AF66 Submittals 23-1014 PD.xlsx
XLSX spreadsheet 58 KB Posted
- Attached to
- Replace Potable Water Line System Federal contract opportunity
- Solicitation number
- FA557525B0007
About this file
The document is a Material Submittals Schedule for a federal contract opportunity to replace the potable water line system at Moron Air Base in Spain. The project (QUUG 23-1014 PD) is valued between $500,000 and $1,000,000, with a solicitation number of FA557525B0007. The schedule details 45 specific submittal requirements across multiple sections, including warranty letters, construction schedules, work plans, environmental protection plans, technical specifications for piping and hydrants, operation and maintenance manuals, and various technical reports.
Key dates include a pre-proposal conference/site visit on 25 June 2025, a question submission deadline of 4 July 2025, and bid submission deadline of 18 July 2025 at 10:00 hours local time. The solicitation is restricted to local sources in Spain, with contractors required to meet Spanish legislative requirements for government works. The project is being conducted by the Department of the Air Force, United States Air Forces in Europe - Air Forces Africa, with multiple contracting points of contact provided. Notably, the government reserves the right to cancel the solicitation, and funds are not currently available, with the bid acceptance period requested to be valid through 31 December 2025.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers.pdf | ||
| Specifications En 23-1014 PD.pdf | ||
| Especificaciones Sp 23-1014 PD.pdf | ||
| Blank Cost Estimate 23-1014 PD.xlsx | XLSX spreadsheet | |
| Drawings 23-1014 PD.pdf | ||
| Solicitation - FA557525B0007.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | ||
| QUUG 23-1014 PD | PROJECT TITLE |
RPR POTABLE LINE SYSTEM APRON, F2001, PH4
SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal
| SECTION 01 11 00 | ||||||
| 01 | Warranty letter | 1 | Acceptance +15 | |||
| 02 | Construction Schedule | 1 | Contract Award +7 | BCE to review and approve. | ||
| 03 | Progress Schedule | 1 | Contract Award +10 | |||
| 04 | Work Plan | 1 | Contract Award +7 | |||
| 05 | Mobility Plan | 1 | Contract Award +15 | |||
| 06 | Quality Control Plan | 1 | Contract Award +15 | |||
| 07 | Environmental Protection Plan | 1 | Contract Award +15 | |||
| 08 | DD Form 1354 | 1 | Pre-Final Inspection -15 | RP needs to complete the form within 10 days after BOD | ||
| 09 | Waste & construction debris management | 1 | Final Inspection-15 | |||
| 10 | As-Built drawings | 1 | Final Inspection -15 | |||
| 11 | Spatial Data | 1 | As-Built Drawings Approval +10 | Spatial data should be based on the approved As-Built drawings. | ||
| 12 | Key Staff | 1 | Contract Award +15 | |||
| 13 | Health and safety Plan | 1 | Contract Award +15 | |||
| SECTION 01 11 02 | ||||||
| 14 | Ground Penetrating Radar report | 1 | ||||
| 15 | Water Outage Schedule | 1 | Contract Award +15 | |||
| 16 | Request for Waiver to Airfield and Airspace Criteria | 1 | Contract Award +15 | |||
| 17 | Deliberate Risk Assessment Worksheet | 1 | Contract Award +15 | |||
