Bldg-F_Fire_Alarm_Specs.pdf
PDF 3 MB Posted
- Solicitation number
- Y23-7014
- Issued by
- Orange County, Orlando City, Florida
About this file
The document is a comprehensive fire alarm system replacement specification for Building F at the Orange County Correctional Center in Orlando, Florida, prepared by Hanson Professional Services Inc. on October 14, 2022. The project involves a complete replacement of the existing fire alarm system, which will interface with new smoke control equipment and must be designed per NFPA 72, 101, and 70 standards. The system will be compatible with campus-wide fire alarm systems and will require removal of existing fire alarm panels, devices, wiring, and conduit. The contractor must have all submittals approved by the engineer and accepted by the owner prior to beginning construction, and must field verify existing conditions.
The project is part of a larger $12,000,000 Corrections Mechanical Electrical & Plumbing Upgrades project for Building F, with sealed bids to be accepted electronically via the ProcureNow OpenGov e-Procurement Platform until 4:00 pm EST on Tuesday, August 15, 2023. Questions about the solicitation were due by Monday, July 10, 2023 at 5:00 pm EST. The fire alarm system replacement will require coordination with Orange County Project Manager, with work potentially occurring on weekends and after hours, subject to the County's approval. The contractor will be responsible for providing temporary power, maintaining occupied facility operations, and ensuring all work complies with strict security and identification requirements of the correctional facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
FOR
BUILDING F
FIRE ALARM SYSTEM REPLACEMENT
AT
ORANGE COUNTY
CORRECTIONAL CENTER
HANSON No. 17G0175A October 14, 2022
Prepared By:
Hanson Professional Services, Inc.
2300 Maitland Center Pkwy, Suite 310 Maitland, FL 32751
100% Bid Document Submittal
Building F Replacement of Fire Alarm Systems
Orange County Corrections - Orlando, FL
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 000110 – TABLE OF CONTENTS
Hanson Professional Services Inc. 000110 - 1
SECTION 000110 – TABLE OF CONTENTS
DIVISON 01
000110 TABLE OF CONTENTS
010100 SUMMARY OF WORK
010270 APPLICATION FOR PAYMENT
010350 MODIFICATION PROCEDURES
010400 PROJECT COORDINATION
010450 CUTTING AND PATCHING
010950 REFERENCE STANDARDS AND DEFINITIONS
012000 PROJECT MEETINGS
013000 SUBMITTALS
016000 MATERIALS AND EQUIPMENT
016310 PRODUCT SUBSTITUTIONS
017000 PROJECT CLOSE-OUT
017400
DIVISONS 02
WARRANTIES AND BONDS
024119
DIVISONS 07
SELECTIVE DEMOLITION
078413 PENETRATION FIRESTOPPING
DIVISONS 26
260010 GENERAL ELECTRICAL PROVISIONS
260050 BASIC ELECTRIC MATERIALS AND METHODS
260133
260519
260526
260529
260533
260553
TERMINAL CABINETS
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
IDENTIFICATION FOR ELECTRICAL SYSTEMS
260950
262416
262726
262813
262816
268721
TESTING
PANELBOARDS
WIRING DEVICES
FUSES
ENCLOSED SWITCHES AND CIRCUIT BREAKERS
FIRE ALARM SYSTEMS
END OF TABLE OF CONTENTS
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010100 – SUMMARY OF WORK
Hanson Professional Services Inc. 010100 - 1
SECTION 010100 - SUMMARY OF WORK
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
Conditions and other Division-1 Specification Sections, apply to this Section.
1.02 PROJECT DESCRIPTION
A. Performance of all tasks specified in the contract documents shall be the responsibility of the contractor unless specified otherwise.
1.03 SCOPE OF WORK
A. Summary of Work:
Fire Alarm Systems - Replacement of the existing Fire Alarm Systems (FAS) within Building F located at the 33rd Street Correctional Facility in Orange
County, FL. Building F at the 33rd Street Correctional Facility are used for maintaining and housing inmates and the buildings are regularly occupied. The replacement fire alarm system will be required to interface with and support a new smoke control equipment replacement project being designed by another engineering firm.
The fire alarm system replacement will consist of the removal of the existing fire alarm system including fire alarm panels, fire alarm devices, wiring, and conduit. The new fire alarm system shall be designed per NFPA 72, 101, and
70 (NEC) requirements and shall be compatible with existing campus wide fire alarm systems.
1.04 CONTRACTOR RESPONSIBILITIES
A. The contractor shall have all submittals approved by the Engineer and accepted by the Owner prior to the start of active construction.
