOR GLAZED
PARTITION CONTRACTOR, INCLUDING
WOOD DOORS IN HOLLOW METAL
FRAMES. CM TO COORDINATE DOOR
HARDWARE CONTRACTOR AND
INTERIOR GLASS PARTITION
CONTRACTOR."
WD-1 might be a better example - A/E will update drawings accordingly.
Contractor to refer to finish schedule for veneer finishes. Follow instructions in note for all doors with veneer finish.
36 Doors Type A & B show a dotted line which indicates to provide glazing where shown on schedule. We do not find any notes regarding glazing.
OK
37 Doors 202B & 319 are to be STC51 rated but we do not find any specifications on STC doors.
Door 202B does not require STC51 rating.
Door 319 does require STC51 rating. A/E will update construction documents accordingly. BOD for STC51 door is QuietStar IAC NoiseLock Doors or Noise Barriers Quiet Swing Doors.
38 Please provide who the Fire Alarm company on record is. Ellis Fire Portection Company is the company on record. Mfg for new system req'd to match campus system: EST
39 Reference Amendment 0003. We have successfully downloaded ten (10) of the eleven (11) CUI‑marked files issued as part of Amendment 0003 to our secure enclave.
However, one file appears to be missing and remains unavailable for download: “Attachment 11 – Drawings dated 2025‑10‑13 (11 Drawings 2025 10 13.pdf).” Please provide the missing file or confirm when it will be made available to ensure bidders have access to the complete and current set of solicitation documents.
The file has been availble and ready to request access since amendment 0003 was issued. CO has confirmed you have access.
40 "Reference Amendment 0003. Eleven (11) files, identified as Attachments 10 through 20, were deleted from SAM.
gov and subsequently re issued, with the exception of Attachment 11 (Drawings dated 2025 10 13, 376 pages).
The re issued documents now include Controlled Unclassified Information (CUI) markings at the top of each page, whereas the previously posted versions did not.
Please clarify the following:
CUI Applicability Review:
We formally request the Government conduct and confirm a review of all re issued attachments currently marked as CUI to verify whether CUI designation is appropriate and necessary for each document, consistent with applicable CUI guidance and criteria.
Document Supersession and Authorized Use:
Confirm whether the previously posted, unmarked versions of the re issued attachments are fully superseded and no longer authorized for use, and whether bidders are required to rely solely on the re issued CUI marked documents for proposal preparation, pricing, and subcontractor solicitation.
Safeguarding and Handling Requirements:
For any documents that remain designated as CUI, please clarify the specific safeguarding, handling, storage, and distribution requirements bidders and their subcontractors must comply with when accessing and using these materials.
Disposal of Previously Issued Unmarked Documents:
Provide direction regarding the proper destruction or deletion of any electronic and hard copy versions of the previously issued, unmarked attachments that may have been downloaded, printed, or distributed prior to re issuance. Please clarify whether certified deletion, document destruction, or other disposition actions are required, and whether bidders must confirm compliance.
Industry and Subcontractor Availability Impact:
Additionally, please advise whether the Government has considered the likely impact on competition should all re issued documents remain designated as CUI. Broad application of CUI markings may significantly limit bidders’ ability to solicit and engage subcontractors, as a substantial portion of the subcontractor marketplace is not currently compliant with CUI safeguarding requirements.
This condition could adversely affect pricing, schedule, overall bid participation, and project execution."
"Yes, contractors registered on SAM.gov are authorized holders and may share solicitation documents marked as Controlled Unclassified Information (CUI) with potential subcontractors for a lawful government purpose, such as bidding.
Please adhere to the following security requirements:
- Email Distribution: Any documents sent via email must be password protected.
- Physical Copies: Documents must be kept in a secured location and protected by a physical barrier, such as a folder or a locked cabinet, when left unattended. Any printed documents must be shredded after use.
- Direct Access: Alternatively, subcontractors may register to access the documents directly via SAM.gov.
