This file is a detailed cost estimate spreadsheet for a potable water line system replacement project at Moron Air Base, Spain. The project involves extensive infrastructure work across multiple zones (A through N), including demolishing existing underground pipes, installing new polyethylene pipes of various diameters, replacing valves, hydrants, road crossings, and performing GPS surveys. The basic package and an optional scope (Option #1) are included, with itemized costs for materials, labor, and other direct costs.

The federal contract opportunity is a solicitation (FA557625B0007) issued by the Department of the Air Force United States Air Forces in Europe - Air Forces Africa, with a project value between $500,000 and $1,000,000. Key dates include a pre-proposal conference on 25 June 2025, a question submission deadline of 4 July 2025, and bid submission deadline of 18 July 2025. The solicitation is exclusively for local sources registered to conduct construction business in Spain, with the bid acceptance period valid through 31 December 2025. Contractors must comply with Spanish legislative requirements for government works.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Potable Water Line System, newest first.
File Type Posted
Questions and Answers.pdf PDF
AF66 Submittals 23-1014 PD.xlsx XLSX spreadsheet
Solicitation - FA557525B0007.pdf PDF
Specifications En 23-1014 PD.pdf PDF
Especificaciones Sp 23-1014 PD.pdf PDF
Drawings 23-1014 PD.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Basic pkg KTR