B. The contractor shall have all equipment and material onsite prior to the start of active construction.
C. The contractor shall submit to the Owner prior to the project pre-construction meeting the following:
Preliminary Schedule of Values
Construction Schedule
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010100 – SUMMARY OF WORK
Hanson Professional Services Inc. 010100 - 2
Submittal Schedule
Emergency Telephone List including subcontractors and suppliers
D. The contractor shall field verify existing conditions of construction prior to start of active construction.
1.05 WORK UNDER OTHER CONTRACTS
A. Separate contracts may be issued to perform certain construction operations at the site.
The contractor of this project will allow reasonable access and coordination to the other contractor/s.
1.06 WORK SEQUENCE
A. Portions of the facility shall remain occupied and operational while work is in progress. The facility shall remain occupied and operational while work is in progress. All work shall be fully coordinated in writing with Orange County Project
Manager prior to commencement of work. Material and equipment deliveries shall be made during normal business hours.
B. The contractor may work on the weekends at his or her discretion with prior written approval from Orange County Project Manager. Weekend work shall not be an additional cost to the Owner. The contractor will coordinate with the Orange County
Project Manager for access to the building on weekends and after hours work.
C. Orange County Project Manager shall direct contractor on which days and hours are acceptable for work.
1.07 CONTRACTOR USE OF PREMISES
A. General: During the construction period, the Contractor shall have limited use of the premises for construction operations, including use of the site. The Contractor shall coordinate which areas are acceptable to Orange County Staff for use during the life of the project. The Contractor’s use of the premises is limited only by the Owner’s right to perform construction operations with its own forces or to employ separate contractors on portion of the project.
A. General: Limited use of the premises to construction activities in areas indicated within the limit of the premises. The Contractor may use any portion(s) of the site for storage or work areas only with prior approval from Orange County Project Manager.
1. Confine operations to areas within Contract limits indicated on the Drawings.
Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010100 – SUMMARY OF WORK
Hanson Professional Services Inc. 010100 - 3
2. Keep driveways and entrances serving the premises clear and available to the
Owner and the Owners’ employees at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
3. Burial of Waste Materials: Do not dispose of organic and hazardous material on site, either by burial or by burning.
4. Comply with Owner’s requirements for ingress and egress procedures, prohibitions against firearms, procedures for transportation of workers, safety and fire prevention requirements, and all applicable pollution control requirements.
Refer to the following reference documents:
a. Orange County Safety and Health Manual
b. Orange County Policy Manual (pg. 100 regarding firearms)
5. Require all employees and subcontractors to wear no-objectionable clothing;
prohibit revealing clothing and articles of clothing with offensive writing displayed. Remove from premises all personnel until such clothing is changed.
6. All personnel shall abide by the Orange County Tobacco Free policy while on any
Orange County property. Policy applies to buildings, parking lots, parks, break areas, and work sites. Tobacco products are defined as cigars, cigarettes, pipes, e-cigs, chewing tobacco and snuff. Failure to abide by the policy may result in civil penalties levied under Chapter 386, Florida Statutes and Contract enforcement remedies.
1.08 DISTRIBUTION OF RELATED DOCUMENTS
A. The Contractor is solely responsible for the distribution of ALL related documents/drawings to ALL appropriate vendors/subcontractors to ensure proper coordination of all aspects of the project and its related parts during bidding and construction.
1.09 CONTRACT DOCUMENT FILE
A. Copies of the Contract Documents, Plans, Specifications, Addenda, Change Orders, Engineers Supplemental Instructions, approved Shop Drawings, Substitution
Acceptances, etc. shall be placed and maintained at the project site by the Contractor throughout the entire contract period. These said documents shall be filed in a manner that allows for ease of retrieval. Documents shall be made available to the Engineer and the County's representatives throughout this same period.
1.10 SECURITY AND IDENTIFICATION
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010100 – SUMMARY OF WORK
Hanson Professional Services Inc. 010100 - 4
A. All costs for background investigations will be the Contractor’s responsibility. The County shall have the right to request any additional investigative background information including, but not limited to, employment records, Right-to Know records, E-verify system records (If the contractor uses this service as a means to determine employee eligibility), training records, payroll records, position for which hired including site location of any personnel assigned to perform the services. Furnish, in writing, all such information to the extent allowed by law, prior to commencement of services. The County reserves the right to conduct its own investigation of any employee or subcontractor of the Contractor.
B. Background Checks for the Contractor’s staff must be approved by Orange County’s security team prior to working in any County facility. Obtain necessary forms for background checks for work at Orange County. All Contractor’s staff background checks will be sent to the Orange County project Manager for approval.