Please note that CUI replaces former designations such as ""For Official Use Only"" (FOUO) and ""Sensitive But Unclassified"" (SBU). A non disclosure form is not required to share CUI marked documents for this solicitation.
41 The Solicitation indicates that Requests for Clarification or Interpretation are due by April 27, 2026. Given the significant volume and complexity of documents associated with this project, we respectfully request that the deadline for submitting questions be extended by three (3) weeks. This additional time will allow Prime Contractors and their Subcontractors to complete a thorough review of the solicitation documents and submit informed and meaningful clarifications.
Request for Clarifications and Interpretations has been extended to May 20th, 2026 by 2:
00 PM EST.
42 The Solicitation identifies May 28, 2026 as the proposal due date. Should certain RFP documents remain designated as Controlled Unclassified Information (CUI), additional time will be required to identify, evaluate, and engage subcontractors that are compliant with CUI safeguarding requirements. Accordingly, we respectfully request that the proposal due date be extended by a minimum of four (4) weeks to allow sufficient time for compliant subcontractor outreach, coordination, and proposal development.
The proposal due date has been extended to June 4th, 2026 by 2:00 PM EST.
43 Please confirm whether the full AV, Security, and Telecommunications scope is included under the Electrical Subcontractor, or if only the boxes, raceways, and pull strings shown on the Electrical Drawings are part of this contract, with the balance by others. On some prior federal projects, portions of this work have been performed by separate Government-retained contractors, so we request clarification on the intended scope for this project.
Security and Telecom system are 100% included in contract. The AV system boxes, raceways and pull strings by contractor;
equipment and cable will be furnished and installed by NPS.
44 There is no notation of BFE or DFE on the drawings, so I don’t know how tall the flood protection needs to be. Can you please confirm the required height?
Height of flood barriers to match the height of existing granite water table. See Building Elevations.
45 The solicitation doc says it's not required to be submitted with offers, but the proposal contents checklist in Section II. A lists the subcontracting plan as one of the required submission docs. Please clarify
The plan is required from the apparently successful offeror prior to contract award, not with the initial proposal.
46 Is there an intent to utilzie exisitng slate that gets demolished ?
Yes - for interior finish. Refer to finish schedule. Note: not ALL roofing slate needs to be reclaimed.
47 Permitting: Can you please indicate if there are any permits anticipated to be procured by owner?
Refer to Supplemental Clarifications included as part of Ammendment 04.
48 Permitting: Are there any special permits required by the GC beyond typical: ISD, BFD, DPW, DEP.
Refer to Supplemental Clarifications included as part of Ammendment 04.
49 Within the bid documents provided the bidders received the documentation listed below. Can you please confirm if all of these items should be priced and included by the bidder? Or if there are some items to be purchased and managed by owner? i.Fixed Furniture Plan ii.Lighting & BOH Lighting Plan iii. Wayfinding and Signage
Confirmed
50 For the purposes of our “Project Management Plan” Is there a milestone schedule, or desired construction start date of completion date that this project is aiming for? i.
Please list any important milestones that are important.
See RFI #18.
51 For the purposes of our “Project management Plan”, are there any locations that will be off-limits for lay-down space or loading.
Refer to RFI #23 and #31 for adjacent project areas available for contractor use.
52 Are there any easements or property information that would be pertinent for storage of materials during construction.
Refer to RFI #23 and #31 for adjacent project areas available for contractor use.
53 Will the GC be required to carry any additional testing for ACM or other harmful environmental concerns, beyond what has been shared as part of this RFP.
Refer to Supplemental Clarifications included as part of Ammendment 04.
54 Will the GC be required to carry disposal of ACM containing soil?
Yes.
55 For the Technical Proposal, do Factors 2 and 3 need to be the same 3 Similar Projects?
Yes. Solicitation page 11 under Factor 2.