| 18 | Airfield Construction Requirements Checklist | 1 | Contract Award +15 | |||
| 19 | Construction Phasing Plan | 1 | Contract Award +15 | |||
| 20 | Operational Safety on Airfield during Construction | 1 | Contract Award +15 | |||
| SECTION 09 90 00 | ||||||
| 21 | Each type of coating and/or product furnished | 1 | ||||
| SECTION 22 00 00 | ||||||
| 22 | PE100 High-density polyethylene piping and connections accessories | 1 | ||||
| 23 | Barrel type fire hydrant | 1 | ||||
| 24 | Flush type fire hydrant | 1 | ||||
| 25 | Quick connection for hydrant | 1 | ||||
| 26 | Gate valve for hydrant | 1 | ||||
| 27 | Valve box for hydrant | 1 | ||||
| 28 | Gate valve | 1 | ||||
| 29 | Valve box | 1 | ||||
| 30 | Air relief valve | 1 | ||||
| 31 | Fast acting anti-water hammer valve | 1 | ||||
| 32 | Geotextile | 1 | ||||
| 33 | Emergency eye-wash shower unit | 1 | ||||
| 34 | Water meter | 1 | ||||
| 35 | Hose bibb and Hose Connection Vacuum Breaker | 1 | ||||
| 36 | Backflow preventer (RPPD) | 1 | ||||
| 37 | Ball valve | 1 | ||||
| 38 | Strainer | 1 | ||||
| 39 | Bollards | 1 | ||||
| 40 | On-site electro-fusing procedures report | 1 | ||||
| SECTION 23 00 00 | ||||||
| 41 | Operation & Maintenance (O&M) Manuals | 1 | Pre-Final Inspection -15 | Shops to review and provide inputs as applicable. | ||
| SECTION 31 00 00 | ||||||
| 42 | Shoring Plan | 1 | ||||
| 43 | Borrow Material | 1 | ||||
| 44 | Material Proposed as Backfill | 1 | ||||
| 45 | Material Proposed as Soil and Topsoil | 1 |
&"Arial,Bold"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP) Page &P of &N
MSS Spanish
| RESUMEN MUESTRAS DE MATERIAL | NÚMERO PROYECTO: | |||
| QUUG 23-1014 PD | TÍTULO DE PROYECTO: | |||
| REPARAR SISTEMA DE AGUA POTABLE APRON, F2001, PH4 | SOLICITACIÓN / CONTRATO NO. |
| (A cumplimentar por el ingeniero del proyecto) | (A cumplimentar por administrador del contrato) | ||||||||||||||
| NÚMERO DE COPIAS REQUERIDAS | |||||||||||||||
| LÍNEA NÚMERO | PARTIDA O DESCRIPCIÓN DE PARTIDA, REFERENCIA DEL CONTRATO, TIPO DE PRESENTACIÓN | CERTIFICADO DE CUMPLIMIENTO | PLANOS DE TALLER | MUESTRAS | SELECCIÓN DE COLOR | RECOMENDACIONES DEL FABRICANTE | GARANTÍA DEL FABRICANTE | DATOS DE CATÁLOGO | INSTRUCCIONES DE FUNCIONAMIENTO | PROGRAMAS, LISTADOS, INFORMES, PLANES | DATOS TÉCNICOS | PRUEBAS | INFORMES DE TRABAJOS DE CAMPO | FECHA DE ENTREGA |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
FECHA RECEPCIÓN EN CONTRATACIÓN
fergusog: Enter the date received from the Contractor. (MM/DD/YY) FECHA EN INGENIERíA CIVIL fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
FECHA LÍMITE DE DEVOLUCIÓN
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
NÚMERO DE MUESTRA
fergusog: Enter the Submittal Number
FECHA NOTIFICACIÓN A CONTRATISTA SEGUNDA PRESENTACIÓN DEL CONTRATISTA
fergusog: Enter Resubmittal Number
APROBACIÓN FINAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
OBSERVACIONES
fergusog: Enter any comments pertaining to the submittal
APROBADO
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DESAPROBADO
fergusog: Enter date the Contractor was notified of submittal disapproval fergusog: Enter the submittal final approval date fergusog: Enter any comments pertaining to the submittal