C. For security purposes and to maintain privacy, please submit a FDLE Background Checks via email. The subject line of the email must contain the following ***EXEMPT***
D. Orange County will inform the Contractor of their Background Check results. Upon
Background Check approval, the contractor’s staff shall arrange an appointment with the
Orange County staff to obtain an Orange County ID Badge. An Affidavit of Identity form
(Issued by Contractor) and a State of Florida ID or Driver’s License will be required.
E. Contractor’s employees will not be allowed in Orange County facilities without completed and approved background investigations.
1.11 BUILDING/SITE SECURITY REQUIREMENTS
A. Contractor shall include in the bid the costs necessary to provide security for each and every day that work is being performed on Site. The security firm that will be used is:
G4S Security Systems (USA), Inc.
Contact: Jose Troche, MBA
Phone: 407 207 3221
Jose.troche@usa.g4s.com
1.12 OWNER OCCUPANCY
A. The Owner will occupy the building and areas next to the Work area. Normal hours are
7:00 AM to 5:00 PM Monday thru Friday. Coordinate with the Owner’s representative for
Work areas that can be performed on during normal work hours. Work can be performed after hours provided the area where Work is done is fully operational and back in original condition prior to beginning the next business day. Such placing of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. A certificate of Substantial Completion will be executed for each specific portion of the Work to be occupied prior to Owner occupancy mailto:Jose.troche@usa.g4s.com
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010100 – SUMMARY OF WORK
Hanson Professional Services Inc. 010100 - 5
2. Obtain a Certificate of Occupancy from the local building officials prior to Owner occupancy.
3. Prior to partial occupancy, mechanical and electrical systems shall be fully operational. Required inspections and tests shall have been successfully completed. Upon occupancy, the Owner will provide operation and maintenance of mechanical and electrical systems in occupied portions of the building.
PART 2 PRODUCTS
2.01 ASBESTOS FREE MATERIAL
A. Contractor shall provide a written and notarized statement on company letterhead(s) to certify and warrant that ONLY ASBESTOS FREE MATERIALS AND PRODUCTS were provided as required by the Engineer. Such statement shall be submitted with the final payment request. Final payment shall not be made until such statement is submitted.
Contractor agrees that if materials containing asbestos are subsequently discovered at any future time to have been included in the construction, the Contractor shall be liable for all costs related to the redesign or modification of the construction of the project so that materials containing asbestos are removed from the facility. If construction has begun or has been completed pursuant to a design that includes asbestos containing materials, the
Contractor shall also be liable for all costs related to the abatement of such asbestos.
PART 3 EXECUTION (Not applicable).
END OF SECTION 010100
Hanson Project No. 17G0175A
100% Bid Document Submittal – 10/14/2022
Section 010270 – APPLICATION FOR PAYMENT
Hanson Professional Services Inc. 010270 - 1
SECTION 010270 - APPLICATION FOR PAYMENT
PART I GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
Conditions and other Division-1 Specification Sections, apply to this Section.
1.02 SUMMARY
A. This Section specifies administrative and procedural requirements governing the Contractor’s
Applications for Payment.
B. The Contractor’s Construction Schedule and Submittal Schedule are included in Section
013000 – SUBMITTALS.
1.03 SCHEDULE OF VALUES
A. Coordinate preparation of the Schedule of Values with preparation of Contractor’s
Construction Schedule.
1. Submit the Schedule of Values to the Owner at the earliest feasible date, but in no case later than Preconstruction Meeting. Refer to Section 012000.
2. Sub-Schedules: Where the Work is separated into phases that require separately phased payments, provide sub-schedules showing values correlated with each phase of payment.
B. Format and Content: Use the Project Manual Table of Contents as a guide to establish the format for the Schedule of Values.
1. Identification: Include the following project identification on the Schedule of Values:
a. Project name and location.
b. Name of the Engineer
c. Project Number
d. Contractor’s name and address
e. Date of submittal
2. Arrange the Schedule of Values in a tabular form with separate columns to indicate the following for each item listed:
Hanson Project No. 17G0175A
100% Bid Document Submittal – 10/14/2022
Section 010270 – APPLICATION FOR PAYMENT
Hanson Professional Services Inc. 010270 - 2
a. Generic name
b. Related Specification Section
c. Change Orders (numbers) that have affected value
d. Dollar Value
e. Percentage of Contract Sum to the nearest one-hundredth percent, adjusted to total 100 percent
3. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports. Break principal subcontract amounts down into several line items:
a. A value will be given for at least every major specification section
(subsections can logically be grouped together).