*
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR POTABLE LINE SYSTEM APRON, F2001, PH4 (BASIC PACKAGE)
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 23-1014PDMORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
GROUND PENETRATING RADAR GPR
GEO-RADAR
1Ground Penetrating Radar GPR survey
Estudio Geo-Radar (GPR)JOB
TOTAL GROUND PENETRATING RADAR GPR
TOTAL GEO-RADAR
ZONE A
ZONA A
2Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
TOTAL ZONE A
TOTAL ZONA A
ZONE B
ZONA B
3Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
TOTAL ZONE B
TOTAL ZONA B
ZONE C
ZONA C
4Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
5Gate Valve 3/4" and accessories
Válvulas de compuerta 3/4" y accesoriosEa
6Strainer 3/4" and accessories
Filtro colador 3/4" y accesoriosEa
7Hose Bibb and Hose Connection Vacuum Breaker 3/4"
Grifo de manguera y rompedor de vacío 3/4"Ea
8Water meter DN15 and accessories
Contador de agua DN15 y accesoriosEa
9Backflow preventer 6" (RPPD) and accessories
Desconector 6" (RPPD) y accesoriosEa
10Polyethylene Pipe PE100 DN160 and connection accessories
Tubería polietileno PE100 DN160 y accesorios de conexiónLm
11Polyethylene Pipe PE100 DN32 and connection accessories
Tubería polietileno PE100 DN32 y accesorios de conexiónLm
12Road crossing (drilled) RC-1
Cruce carretera (con topo) RC-1Lm
13Road crossing (drilled) RC-2
Cruce carretera (con topo) RC-2Lm
13Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
14GPS Survey
Survey GPSLm
TOTAL ZONE C
TOTAL ZONA C
ZONE D
ZONA D
15Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
16Air Relief valve
VentosaEa
17Fast acting anti water hammer valve
Válvula de alivio rápidoEa
18Bollards installation
Instalación de bolardosEa
19Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
20GPS Survey
Survey GPSLm
TOTAL ZONE D
TOTAL ZONA D
ZONE E
ZONA E
21Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
22Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
23Gate Valve 6", valve box and accessories
Válvula de compuerta 6", caja de válvulas y accesoriosEa
24Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
25Polyethylene Pipe PE100 DN160 and connection accessories
Tubería polietileno PE100 DN160 y accesorios de conexiónLm
26Road crossing (drilled) RC-3
Cruce carretera (con topo) RC-3Lm
27Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
28GPS Survey
Survey GPSJOB
TOTAL ZONE E
TOTAL ZONA E
ZONE F
ZONA F
29Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
30Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
31Air Relief valve
VentosaEa
32Fast acting anti water hammer valve
Válvula de alivio rápidoEa
33Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
34Bollards installation
Instalación de bolardosEa
35Road crossing (drilled) RC-4
Cruce carretera (con topo) RC-4Lm
36Reinstall water meter
Reinstalar contador de aguaEa
37Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
38GPS Survey
Survey GPSLm
TOTAL ZONE F
TOTAL ZONA F
ZONE G
ZONA G
39Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
40Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
41Gate Valve 6", valve box and accessories
Válvula de compuerta 6", caja de válvulas y accesoriosEa
42Gate Valve 2", valve box and accessories
Válvula de compuerta 2", caja de válvulas y accesoriosEa
43Air Relief valve to be reinstalled
Ventosa a reinstalarEa
44Valve assembly to be reinstalled
Conjunto de válvulas a reinstalarEa
45Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
46Polyethylene Pipe PE100 DN160 and connection accessories
Tubería polietileno PE100 DN160 y accesorios de conexiónLm
47Polyethylene Pipe PE100 DN63 and connection accessories
Tubería polietileno PE100 DN63 y accesorios de conexiónLm
48Bollards installation
Instalación de bolardosEa
49Paint and marking of new/existing hydrants
Pintura y marcado de hidrantes nuevos/existentesEa
50GPS Survey
Survey GPSLm
TOTAL ZONE G
TOTAL ZONA G
ZONE H
ZONA H
51Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
52Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
53Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
54Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
55Paint and marking of new/existing hydrants
Pintura y marcado de hidrantes nuevos/existentesEa
56GPS Survey
Survey GPSLm
TOTAL ZONE H
TOTAL ZONA H
ZONE I
ZONA I
57Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
58Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
59Flush type hydrant, T, valve, pipe and accessories
Hidrante enrasado, T, válvula, tubería y accesoriosEa
60Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
61Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
62Paint and marking of new/existing hydrants
Pintura y marcado de hidrantes nuevos/existentesEa
63GPS Survey
Survey GPSLm
TOTAL ZONE I
TOTAL ZONA I
ZONE J
ZONA J
64Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
65Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
66Polyethylene Pipe PE100 DN180 and connection accessories
Tubería polietileno PE100 DN180 y accesorios de conexiónLm
67Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
68GPS Survey
Survey GPSLm
TOTAL ZONE J
TOTAL ZONA J
ZONE K
ZONA K
69Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
70Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
71Gate Valve 1 1/2", valve box and accessories
Válvula de compuerta 1 1/2", caja de válvulas y accesoriosEa
72Air Relief valve
VentosaEa
73Flush type hydrant, T, valve, pipe and accessories
Hidrante enrasado, T, válvula, tubería y accesoriosEa
73Barrel type hydrant, T, valve, pipe and accessories
Hidrante vertical, T, válvula, tubería y accesoriosEa
74Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
75Polyethylene Pipe PE100 DN160 and connection accessories
Tubería polietileno PE100 DN160 y accesorios de conexiónLm
76Polyethylene Pipe PE100 DN110 and connection accessories
Tubería polietileno PE100 DN110 accesorios de conexiónLm
77Polyethylene Pipe PE100 DN50 and connection accessories
Tubería polietileno PE100 DN50 y accesorios de conexiónLm
78Road crossing (drilled) RC-5
Cruce carretera (con topo) RC-5Lm
79Road crossing (drilled) RC-6
Cruce carretera (con topo) RC-6Lm
80Road crossing (drilled) RC-7
Cruce carretera (con topo) RC-7Lm
81Emergency shower and accessories
Ducha de emergencia y accesoriosEa
82Bollards installation
Instalación de bolardosEa
83Paint and marking of new/existing hydrants
Pintura y marcado de hidrantes nuevos/existentesEa
84Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
85GPS Survey
Survey GPSLm
TOTAL ZONE K
TOTAL ZONA K
ZONE L
ZONA L
86Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
87Flush type hydrant, T, valve, pipe and accessories
Hidrante enrasado, T, válvula, tubería y accesoriosEa
87Barrel type hydrant, T, valve, pipe and accessories
Hidrante vertical, T, válvula, tubería y accesoriosEa
88Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
89Gate Valve 3/4", valve box and accessories
Válvula de compuerta 3/4", caja de válvulas y accesoriosEa
87Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
88Polyethylene Pipe PE100 DN160 and connection accessories
Tubería polietileno PE100 DN160 y accesorios de conexiónLm
89Bollards installation
Instalación de bolardosEa
90Paint and marking of new/existing hydrants
Pintura y marcado de hidrantes nuevos/existentesEa
91Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
92GPS Survey
Survey GPSLm
TOTAL ZONE L
TOTAL ZONA L
ZONE M
ZONA M
93Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
94Gate Valve 8", valve box and accessories
Válvula de compuerta 8", caja de válvulas y accesoriosEa
95Gate Valve 1 1/2", valve box and accessories
Válvula de compuerta 1 1/2", caja de válvulas y accesoriosEa
96Flush type hydrant, T, valve, pipe and accessories
Hidrante enrasado, T, válvula, tubería y accesoriosEa
97Barrel type hydrant, T, valve, pipe and accessories
Hidrante vertical, T, válvula, tubería y accesoriosEa
98Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
99Polyethylene Pipe PE100 DN160 and connection accessories
Tubería polietileno PE100 DN160 y accesorios de conexiónLm
100Polyethylene Pipe PE100 DN50 and connection accessories
Tubería polietileno PE100 DN50 y accesorios de conexiónLm
101Road crossing (drilled) RC-8
Cruce carretera (con topo) RC-8Lm
102Road crossing (drilled) RC-9
Cruce carretera (con topo) RC-9Lm
103Road crossing (drilled) RC-10
Cruce carretera (con topo) RC-10Lm
104Bollards installation
Instalación de bolardosEa
105Paint and marking of new/existing hydrants
Pintura y marcado de hidrantes nuevos/existentesEa
106Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
107GPS Survey
Survey GPSLm
TOTAL ZONE M
TOTAL ZONA M
ZONE N
ZONA N
108Demolish existing underground pipe and accessories
Demolición de tubería enterrada existente y accesoriosLm
109Flush type hydrant, T, valve, pipe and accessories
Hidrante enrasado, T, válvula, tubería y accesoriosEa
110Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
111Paint and marking of new/existing hydrants
Pintura y marcado de hidrantes nuevos/existentesEa
112Repair elements affected by the execution of the project
Reparar elementos afectados por la ejecución del proyectoJOB
113GPS Survey
Survey GPSLm
TOTAL ZONE N
TOTAL ZONA N
TOTAL GROUND PENETRATING RADAR GPR
TOTAL GEO-RADAR
TOTAL ZONE A
TOTAL ZONA A
TOTAL ZONE B
TOTAL ZONA B
TOTAL ZONE C
TOTAL ZONA C
TOTAL ZONE D
TOTAL ZONA D
TOTAL ZONE E
TOTAL ZONA E
TOTAL ZONE F
TOTAL ZONA F
TOTAL ZONE G
TOTAL ZONA G
TOTAL ZONE H
TOTAL ZONA H
TOTAL ZONE I
TOTAL ZONA I
TOTAL ZONE J
TOTAL ZONA J
TOTAL ZONE K
TOTAL ZONA K
TOTAL ZONE L
TOTAL ZONA L
TOTAL ZONE M
TOTAL ZONA M
TOTAL ZONE N
TOTAL ZONA N
TOTAL
TOTAL