"Note: Reference “Definitions” above in the “Technical Proposal” section. Offerors must not submit more than three (3) Similar Projects to satisfy the submittal requirements of both evaluation Factor 2 and Factor 3."
56 On the Sam.gov viewing portal Wise Construction does not have clear visibility into all documentation listed. We also can’t see ourselves on the list of interested vendors.
Please see the notification below.
Interested vendors list has been enabled through the solicitation within sam.gov.
Please reach out to the CO with any further issues.
57 We experienced difficulty in accessing and opening the CUI documents on the SAM.gov site for several days.
Would GSA be agreeable to extending the deadline for Request for Clarifications and Interpretations to Friday, 5/1/2026?
Request for Clarifications and Interpretations has been extended to May 20th, 2026 by 2:
00 PM EST.
58 Please indicate when Notice to Proceed (NTP) will occur within the 730 calendar day (CD) period of performance.
Does NTP occur after GSA has approved project plans or upon contract award?
See RFI #18.
59 Specification 01 11 00 Section 1.6 C. Storage of Materials states "Confine storage of materials, field offices, equipment storage, trailer storage and parking to areas approved by Contracting Officer." Will this include possible use of the empty lot at 3rd and 8th adjacent to the Site and additional area between the Ropewalk Building and Building 107?
Refer to RFI #23 and #31
60 Specification 01 11 00 Section 1.12 A. states normal business working hours of 8:00am to 4:30pm. Would GSA/NPS be agreeable to starting at 7:00am and off hours/weekends if needed?
City of Boston regular construction hours are 7 AM to 6PM weekdays. Due to the proximity of residential abutters, work requests outside these hours will be dependent on review by federal and local authorities. Additionally, The Boston Municipal Code sets standards for reasonable noise levels. It also sets maximum acceptable noise levels for different times of day. An unreasonable level of noise is anything louder than 70 decibels at any time, except for permitted construction. Compliance with these requirements is a condition of the contract.
61 Drawing Sheet C1-0 Proposed Demolition shows that the existing concrete sidewalk along Third Avenue will be removed and replaced. Is this a City of Boston owned sidewalk requiring City permitting/approval?
Yes
62 Can work such as site prep and demolition commence before all work plans are submitted and approved?
Work can proceed once NTP is issued.
63 Please indicate where the information required in RFP Section II. E (Other Information to Submit with Proposal) should be included, i.e., in Price Proposal or Technical Proposal? And we assume this information does not count toward the 45 page limit, correct?
Other information to submit with proposal is not a submital for the technical proposal and does not count toward the technical proposal page limit. The technical proposal has been increased from 45-pages to 60-pages.
64 Please clarify where the JV Agreement is to be included in our proposal (i.e., Price Proposal or Technical Proposal).
If included in the Technical Proposal, please confirm it is excluded from the 45-page limitation as it would require up to 50% of the allotted 45 pages.
The JV agreement is not a submittal requirement for the technical proposal therefor isn't apart of the 60-page limitation.
65 Solicitation Section II.E. Other Information to Submit with Proposal (2) Qualifications of Offerors page 14 of 51.
Does GSA Form 527 – Contractor’s Qualifications and Financial need to be submitted for each JV member/partner? If so, can the information be submitted directly to GSA? If so, to whom and how?
Please ensure that a GSA Form 527 is submitted with the proposal for each Joint Venture member or partner.
66 The RFP currently does not exclude the Reps & Certs from the page limitation…we’re assuming this would be included as part of the Price Proposal and therefore excluded from the 45-page limitation?
The Reps & Certs is not a submital of the technical proposal and is excluded from the 60 page limitation.
67 Do the three example Similar Projects required in Factor 2, Company’s Experience, need to be the same Similar Projects required in Factor 3, Company’s Past Performance?
Yes. Solicitation page 11 under Factor 2.