b. A single material subcontractor (i.e. sod, window blinds) will not be required to be broken down into labor and material unless it is anticipated the materials will be stored and invoiced prior to installation.
c. All multiple item subcontracts or work items (i.e. concrete, roofing, painting, mechanical, electrical items, etc.) will be shown broken down at least in labor and material (all taxes, burden and overhead and profit included).
d. Mobilization (move-on, bond, insurance, temporary office and sanitary service installation) shall not exceed 2 1/2% of contract price.
e. Fire Alarm System: Typically shown per specification section, labor and material, per floor.
f. Electrical: same as Fire Alarm System.
g. Conduit and Raceways broken down at least into underground, rough-in and trim. All per building and labor and material.
h. Logical grouping of specification subsections is permitted.
4. Round amounts off the nearest whole dollar, the total shall equal the Contract Sum.
5. For each part of the Work where an Application for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed, provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
6. Margins of Cost: Show line items for indirect costs, and margins on actual costs, only to the extent that such items will be listed individually in Applications for Payment.
Each item in the Schedule of Values and Applications for Payment shall be complete including its total cost and proportionate share of general overhead and profit margin.
a. At the Contractors’ option, temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown as separate line items in the Schedule of Values or distributed as general overhead expense.
7. Schedule Updating: Update and resubmit the Schedule of Values when Change Orders or Construction Change Directives result in a change in the contract sum.
Hanson Project No. 17G0175A
100% Bid Document Submittal – 10/14/2022
Section 010270 – APPLICATION FOR PAYMENT
Hanson Professional Services Inc. 010270 - 3
1.04 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as reviewed by the Owner representative and paid for by the Owner.
1. The initial Application for Payment, the Application for Payment at time of
Substantial Completion, and the Final Application for Payment involve additional requirements.
B. Payment Application Times: The period of construction work covered by each Application of
Payment is the period indicated in the Agreement.
C. Payment Application Forms: Use the County’s most updated form as the form for Application for Payment. Form given at the Preconstruction Conference.
D. Application Preparation: Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the Owner. Incomplete applications will be returned without action.
1. Entries shall match data on the Schedule of Values and Contractors’ Construction
Schedule. Use updated schedules if revisions have been made.
2. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application.
E. Transmittal: Submit five (5) original executed copies of each Application for Payment to the
Project Manager by means ensuring receipt within 24 hours; one copy shall be complete, including waivers of lien and similar attachments, when required.
1. Transmit each copy with a transmittal form listing attachments, and recording appropriate information related to the application in a manner acceptable to the Project
Manager.
F. Payment will be processed once a month. Payment for item will be based on percentage completed as determined and approved by the County Project Manager or invoice for stored materials. Retainage (10%) will be held for all applications.
G. Application for Payment at Substantial Completion: Following issuance of the Certificate of
Substantial Completion, submit an Application for Payment; this application shall reflect any
Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work. Application shall also include all items listed in Part H.
above.
H. Final Payment Application: Administrative actions and submittals, which must precede or coincide with submittal of the final payment. Application for Payment includes the following:
1. Completion of Project Close-Out requirements
Hanson Project No. 17G0175A
100% Bid Document Submittal – 10/14/2022
Section 010270 – APPLICATION FOR PAYMENT
Hanson Professional Services Inc. 010270 - 4
2. Completion of items specified for completion after Substantial Completion
(Punch List)
3. Contractor’s release of lien (on Owner’s form)
4. Subcontractor and material supplier release of lien (If applicable)
5. Consent of Surety
6. Power of attorney
7. Asbestos-free letter, notarized
PART 2PRODUCTS (Not Applicable)
PART 3EXECUTION (Not Applicable)
END OF SECTION 010270
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010350 – MODIFICATION
PROCEDURES
Hanson Professional Services Inc. 010350 - 1
SECTION 010350 - MODIFICATION PROCEDURES
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this section.
1.02 SUMMARY
A. This section specifies administrative and procedural requirements for handling and processing Contract modifications.
1.03 MINOR CHANGES IN THE WORK
A. Supplemental instructions authorizing minor changes in the work, not involving an adjustment to the Contract Sum or Contract Time, will be issued by the Project Manager.
1.04 CHANGE ORDER PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Proposed changes in the work that will require adjustment to the Contract Sum or Contract Time will be issued by the Project Manager, with a detailed description of the proposed change and supplemental or revised Drawings and Specifications, if necessary.