TOTAL MATERIAL COSTS

TOTAL LABOR COSTS

TOTAL OTHER DIRECT COSTS

TOTAL DIRECT COSTS

OVERHEAD %

SUBTOTAL

PROFIT %

TOTAL PROJECT EUROS (BASIC PACKAGE)
euros

PREPARED BY:

REVIEWED BY:

APPROVED BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

&"Times New Roman,Regular"Page &P of &N

Option #1 (obstructions) KTR

*
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR POTABLE LINE SYSTEM APRON, F2001, PH4 (OPTION #1)
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 23-1014PDMORÓN AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
OPTION #1
OPCIÓN #1
1Demolish underground concrete block
Demoler bloque de hormigón enterradoEa
2Gate Valve 8" and accessories
Válvulas de compuerta 8" y accesoriosEa
3Air Relief valve
VentosaEa
4Fast acting anti water hammer valve
Válvula de alivio rápidoEa
5Polyethylene Pipe PE100 DN200 and connection accessories
Tubería polietileno PE100 DN200 y accesorios de conexiónLm
6Flush type hydrant, T, valve, pipe and accessories
Hidrante enrasado, T, válvula, tubería y accesoriosEa
7Barrel type hydrant, T, valve, pipe and accessories
Hidrante vertical, T, válvula, tubería y accesoriosEa
8Road crossing (drilled) RC-3
Cruce carretera (con topo) RC-3Lm
TOTAL OPTION #1
TOTAL OPCIÓN #1

TOTAL MATERIAL COSTS

TOTAL LABOR COSTS

TOTAL OTHER DIRECT COSTS

TOTAL DIRECT COSTS

OVERHEAD %

SUBTOTAL

PROFIT %

TOTAL PROJECT EUROS (OPTION #1)

PREPARED BY:

REVIEWED BY:

APPROVED BY:

These costs and overhead and profit percentages will be applied in any possible future modifications