"Note: Reference “Definitions” above in the “Technical Proposal” section. Offerors must not submit more than three (3) Similar Projects to satisfy the submittal requirements of both evaluation Factor 2 and Factor 3."
68 If additional key personnel beyond the Project Manager and Onsite Superintendent are provided in our proposal, will the additional personnel be considered more favorably from an evaluation perspective?
At a minimum, the key personnel for the project must consist of the following positions: Project Manager On-site Superintendent
69 Are a Table of Contents and/or List of Figures required for the Technical Proposal? If so, can they be excluded from the page limitation? Also, please consider excluding the proposal cover from the page limitation.
The technical proposal page limitation is increased to 60-pages inclusive of cover page, table of contents, and section tabs.
70 RFP Section II.F (Requirements of Joint Venture Offerors), paragraph (4) requires past performance information for each member of the joint venture. Please confirm that this past performance information is in addition to what is required in Factor 3—Company’s Past Performance. Please confirm it is not part of the 45-page limit for the Technical Proposal. Also, please indicate where this information should be provided—price proposal?
The Government will evaluate past performance in accordance with Factor 3 of the solicitation. Offerors are required to submit up to three (3) Similar Projects performed by the offeror. As stated in the solicitation, the Government may consider past performance information from a variety of sources, including those related to team members, parent companies, subsidiaries, or affiliates identified in the offeror’s proposal. However, the solicitation does not provide for the submission of affiliate projects in lieu of the offeror’s required Similar Projects. The extent to which any such information is considered, and the weight it is given, will be determined by the Government based on its relevance to the effort.
71 In the SF 1442, Section 11 indicates that the Offeror will commence performance within 14 days of NTP; however, Section I.C(1) in the Agreement indicates performance must commence within 10 days of NTP. Please clarify.
Section 11 of SF 1442 has been updated to 10 days.
72 Agreement Section III H Administrative Matters, (5) Security Clearances. Can you let us know how long the Enter on Duty (EOD), GSA Access Card, and clearance in accordance with Homeland Security Presidential Directive 12 (HSPD-12) process takes? In our experience this can be lengthy. Can this be taken into account in the PoP and consider extending the PoP by 6 more months?
See RFI #32.
73 Will work by others on the Building 108 Connector be at the same time as Building 107 Renovation work?
Yes, see Supplemental Clarifications included in Amendment 4.
74 Sheet A5.1 Typ. Roofing Build-Up states that fiberglass Z girts spaced at 24" OC will have 1/2" wood blocking to allow for slate nails to fully penetrate plywood sheathing.
Please confirm that the 3/4" plywood only between the girts is sufficient for slate nailing.
Confirmed. The wood blocking is intended to "allow for slate nails to fully penetrate plywood sheathing." Otherwise, the Z girt, and its embedded metal plate, could prevent the nail from fully penetrating the roof sheathing. Contractor to coordinate depth of blocking with depth of fasteners.
75 Spec 013323 Submittals Section 1.3 C Submittal List page
2. The spec states: "Submittal List: Submittal list is attached to the end of this Specification Section." I could not locate it at the end of the section. Please provide Submittal List or clarify its location in the Contract Documents.
No A/E list provided. A/E will update 013323 accordingly. Contractor shall provide all submittals as specified. Note: contractor shall provide a submittal schedule per 013323 1.3 A 2 and 013216. Include submittals and all procuement durations as part of the construction schedule.
76 Spec 01 40 00 - Quality Requirements & Attachment 19 Statement of Structural Tests and Special Inspections.
Please confirm which Structural Tests and Special Inspections will be completed by the Owner or Owner's Representative?
All by contractor.
77 Spec 02 80 30 Section 1.1B identifies lead abatement at approximately 50 steel beam locations. Please confirm whether additional lead‑containing substrates require abatement or disturbance controls. General Lead locations are listed, but quantities and limits are not defined.
Assume lead abatement at hot-work locations, per structural drawings.