1. Proposal requests issued by the Project Manager are for information only. Do not consider them instruction either to stop work in progress, or to execute the proposed change.
2. Unless otherwise indicated in the proposal request, within 7 days of receipt of the proposal request, submit to the Project Manager from the Owner's review, an estimate of cost necessary to execute the proposed change.
a. Include a list of quantities of products to be purchased and unit costs, along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include a statement indicating the effect the proposed change in the work will have on the Contract Time.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010350 – MODIFICATION
PROCEDURES
Hanson Professional Services Inc. 010350 - 2
d. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amount.
B. Contractor-Initiated Change Order Proposal Requests: When latent or other unforeseen conditions in mutual accord with the Owner Representative’s findings require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the Architect.
1. Include a statement outlining the reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change.
Indicate the effect of the proposed change on the Contract Sum and Contract Time.
2. Include a list of quantities of products to be purchased and unit costs along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Comply with requirements in Section 016310 Product Substitutions- if the proposed change in the work requires that substitution of one product or system for a product or system not specified.
5. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amounts.
1.05 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: When the Owner and Contractor are not in total agreement on the terms of a Change Order Proposal Request, the Project Manager may issue a
Construction Change Directive instructing the Contractor to proceed with a change in the
Work, for subsequent inclusion in a Change Order.
1. The Construction Change Directive will contain a complete description of the change in the Work and designate the method to be followed to determine change in the Contract Sum or Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of the change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
1.07 CHANGE ORDER PROCEDURES
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010350 – MODIFICATION
PROCEDURES
Hanson Professional Services Inc. 010350 - 3
A. Upon the Owner's approval of a Change Order Proposal Request, the Project Manager will issue a Change Order for signatures of the Owner and Contractor on County's Change
Order form, as provided in the Conditions of the Contract.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION 010350
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010400 – PROJECT COORDINATION
Hanson Professional Services Inc. 010400 - 1
SECTION 010400 - PROJECT COORDINATION
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this Section.
1.02 SUMMARY
A. This Section specifies administrative and supervisory requirements necessary for project coordination including, but not necessarily limited to:
1. Coordination
2. Administrative and supervisory personnel
3. General installation provisions
4. Cleaning and protection
B. Progress meetings, coordination meetings and Pre-installation conferences are included in
Section 012000 ‘Project Meetings’.
C. Requirements for the Contractor’s Construction Schedule are included in Section 013000
‘Submittals’.
1.03 COORDINATION
A. Coordination: Coordinate construction activities included under various Sections of these
Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations included under different Sections of the Specification that are dependent upon each other for proper installation, connection, and operation.
1. Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.
2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010400 – PROJECT COORDINATION
Hanson Professional Services Inc. 010400 - 2
B. Where necessary, prepare memoranda for distribution to each party involved outlining special procedures required for coordination. Include such items as required: notices, reports, and attendance at meetings.
1. Prepare similar memoranda for the Owner and separate Contractors where coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Schedules
2. Installation and removal of temporary facilities
3. Delivery and processing of submittals
4. Progress meetings
5. Project close-out activities
D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
1. Salvage materials and equipment (if any) involved in performance of, but not actually incorporated in, the Work.
E. Lack of coordination as specified in this and other sections of the contract documents are in grounds for assessment of back charges and/or termination in order to remediate the situation.
1.04 SUBMITTALS
A. Coordination Drawings: Prepare and submit coordination Drawings where close and careful coordination is required for installation of products and materials fabricated off-site by separate entities, and where limited space availability necessitates maximum utilization of space for efficient installation of different components.
1. Show the interrelationship of components shown on separate Shop Drawings.
2. Indicate required installation sequences.
3. Comply with requirements contained in Section Submittals.
4. Refer to Facility Services documents for specific coordination drawing requirements for mechanical and electrical installations.
B. Staff Names: At the Preconstruction Conference submit a list of the Contractor’s principal staff assignments, including the Superintendent and other personnel in attendance at the site; identify individuals, their duties and responsibilities; list their addresses and telephone numbers.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010400 – PROJECT COORDINATION
Hanson Professional Services Inc. 010400 - 3
1. Post copies of the list in the project meeting room, the temporary field office, and each temporary telephone.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.01 GENERAL INSTALLATION PROVISIONS
A. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
B. Manufacturer’s Instructions: Comply with manufacturer’s installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.
C. Inspect materials or equipment immediately upon delivery and again prior to installation.
Reject damaged and defective items.
D. Provide attachment and connection devices and methods necessary for securing work.
Secure work true to line and level. Allow for expansion and building movement.