| SECCIÓN 01 11 00 | ||||||
| 01 | Carta de garantía | 1 | Aceptación +15 | |||
| 02 | Programa de obra | 1 | Comienzo Contrato +7 | A revisar y aprobar por el BCE | ||
| 03 | Programa de ejecución | 1 | Comienzo Contrato +10 | |||
| 04 | Plan de obra | 1 | Comienzo Contrato +7 | |||
| 05 | Plan de movilización | 1 | Comienzo Contrato +15 | |||
| 06 | Plan de control de calidad | 1 | Comienzo Contrato +15 | |||
| 07 | Plan de protección medioambiental | 1 | Comienzo Contrato +15 | |||
| 08 | DD Forma 1354 | 1 | Inspección Pre-Final -15 | RP tiene que rellenarla en10 días después del BOD | ||
| 09 | Gestión de residuos y escombros | 1 | Inspección Final-15 | |||
| 10 | Planos As-Builts | 1 | Inspección Final -15 | |||
| 11 | Datos espaciales | 1 | Aprobación planos As-Built +10 | Los datos espaciales estarán basados en los planos As-Built aprobados. | ||
| 12 | Personal clave | 1 | Comienzo Contrato+15 | |||
| 13 | Plan de seguridad | 1 | Comienzo Contrato+15 | |||
| SECCIÓN 01 11 02 | ||||||
| 14 | Informe Geo-Radar (GPR) | 1 | ||||
| 15 | Plan de cortes de suministro de agua | 1 | Comiento Contrato+15 | |||
| 16 | Solicitud de exención de los criterios relativos al aeródromo y al espacio aéreo | 1 | Comiento Contrato+15 | |||
| 17 | Hoja de trabajo de evaluación de riesgos deliberados | 1 | Comiento Contrato+15 | |||
| 18 | Lista de comprobación de los requisitos de construcción del aeródromo | 1 | Comiento Contrato+15 | |||
| 19 | Plan de fases de construcción | 1 | Comiento Contrato+15 | |||
| 20 | Seguridad operativa en el aeródromo durante la construcción | 1 | Comiento Contrato+15 | |||
| SECCIÓN 09 90 00 | ||||||
| 21 | Cada tipo de recubrimiento y/o producto suministrado | 1 | ||||
| SECCIÓN 22 00 00 | ||||||
| 22 | Tubos de polietileno de alta densidad PE100 y accesorios de conexión | 1 | ||||
| 23 | Hidrante contraincendios tipo barril | 1 | ||||
| 24 | Hidrante enrasado | 1 | ||||
| 25 | Conexión rápida para hidrante | 1 | ||||
| 26 | Válvula de compuerta para hidrante | 1 | ||||
| 27 | Caja de válvulas para hidrante | 1 | ||||
| 28 | Válvula de compuerta | 1 | ||||
| 29 | Caja de válvulas | 1 | ||||
| 30 | Ventosa | 1 | ||||
| 31 | Válvula de alivio de acción rápida (anti golpe de ariete) | 1 | ||||
| 32 | Geotextil | 1 | ||||
| 33 | Ducha lava-ojos de emergencia | 1 | ||||
| 34 | Contador de agua | 1 | ||||
| 35 | Grifo de manguera y rompedor de vacío | 1 | ||||
| 36 | Desconector (RPPD) | 1 | ||||
| 37 | Válvula de bola | 1 | ||||
| 38 | Filtro colador | 1 | ||||
| 39 | Bolardos | 1 | ||||
| 40 | Informe de procedimientos de soldadura in-situ | 1 | ||||
| SECCIÓN 23 00 00 | ||||||
| 41 | Manuales de operación y mantenuimiento (O&M) | 1 | Inspección Pre-Final -15 | Los talleres lo revisarán y proveerán comentarios según se requiera. | ||
| SECCIÓN 31 00 00 | ||||||
| 42 | Plan de entibación | 4 | ||||
| 43 | Material de préstamo | 4 | ||||
| 44 | Material propuesto para relleno | 4 | ||||
| 45 | Material propuesto para tierra vegetal | 4 |
&"Arial,Bold"&8Resumen de muestras de material, Feb 05 (SAF/AQCP) Página &P de &N