Contractor shall include cleaning lead paint from all new steel connections per lead abatement specifications procedures. For demolition work, assume that lead-containing substrates can be disposed of as normal construction debris. See Addendum 1 drawings for select interior location for lead abatement at exposed brick walls in egress stair wells. At other lead-containing substrates, use subtrate prep methods that do not airborne lead-containing material.
78 Spec 02 80 30. Please confirm whether lead abatement is limited to areas impacted by hot work, or if lead removal/stabilization is required in all demolition areas.
Specifications address hot work but are ambiguous for non‑hot‑work demolition.
See response to RFI #77.
79 Please confirm the government's process and turnaround time for manifest signatures (hours of availability, who signs, and how to handle weekend/off-hours loads if approved)
Contractor is required to provide compliance with state and local regulations
80 We are requesting at least (1) additional walk-through be provided. We have had a number of subcontractors reach out with interest in walking the building over the coming weeks that were unable to attend the initial visits
An additional site-visit is scheduled for May 19th, 2026 at 9:30 AM.
81 We are requesting an RFI extension to at least 5/18 in lieu of the current date of 4/27 to allow for further review of the documents and subcontractor feedback
Request for Clarifications and Interpretations has been extended to May 20th, 2026 by 2:
00 PM EST.
82 We are requesting a bid extension to at least 6/11 in lieu of the current 5/28 due date
The proposal due date has been extended to June 4th, 2026 by 2:00 PM EST.
83 Confirming that a Builder's Risk Policy is not required to be carried the General Contractor for this project
The Solicitation does not require contractors to obtain builder's risk insurance. However, per FAR clause 52.236-7, the contractor is responsible for all damages to persons or property resulting from their fault or negligence. The contractor is also responsible for all materials delivered and work performed until the entire project is completed and accepted.
Additionally, the contractor must obtain and maintain the insurance coverages required under FAR 52.228-5, Insurance – Work on a Government Installation, GSAR 552.228-5, Government as Additional Insured, and Section III.F. of the Agreement, including:
- Workers' compensation insurance
- Broad form comprehensive commercial general liability insurance
- Comprehensive automobile liability insurance
- Professional liability insurance
Please refer to Section III.F. of the Agreement for specific coverage details.
84 Confirming that the costs for temporary utility usage (water, power, etc.) is by Owner and not to be included by the General Contractor
See Supplemental Clarifications included in Amendment 4.
85 Confirming that costs for a P&P bond are required to be carried by the General Contractor
Yes , costs of bonding required pursuant to the terms of the contract are allowable.
86 Confirming that 3rd party testing and inspections are by owner
Refer to RFI #76
87 Confirming that commissioning provider (CxP) and comissioning provider costs are by the owner and not by the General Contractor
Confirmed. By owner.
88 Detail 2/S4.3 calls for "New masonry to replace unsound brick and build back top of multi-wythe wall". This callout is noted on S1.2 and S1.3, but not on S1.4 (although the detail appears to show the roof lien adjacent to this location). Are we to assume this detail applies to the entire wall length on S1.2 and S1.3? Additionally, are we to assume the entire across shown on the detail should be replaced with new brick?
Brick repair should be assumed at entire perimeter of building at top of wall where it intersects the roof. A/E and contractor should review conditions after demolition of roof and identify areas where rebuilding is not required. Call-out should be only on S1.
3, will revise S1.2 in bid addendum to prevent further confusion.
89 Keynote 07-11 on A1.1, A1.2, A1.3 notes to "Prep masonry as required for fluid applied air-water barrier".
Please clarify the extent of prep work required. Are we to assume a new parge coat across the entire inside face of these walls?
Extent is at interior face of all existing perimeter walls, UON. For preparation requirements, refer to section 072700 Vapor Permeable Air Barrier Liquid Membrane, 3.2 Surface Preparation. Also refer to manufacturer's installation instructions. A/E does not recommend assuming a new parge coat across the entire face of these walls as suggested.