E. Visual Effects: Provide uniform joint widths in exposed work. Arrange joints in exposed work to obtain the best visual effect. Refer questionable choices to Project Manager for final decision.
F. Recheck measurements and dimensions, before starting each installation.
G. Install each component during weather conditions and Project status that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.
H. Coordinate temporary enclosures with required inspections and tests, to minimize the necessity of uncovering completed construction for that purpose.
I. Mounting Heights: Where mounting heights are not indicated, install individual components at standard mounting heights recognized within the industry for the particular application indicated. Refer questionable mounting height decisions to the
Engineer/Project Manager for final decision.
3.02 CLEANING AND PROTECTION
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010400 – PROJECT COORDINATION
Hanson Professional Services Inc. 010400 - 4
A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
B. Clean and maintain completed construction as directed by the Project Manager and as frequently as necessary to ensure its integrity and safety through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
C. Limiting Exposures: Supervise construction activities to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. Where the applicable, such exposures include, but are not limited to, the following:
1. Excessive static or dynamic loading
2. Excessively high or low temperatures
3. Excessively high or low humidity
4. Air contamination or pollution
5. Water
6. Solvents
7. Chemicals
8. Soiling, staining and corrosion
9. Rodent and insect infestation
10. Combustion
11. Destructive testing
12. Misalignment
13. Excessive weathering
14. Unprotected storage
15. Improper shipping or handling
16. Theft
17. Vandalism
END OF SECTION 010400
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010450 – CUTTING AND PATCHING
Hanson Professional Services Inc. 010450 - 1
SECTION 010450 - CUTTING AND PATCHING
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
Conditions and other Division-1 Specification Sections, apply to this Section.
1.02 SUMMARY
A. This Section specifies administrative and procedural requirements for cutting and patching.
B. Refer to other Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work.
1. Requirements of this Section apply to mechanical and electrical installations.
Refer to Facility Services Sections for other requirements and limitations applicable to cutting and patching mechanical and electrical installations.
1.03 SUBMITTALS
A. Cutting and Patching Proposal: Where approval of procedures for cutting and patching is required before proceeding, submit a proposal describing procedures well in advance of the time cutting and patching will be performed and request approval to proceed. Include the following information, as applicable, in the proposal:
1. Describe the extent of cutting and patching required and how it is to be performed;
indicate why it cannot be avoided.
2. Describe anticipated results in terms of changes to existing construction; include changes to structural elements and operating components as well as changes in the building’s appearance and other significant visual elements.
3. List products to be used and firms or entities that will perform Work.
4. Indicate dates when cutting and patching is to be performed.
5. List utilities that will be disturbed or affected, including those that will be relocated and those that will be temporarily out-of-service. Indicate how long service will be disrupted.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010450 – CUTTING AND PATCHING
Hanson Professional Services Inc. 010450 - 2
6. Where cutting and patching involves addition of reinforcement to structural elements, submit details and engineering calculations to show how reinforcement is integrated with the original structure.
7. Approval by the Engineer to proceed with cutting and patching does not waive the
Engineer’s right to later require complete removal and replacement of a part of the
Work found to be unsatisfactory.
1.04 QUALITY ASSURANCE
A. Requirements for Structural Work: Do not cut and patch structural elements in a manner that would reduce their load carrying capacity or load-deflection ratio.
1. Obtain approval of the cutting and patching proposal before cutting and patching the following structural elements.
a. Structural steel
b. Lintels
c. Structural decking
d. Miscellaneous structural metals e Exterior curtain wall construction
e. Structural systems of special construction.
B. Operational and Safety Limitations: Do not cut and patch operating elements or safety related components in a manner that would result in reducing their capacity to perform as intended, or result in increased maintenance, or decreased operational life or safety.
1. Obtain approval of the cutting and patching proposal before cutting and patching the following operating elements or safety related systems.
a. Shoring, bracing and sheeting
b. Primary operational systems and equipment
c. Air or smoke barriers
d. Water, moisture, or vapor barriers
e. Membranes and flashings
f. Fire protection systems
g. Noise and vibration control elements and systems
h. Control systems
I. Communication systems
j. Conveying systems
k. Electrical wiring systems
C. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied spaces, in a manner that would, in the Engineer’s opinion, reduce the building’s aesthetic qualities, or result in visual evidence of cutting and patching. Remove and replace work cut and patched in a visually unsatisfactory manner.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010450 – CUTTING AND PATCHING
Hanson Professional Services Inc. 010450 - 3
1. If possible retain the original installer or fabricator to cut and patch the following categories of exposed work, or if it is not possible to engage the original installer or fabricator, engage another recognized experienced and specialized firm:
a. Preformed metal panels
b. Window wall system
c. Roofing systems
PART 2 PRODUCTS
2.01 MATERIALS
A. Use materials that are identical to existing materials. If identical materials are not available or cannot be used where exposed surfaces are involved, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect unless otherwise indicated by Engineer/Owner. Use materials whose installed performance will equal or surpass that of existing materials.