90 The model # for the ice dispenser indicates a unit with remote refrigeration. Please clarify if remote refrigeration is required, or if a self-contained unit would be acceptable.
If remote refrigeration is required, please clarify the location of the remote condenser
See M3.1B for location of remote condenser unit.
91 Regarding the same ice dispenser, is the intent for this to sit on top of an ice bin? There is nothing specifing what this unit will sit on top of
Yes, include bin option from ice dispenser manufacturer for complete free-standing functional unit.
92 Within the summary of work spec section 011100 it notes that "work includes fixed furniture, including workstations and tables - it does not include loose or non-fixed furniture". Confirming the intent is for the GC to supply and install all items noted in the Fixed Furniture Book - in addition to work stations and tables this appears to include book shelves, lockers, trash enclosures, benches, credenzas, etc.
Confirmed. The work shown in the Fixed Furniture Book is by the GC.
93 Please clarify the Controls company of record, if there is one. If so, please also provide a contact
See Supplemental Clarifications included in Amendment 4.
94 Please clarify the Fire Alarm company of record, if there is one. If so, please also provide a contact
See Supplemental Clarifications included in Amendment 4.
95 01 11 00 - 1.12.C.3: Provide allowable utility-shutdown windows, currently TBD.
GC means and methods
96 Pleaese identify if required to list Key Trades for the project and where to list them and if requried to provide any qualifications? Some of the key trades we feel would be important are Historic Masonry, Slate Roofing, HVAC, Electrical, and Windows, but please advise.
This is at the discretion of the offeror.
Additionally, the approach to the project can be addressed in the desired level of detail within the project management plan / narrative.
97 064023-2.9: What is the current condition of the wood used to produce AWP-1, SWS, WD-2, WSF-1, and WSF- 2?
Stockpile of existing material is stored on site at the CNY Hoosac Warehouse site.
98 064023-2.9: Where is the reclaimed wood mentioned in RFI-A 14.00 currently stored?
Stockpile of existing material is stored on site at the CNY Hoosac Warehouse site.
99 064023-2.9: Can you confirm that the pine was reclaimed from the Hoosac Stores Beams, as specified?
Yes. Historic timbers are stacked and covered but will need to be inspected, and milled for use.
100 064023-2.9: What are the current dimensional specifications and quantities reclaimed?
This question is unclear but we assume this is referring to the reclaimed Hoosac Stores Beams. The size and quantity for these timbers are as follow:
- 8" x 15" x 15', 100 total
- 10" x 15" x 15', 100 total
101 A1.2: What are the floating rectangles at 235 and 237A? Graphical error. These were part of typical workstation furniture. Will remove from A1.
2.
102 WD-10 Baltic birch plywood with clear finish and exposed clear-finished edges is called for several cabinet interiors.
If these are exposed to moisture they will cause warranty issues. Please confirm this is the desired product and if warranties will be waived for these locations since the product is susceptible to warping.
Cabinet interior components whose edges are not visible could be different composition with veneer to match WD-10, however visible edges should be as specified.
Alternate products may be submitted for review. Warranty requirements will not be waived.
103 06-93/A4.5 & 8/A4.5A: Is the WD-2 at the vertical Stairs on A4.3 going to be a vertical .75” x 10” T&G? OR is this a cable system per 8/A4.5A. Also see cross section at Main Stairs on 3/A4.3
The WD-2 at the vertical stairs on A4.3 refers to a "RECLAIMED WOOD
GUARDRAIL - 10" WIDE WD-2 PLANKS
ADHERED TO PLYWOOD CORE." WD-2 is not a cable system.
104 09-24/A4.61 - A4.62, A5.4 - A5.6 & A5.50 - A5.51: Please confirm 09-24 interior poplar wood trim is to be by the millworker.
Confirmed.
105 4-5/A5.54: Who is picking up the Acoustic panels glued to the bottom of the slab above?
GC means and methods.
106 10/05/A1.1 - A1.3: Are the Vitrine cabinets (display cases) millwork or Division 10 as noted?
The vitrine cabinets are custom millwork items.
107 GL-6 & 1/A5.55: Please confirm if detail 1/A5.55 edge trim applies to all GL-6 locations?
Detail 1/A5.55 applies at Room 104 and 206 as indicated on RCPs and also per title of detail.
108 02-71/X1.4: Please confirm only 150 SF of slate must be salvaged for re-use.
Contractor is responsible for quantity take-offs.
109 024119: Please confirm all interior wall partitions noted to be removed by dashed lines are non-load bearing.
A/E assumes contractor is referring to demolition plans, X1.1 to X1.4. Typically the answer is yes, but there are exceptions.
Note that "vault" walls are assumed to be load bearing. (See S1.2 and note 04-12 on X1.1 and X1.2 )
110 011100-1.4.2.: Will a furnishings schedule be provided to define which loose furniture is by owner and which work-stations and tables are furnish and installed by the GC?
See RFI #92.
111 020810 -1.7.C: Confirm scope boundary for presumed ACM at roof level. Will this be unit priced and pay as found?
No unit pricing. See January 26, 2022 Building 107 Field Investigation and Assessment Draft Report included in Ammendment 4. Assume slate shingles are nailed directly to concrete and do not have ACM. For all other roof work, abate ACM at roof level per hazmat specificaitons.
112 Confirm AV equipment-supplied-by-others cable routing:
does NPS provide cable schedule for GC conduit sizing
Conduit size is indicated on AV4.1 AudioVisual Low Voltage Conduit Schedule.
Contractor is to coordinate on site quantity and placement. Contractor shall provide all lengths of conduits, pull boxes and required components necessary to achieve a complete installation. See AV drawings.
113 313000 -1.2.B.7: Confirm pile head connection design responsibility: SER (Tylin) vs. Specialty Contractor
The pile and its components are by the pile contractor. We require the uplift capacity of the pile and have designed/detailed the pile to resist this load, but it will require coordination with the final pile design determined by the pile contractor.
114 F3.1A, F3.2A & F3.2B: The sprinkler heads along the perimeter of the smoke baffle on drawings F3.1A, and F3.
2A & B have a symbol that is not listed on the sprinkler head schedule. Can you tell me what type of sprinkler heads to carry?
Sheet F0.2 updated. Sprinkler heads shown are exposed pendent sprinkler heads. See Addendum 01 drawings.
115 Drawing P3.1B identifies a P-4 sink in Custodial 137, but it is not identified on the fixture schedule on drawing P6.1.
Can you provide the type and model of the sink?
Sheet P3.1B has been updated. Sink is a P- 4B. See Addendum 01 drawings.
116 Drawing P3.1B identifies a FS-1 floor sink in Custodial 137, but it is not identified on the darin schedule on drawing P6.1. Can you provide the type and model of the sink?
Sheet P6.1 updated. FS-1 is a floor sink shown in F&S Laundry 146. Zurn Z1900-NH- 4-11. See Addendum 01 drawings.
117 Key note 7-11 instructs to Prep Masonry as required for Fluid Applied Air Water Barrier. Please clarify intent, will repointing of mortar joints be required, if so how many SF should bidders include. Will brick replacement be required, if so how how much should bidders include.
See RFI #89
118 Key note 4-21 instructs bidders to include for 2 layers of brick 2 wythes each at Vault Meeting Room. Should these 4 wythes of brick be tied together, if so how. Will horizontal joint reinforcing be acceptable, if so please provide specification.
Yes, they should be tied together. Please refer to Unit Masonry Specification - 04200.
See especially 3.4 F, Solid Wall Construction.
119 Keynote 04-08 states to Assume 100% masonry repointing. Does this apply to interior masonry walls or only exterior?
Re…