PART 3 EXECUTION
3.01 INSPECTION
A. Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed. Take corrective action before proceeding, if unsafe or unsatisfactory conditions are encountered.
1. Before proceeding, meet at the site with all parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.
3.02 PREPARATION
A. Temporary Support: Provide temporary support of work to be cut.
B. Protection: Protect existing construction during cutting and patching to prevent damage.
Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations.
C. Avoid interference with use of adjoining areas and interruption of free passage to adjoining areas.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010450 – CUTTING AND PATCHING
Hanson Professional Services Inc. 010450 - 4
D. Take all precautions necessary to avoid cutting existing pipe, conduit or ductwork serving the building, but scheduled to be removed or relocated until provisions have been made to bypass them.
3.03 PERFORMANCE
A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay.
1. Cut existing construction to provide for installation of other components or performance of other construction activities and the subsequent fitting and patching required to restore surfaces to their original condition.
B. Cutting: Cut existing construction using methods least likely to damage elements to be retained or adjoining construction. Where possible review proposed procedures with the original installer; comply with the original installer’s recommendations.
1. In general, where cutting is required use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots neatly to size required with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.
3. Cut through concrete and masonry using a cutting machine such as a Carborundum saw or diamond core drill.
4. By-pass utility services such as pipe or conduit, before cutting, where services are shown or required to be removed. Cap, valve or plug and seal the remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after by-passing and cutting.
C. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances.
1. Where feasible, inspect and test patched areas to demonstrate integrity of the installation.
2. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
3. Where removal of walls or partitions extends one finished area into another, patch and repair floor and wall surfaces in the new space to provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials if necessary to achieve uniform color and appearance.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010450 – CUTTING AND PATCHING
Hanson Professional Services Inc. 010450 - 5
a. Where patching occurs in smooth painted surfaces, extend final coat over entire unbroken surfaces containing the patch, after the patched area has received primer and second coat.
3.04 CLEANING
A. Thoroughly clean areas and spaces where cutting and patching is performed or used as access. Remove completely paint, mortar, oils, putty and items of similar nature.
Thoroughly clean piping, conduit and similar features before painting or other finishing is applied. Restore damaged materials to their original condition.
END OF SECTION 010450
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010950 – REFERENCE STANDARDS
AND DEFINITIONS
Hanson Professional Services Inc. 010950 - 1
SECTION 010950 - REFERENCE STANDARDS AND DEFINITIONS
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
Conditions and other Division-1 Specification Sections, apply to this Section.
1.02 DEFINITIONS
A. General: Basic Contract definitions are included in the Conditions of the Contract.
B. Indicated: The term indicated refers to graphic representations, notes or schedules on the
Drawings, or other Paragraphs or Schedules in the Specifications, and similar requirements in the Contract Documents. Where terms such as shown, noted, scheduled and specified are used, it is to help the reader locate the reference; no limitation on location is intended.
C. Directed: Terms such as directed, requested, authorized, selected, accepted, required, and permitted mean directed by the Project Manager, requested by the Engineer/Project
Manager and similar phrases.
D. Approved: This term approved means accepted, where used in conjunction with the
Engineer's action on the Contractor's submittals, applications, and requests, is limited to the Engineer's duties and responsibilities as stated in the Conditions of the Contract.
E. Regulations: The term Regulations includes laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, as well as rules, conventions, and agreements within the construction industry that control performance of the Work.
F. Furnish: The term furnish is used to mean supply and deliver to the Project site, ready for unloading, unpacking, assembly, installation, and similar operations.
G. Install: The term install is used to describe operations at project site including the actual unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.
H. Provide: The term provide means to furnish and install, complete and ready for the intended use.
I. Installer: An Installer is the Contractor or an entity engaged by the Contractor, either as an employee, subcontractor, or contractor of lower tier for performance of a particular construction activity, including installation, erection, application, and similar operations.
Installers are required to be experienced in the operations they are engaged to perform.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010950 – REFERENCE STANDARDS
AND DEFINITIONS
Hanson Professional Services Inc. 010950 - 2
1. The term experienced, when used with the term Installer, means having a minimum of five previous projects similar in size and scope to this Project, being familiar with the special requirements indicated, and having complied with requirements of the authority having jurisdiction.
2. Trades: Use of titles such as carpentry is not intended to imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as carpenter. It also does not imply that requirements specified apply exclusively to trades persons of the corresponding generic name.
J. Project Site is the space available to the Contractor for performance of construction activities, either exclusively or in conjunction with others performing other work as part of the Project. The extent of the Project Site is shown on the Drawings and may or may not be identical with the description of the land on which the Project is to be built.
K. Testing Laboratories: A testing laboratory is an independent entity engaged to perform specific inspections or tests, either at the Project sites or elsewhere, and to report on and, if required, to interpret results of those inspections or tests.
L. Florida Building Code (FBC): Where the term or acronym is used it will mean the current edition of the Florida Building Code with all applicable revisions adopted by the authorities having jurisdictions at the location of the Project.
1.03 SPECIFICATION FORMAT AND CONTENT EXPLANATION
A. Specification Format: These Specifications are organized into Divisions and Sections based on the Construction Specifications Institute's MASTER FORMAT numbering system.
1. Division 00 and Divisions 02 through 49 are based on Master Format 2014
B. Specification Content: This Specification uses certain conventions in the use of language and the intended meaning of certain terms, words, and phrases when used in particular situations or circumstances. These conventions are explained as follows:
1. Abbreviated Language: Language used in Specifications and other Contract
Documents is the abbreviated type. Words and meaning shall be interpreted as appropriate. Words that are implied, but not stated shall be interpolated as the sense required. Singular words will be interpreted as plural and plural words interpreted as singular where applicable and the context of the Contract Documents so indicates.
2. Imperative and streamlined language is used generally in the Specifications.
Requirements expressed in the imperative mood are to be performed by the
Contrac
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010950 – REFERENCE STANDARDS
AND DEFINITIONS
Hanson Professional Services Inc. 010950 - 3 tor. At certain locations in the text, for clarity, subjective language is used to describe responsibilities that must be fulfilled indirectly by the Contractor, or by others when so noted.
a. The words, shall be shall be included by inference wherever a colon (:) is used within a sentence or phrase.
1.04 INDUSTRY STANDARDS
A. Applicability of Standards: Except where the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copies directly into the Contract Documents to the extend reference. Such standards are made part of the Contract Documents by reference.
B. Publication Dates: Comply with the standard in effect as of the date of the Contract
Documents.
C. Conflicting Requirements: Where compliances with two or more standards are specified, and the standards may establish different or conflicting requirements for minimum quantities or quality levels. Refer requirements that are different, but apparently equal, and uncertainties to the Engineer for a decision before proceeding.
1. Minimum Quantity or Quality Levels: The quantity of quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. In complying with these requirements, indicated numeric values are minimum or maximum, as appropriate for the context of the requirements. Refer uncertainties to the Engineer/Owner for a decision before proceeding.
D. Copies of Standards: Each entity engaged in construction on the Project is required to be familiar with industry standards applicable to that entity's construction activity. Copies of applicable standards are not bound with the Contract Documents.
1. Where copies of standards are needed for performance of a required construction activity. The Contractor shall obtain copies directly from the publication source or any other authorized source.
E. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where such acronyms or abbreviations are used in the
Specifications or other Contract Documents, they mean the recognized name of the trade association, standards generating organization, authority having jurisdiction, or other entity applicable to the context of the text provision. See Trade Reference List at the end of this
Section refer to the Encyclopedia of Associations, published by Gale Research Co., available in most libraries.
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 010950 – REFERENCE STANDARDS
AND DEFINITIONS
Hanson Professional Services Inc. 010950 - 4
1.05 SUBMITTALS
A. Permits, Licenses, and Certificates: For the Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, and similar documents, correspondence, and records established in conjunction with compliance with standards and regulation bearing upon performance of the Work.
PART 2 PRODUCTS
(Not Applicable)
PART 3 EXECUTION
(Not Applicable)
END OF SECTION 010950
Hanson Project No. 17G0175A
100% Bid Documents Submittal – 10/14/2022
Section 012000 – PROJECT MEETINGS
Hanson Professional Services Inc. 012000 - 1
SECTION 012000 - PROJECT MEETINGS
PART 1 GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division-1 Specification Sections, apply to this Section.
1.02 SUMMARY
A. This Section specifies administrative and procedural requirements for project meetings including but not limited to:
1. Pre-Construction Conference
2. Pre-Installation Conference
3. Coordination Meetings
4. Progress Meetings
B.…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .