Billings Cooling Tower Design Specifications.pdf
PDF 1 MB Posted
- Attached to
- Replace Cooling Tower Billings, Montana
- Solicitation number
- 47PD5526R0029
- Issued by
- Not on record
About this file
This document is a Project Manual containing specifications for the Billings Cooling Tower Design project at the James F. Battin Federal Courthouse in Billings, Montana, prepared for the General Services Administration (GSA) by Jackola Engineering & Architecture. The project is a single prime contract based on stipulated price and involves alterations to an existing mechanical system serving multiple occupant agencies.
The scope of work includes replacement of deteriorated cooling tower coils, sprayer nozzles, and evaporative media; relocation of variable frequency drives from outdoor exposed locations; and replacement of heat trace tape on exterior piping conveying non-glycol fluids. Multiple agencies will continue occupying building portions during construction, requiring coordination to maintain operations and emergency access. Key technical specifications address HVAC systems (including induced-draft cooling towers, hydronic piping, and testing/adjusting/balancing per ASHRAE and NEBB standards), electrical systems (selective demolition, low-voltage conductors/cables, grounding/bonding, and support hangers), piping insulation, and general construction requirements. Administrative requirements include electronic document submission, preconstruction and site mobilization meetings, progress reporting, submittal procedures with 15-day review timelines, and requests for interpretation (RFI) with 7-day response periods. The contractor must maintain project record documents, provide operation and maintenance data, and complete testing and balancing work prior to substantial completion. Professional engineering seals are required for mechanical/plumbing and electrical work per Montana licensure requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Billings Cooling Tower Design Billings, Montana
02-14-2025 Project Title Page 00 0101 1 of 1
SECTION 00 0101
PROJECT TITLE PAGE
100% SUBMITTAL
2/14/2025
PROJECT MANUAL
JAMES F. BATTIN FEDERAL COURTHOUSE
COOLING TOWER DESIGN
BILLINGS, MONTANA
PREPARED FOR:
GENERAL SERVICES ADMINISTRATION
PREPARED BY:
JACKOLA ENGINEERING & ARCHITECTURE
2250 HWY 93 S
KALISPELL, MT 59901
02-14-2025 Seals Page 00 0107 1 of 1
SECTION 00 0107
SEALS PAGE
MECHANICAL/PLUMBING
ELECTRICAL
END OF SECTION
M
ONTANA
No. 71046 PE
P R
O F
E S
S
I O N A L EN
G
IN
E E
R
L I C E NS E D
TYLER
ARNOLD
TONJUM
M
ONTANA
No. 84939 PE
P R
O F
E S
S
IO N A L EN
G
IN
E E
R
L I C E NS E D
JONATHAN
LEONARD
RUONAVAARA
02-14-2025 Table of Contents 00 0110 1 of 1
SECTION 00 0110
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
A. 00 0101 - Project Title Page
B. 00 0107 - Seals Page
C. 00 0110 - Table of Contents
SPECIFICATIONS
2.01 DIVISION 01 -- GENERAL REQUIREMENTS
A. 01 1000 - Summary
B. 01 2500 - Substitution Procedures
C. 01 3000 - Administrative Requirements
D. 01 4000 - Quality Requirements
E. 01 5000 - Temporary Facilities and Controls
F. 01 6000 - Product Requirements
G. 01 7000 - Execution and Closeout Requirements
H. 01 7800 - Closeout Submittals
2.02 DIVISION 02 -- EXISTING CONDITIONS
A. 02 4100 - Demolition
2.03 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
A. 23 0593 - Testing, Adjusting, and Balancing for HVAC
B. 23 0719 - HVAC Piping Insulation
C. 23 2113 - Hydronic Piping
D. 23 6514 - Induced-Draft Cooling Towers
2.04 DIVISION 26 -- ELECTRICAL
A. 26 0505 - Selective Demolition for Electrical
B. 26 0519 - Low-Voltage Electrical Power Conductors and Cables
C. 26 0526 - Grounding and Bonding for Electrical Systems
D. 26 0529 - Hangers and Supports for Electrical Systems
END OF SECTION
02-14-2025 Summary 01 1000 1 of 1
SECTION 01 1000
SUMMARY
PART 1 GENERAL
1.01 PROJECT
A. Project Name: Billings Cooling Tower Design
B. Owner's Name: General Services Administration (GSA).
C. Contractor Officer's Reprensative (COR) Name: Kevin Spruell.
D. Occupant Agency: Multiple
E. Architect's Name: Jackola Engineering & Architecture.
F. The Project consists of the alteration of an existing mechanical system.
1. An existing cooling tower in the James Battin courthouse has coils that are experinceing deterioration. The variable frequency drives that serve the cooling towers are also located outside and exposed to the elements. Piping serving the cooling towers has heatrace tape that is nearing the end of its useful life. The scope of work for this project includes the replacement of the coils with new, replacement of sprayer nozzels, replacement of evaporative media, the relocation of the variable frequency drives and the replacement of the heattrace tape on the exterior piping that conveys fluid not containing glycol.
1.02 CONTRACT DESCRIPTION
A. Contract Type: A single prime contract based on a Stipulated Price.
1.03 DESCRIPTION OF ALTERATIONS WORK
A. Scope of demolition and removal work is indicated on drawings.
B. HVAC: Restore existing system and equipment to prevent failure of equipment.
C. Electrical Power and Lighting: Alter existing system.
1.04 OCCUPANT AGENCY
A. Multiple agencies intend to continue to occupy portions of the existing building served by the affect equipment during the entire construction period.
B. Multiple agencies intend to occupy the areas served by the equipment to be replaced upon Substantial
Completion.
C. Schedule the Work to accommodate occupancy.
1.05 CONTRACTOR USE OF SITE AND PREMISES
A. Provide access to and from site as required by law and by GSA:
1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permit.
02-14-2025 Substitution Procedures 01 2500 1 of 3
SECTION 01 2500
SUBSTITUTION PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Procedural requirements for proposed substitutions.
1.02 RELATED REQUIREMENTS
A. Section 01 3000 - Administrative Requirements: Submittal procedures, coordination.
1.03 DEFINITIONS
A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.
1. Substitutions for Cause: Proposed due to changed Project circumstances beyond Contractor's control.
a. Unavailability.
b. Regulatory changes.
2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.
PART 2 PRODUCTS - MATERIAL AND EQUIPMENT SPECIFIED IN THE DRAWINGS OR SPECIFICATIONS MAY BE
SUBSTITUTED WITH AN APPROVED (BY ARCHITECT) EQUIVALENT MATERIAL.
PART 3 EXECUTION
3.01 GENERAL REQUIREMENTS
A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:
1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.
2. Agrees to provide the same warranty for the substitution as for the specified product.
3. Agrees to provide same or equivalent maintenance service and source of replacement parts, as applicable.
4. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to GSA.
5. Waives claims for additional costs or time extension that may subsequently become apparent.
B. Document each request with complete data substantiating compliance of proposed substitution with
Contract Documents. Burden of proof is on proposer.
1. Note explicitly any non-compliant characteristics.
C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.
02-14-2025 Substitution Procedures 01 2500 2 of 3
1. No specific form is required. Contractor's Substitution Request documentation must include the following:
a. Project Information:
1) Official project name and number, and any additional required identifiers established in
Contract Documents.
2) GSA's, COR's, and Contractor's names.
b. Substitution Request Information:
1) Discrete and consecutive Substitution Request number, and descriptive subject/title.
2) Indication of whether the substitution is for cause or convenience.
3) Issue date.
4) Reference to particular Contract Document(s) specification section number, title, and article/paragraph(s).
5) Description of Substitution.
6) Reason why the specified item cannot be provided.
7) Differences between proposed substitution and specified item.
8) Description of how proposed substitution affects other parts of work.
c. Attached Comparative Data: Provide point-by-point, side-by-side comparison addressing essential attributes specified, as appropriate and relevant for the item:
1) Physical characteristics.
2) In-service performance.
3) Expected durability.
4) Visual effect.
5) Sustainable design features.
6) Other salient features and requirements.
d. Impact of Substitution:
D. Limit each request to a single proposed substitution item.
3.02 SUBSTITUTION PROCEDURES DURING CONSTRUCTION
A. COR will consider requests for substitutions only within 15 days after date of Agreement.
B. Submit request for Substitution for Cause within 14 days of discovery of need for substitution, but not later than 14 days prior to time required for review and approval by COR, in order to stay on approved project schedule.
C. Submit request for Substitution for Convenience immediately upon discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by COR, in order to stay on approved project schedule.
02-14-2025 Substitution Procedures 01 2500 3 of 3
1. In addition to meeting general documentation requirements, document how the requested substitution benefits the GSA through cost savings, time savings, greater energy conservation, or in other specific ways.
2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.
D. Substitutions will not be considered under one or more of the following circumstances:
1. When acceptance will require revisions to the Contract Documents.
3.03 RESOLUTION
A. COR may request additional information and documentation prior to rendering a decision. Provide this data in an expeditious manner.
B. COR will notify Contractor in writing of decision to accept or reject request.
1. COR's decision following review of proposed substitution will be noted on the submitted form.
3.04 ACCEPTANCE
A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary
Instructions, or similar instruments provided for in the Conditions of the Contract.
02-14-2025 Administrative Requirements 01 3000 1 of 9
SECTION 01 3000
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General administrative requirements.
B. Electronic document submittal.
C. Preconstruction meeting.
D. Site mobilization meeting.
E. Progress meetings.
F. Construction progress schedule.
G. Contractor's daily reports.
H. Progress photographs.
I. Number of copies of submittals.
J. Requests for Interpretation (RFI) procedures.
K. Submittal procedures.
1.02 RELATED REQUIREMENTS
A. Section 01 6000 - Product Requirements: General product requirements.
B. Section 01 7000 - Execution and Closeout Requirements: Additional coordination requirements.
C. Section 01 7800 - Closeout Submittals: Project record documents; operation and maintenance data;
warranties and bonds.
1.03 GENERAL ADMINISTRATIVE REQUIREMENTS
A. Comply with requirements of Section 01 7000 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 ELECTRONIC DOCUMENT SUBMITTAL
A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF) format, as appropriate to the document, and transmitted via email or as directed by the COR.
1. Besides submittals for review, information, and closeout, this procedure applies to Requests for
Interpretation (RFIs), progress documentation, contract modification documents (e.g.
supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction punchlist, and any other document any participant wishes to make part of the project record.
2. It is Contractor's responsibility to submit documents in allowable format.
3. Paper document transmittals will not be reviewed.
02-14-2025 Administrative Requirements 01 3000 2 of 9
4. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.
B. Training: One, one-hour, web-based training session will be arranged for all participants, with representatives of COR and Contractor participating; further training is the responsibility of the user of the service.
C. Project Closeout: COR will determine when to terminate the service for the project and is responsible for obtaining archive copies of files for GSA.
3.02 PRECONSTRUCTION MEETING
A. Attendance Required:
1. GSA.
2. COR.
3. Contractor.
B. Agenda:
1. Execution of GSA-Contractor Agreement.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.
5. Designation of personnel representing the parties to Contract.
6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
7. Scheduling.
C. Record minutes and distribute copies within two days after meeting to participants, with two copies to
COR, GSA, participants, and those affected by decisions made.
3.03 SITE MOBILIZATION MEETING
A. Attendance Required:
1. Contractor.
2. GSA.
3. COR.
4. Contractor's superintendent.
5. Major subcontractors.
B. Agenda:
1. Use of premises by GSA and Contractor.
2. GSA's requirements.
3. Construction facilities and controls provided by GSA.
4. Temporary utilities provided by GSA.
02-14-2025 Administrative Requirements 01 3000 3 of 9
5. Survey and building layout.
6. Security and housekeeping procedures.
7. Schedules.
8. Application for payment procedures.
9. Procedures for testing.
10. Procedures for maintaining record documents.
11. Requirements for start-up of equipment.
12. Inspection and acceptance of equipment put into service during construction period.
C. Record minutes and distribute copies within two days after meeting to participants, with two copies to
COR, GSA, participants, and those affected by decisions made.
3.04 PROGRESS MEETINGS
A. Attendance Required:
1. Contractor.
2. GSA.
3. COR.
4. Contractor's superintendent.
5. Major subcontractors.
B. Agenda:
1. Review minutes of previous meetings.
2. Review of work progress.
3. Field observations, problems, and decisions.
4. Identification of problems that impede, or will impede, planned progress.
5. Review of submittals schedule and status of submittals.
6. Maintenance of progress schedule.
7. Corrective measures to regain projected schedules.
8. Planned progress during succeeding work period.
9. Maintenance of quality and work standards.
10. Effect of proposed changes on progress schedule and coordination.
11. Other business relating to work.
C. Record minutes and distribute copies within two days after meeting to participants, with two copies to
COR, GSA, participants, and those affected by decisions made.
3.05 CONSTRUCTION PROGRESS SCHEDULE - SEE SECTION 01 3216
3.06 DAILY CONSTRUCTION REPORTS
A. Include only factual information. Do not include personal remarks or opinions regarding operations and/or personnel.
02-14-2025 Administrative Requirements 01 3000 4 of 9
B. Prepare a daily construction report recording the following information concerning events at Project site and project progress:
1. Date.
2. High and low temperatures, and general weather conditions.
3. List of subcontractors at Project site.
4. List of separate contractors at Project site.
5. Approximate count of personnel at Project site.
6. Major equipment at Project site.
7. Material deliveries.
8. Safety, environmental, or industrial relations incidents.
9. Meetings and significant decisions.
10. Stoppages, delays, shortages, and losses. Include comparison between scheduled work activities
(in Contractor's most recently updated and published schedule) and actual activities. Explain differences, if any. Note days or periods when no work was in progress and explain the reasons why.
11. Testing and/or inspections performed.
12. Signature of Contractor's authorized representative.
3.07 PROGRESS PHOTOGRAPHS
A. Submit photographs with each application for payment, taken not more than 3 days prior to submission of application for payment.
B. Submit new photographs at least once a month, within 3 days after being taken.
C. Maintain one set of all photographs at project site for reference; same copies as submitted, identified as such.
D. Photography Type: Digital; electronic files.
E. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to COR.
F. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.
1. Delivery Medium: Via email.
2. File Naming: Include project identification, date and time of view, and view identification.
3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.
3.08 REQUESTS FOR INTERPRETATION (RFI)
A. Definition: A request seeking one of the following:
02-14-2025 Administrative Requirements 01 3000 5 of 9
1. An interpretation, amplification, or clarification of some requirement of Contract Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space
(interference); or when an item of work is described differently at more than one place in the
Contract Documents.
2. A resolution to an issue which has arisen due to field conditions and affects design intent.
B. Whenever possible, request clarifications at the next appropriate project progress meeting, with response entered into meeting minutes, rendering unnecessary the issuance of a formal RFI.
C. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of the Contract
Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.
1. Prepare a separate RFI for each specific item.
a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.
b. Do not forward requests which solely require internal coordination between subcontractors.
2. Prepare in a format and with content acceptable to GSA.
3. Prepare using an electronic version of the form appended to this section.
4. Combine RFI and its attachments into a single electronic file. PDF format is preferred.
D. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.
1. Include in each request Contractor's signature attesting to good faith effort to determine from the
Contract Documents information requiring interpretation.
2. Unacceptable Uses for RFIs: Do not use RFIs to request the following::
a. Approval of submittals (use procedures specified elsewhere in this section).
b. Approval of substitutions (see Section - 01 6000 - Product Requirements)
c. Different methods of performing work than those indicated in the Contract Drawings and
Specifications (comply with provisions of the Conditions of the Contract).
3. Improper RFIs: Requests not prepared in compliance with requirements of this section, and/or missing key information required to render an actionable response. They will be returned without a response, with an explanatory notation.
4. Frivolous RFIs: Requests regarding information that is clearly indicated on, or reasonably inferable from, the Contract Documents, with no additional input required to clarify the question.
They will be returned without a response, with an explanatory notation.
E. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.
02-14-2025 Administrative Requirements 01 3000 6 of 9
1. Official Project name and number, and any additional required identifiers established in Contract
Documents.
2. GSA's, COR's, and Contractor's names.
3. Discrete and consecutive RFI number, and descriptive subject/title.
4. Issue date, and requested reply date.
5. Reference to particular Contract Document(s) requiring additional information/interpretation.
Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).
6. Annotations: Field dimensions and/or description of conditions which have engendered the request.
7. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example; routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.
F. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.
G. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.
1. Indicate current status of every RFI. Update log promptly and on a regular basis.
2. Note dates of when each request is made, and when a response is received.
3. Highlight items for which a timely response has not been received to date.
H. Review Time: COR will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.
1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.
I. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to
Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate
Change Order request to GSA.
1. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith. Identify the amended RFI with an R suffix to the original number.
2. Do not extend applicability of a response to specific item to encompass other similar conditions, unless specifically so noted in the response.
02-14-2025 Administrative Requirements 01 3000 7 of 9
3. Upon receipt of a response, promptly review and distribute it to all affected parties, and update the RFI Log.
4. Notify COR within seven calendar days if an additional or corrected response is required by submitting an amended version of the original RFI, identified as specified above.
3.09 SUBMITTAL SCHEDULE
A. Submit to COR for review a schedule for submittals in tabular format.
1. Submit at the same time as the preliminary schedule.
2. Coordinate with Contractor's construction schedule and schedule of values.
3. Format schedule to allow tracking of status of submittals throughout duration of construction.
4. Account for time required for preparation, review, manufacturing, fabrication and delivery when establishing submittal delivery and review deadline dates.
a. For assemblies, equipment, systems comprised of multiple components and/or requiring detailed coordination with other work, allow for additional time to make corrections or revisions to initial submittals, and time for their review.
3.10 NUMBER OF COPIES OF SUBMITTALS
A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.
3.11 SUBMITTAL PROCEDURES
A. General Requirements:
1. Use a single transmittal for related items.
2. Submit separate packages of submittals for review and submittals for information, when included in the same specification section.
3. Transmit using approved form.
a. Use Contractor's form, subject to prior approval by COR.
4. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.
5. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number;
and specification section number and article/paragraph, as appropriate on each copy.
6. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.
a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.
7. Deliver each submittal on date noted in submittal schedule, unless an earlier date has been agreed to by all affected parties, and is of the benefit to the project.
02-14-2025 Administrative Requirements 01 3000 8 of 9
a. Send submittals in electronic format via email to COR.
8. Schedule submittals to expedite the Project, and coordinate submission of related items.
a. For each submittal for review, allow 15 days excluding delivery time to and from the
Contractor.
b. For sequential reviews involving COR's consultants, GSA, or another affected party, allow an additional 7 days.
c. For sequential reviews involving approval from authorities having jurisdiction (AHJ), in addition to COR's approval, allow an additional 30 days.
9. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.
10. Provide space for Contractor and COR review stamps.
11. When revised for resubmission, identify all changes made since previous submission.
12. Distribute reviewed submittals. Instruct parties to promptly report inability to comply with requirements.
13. Incomplete submittals will not be reviewed, unless they are partial submittals for distinct portion(s) of the work, and have received prior approval for their use.
14. Submittals not requested will be recognized, and will be returned "Not Reviewed", B. Product Data Procedures:
1. Submit only information required by individual specification sections.
2. Collect required information into a single submittal.
3. Submit concurrently with related shop drawing submittal.
4. Do not submit (Material) Safety Data Sheets for materials or products.
5. Submit sustainable design reporting submittals under separate cover.
C. Shop Drawing Procedures:
1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting the
Contract Documents and coordinating related work.
2. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.
D. Samples Procedures:
1. Transmit related items together as single package.
2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.
3. Include with transmittal high-resolution image files of samples to facilitate electronic review and approval. Provide separate submittal page for each item image.
3.12 SUBMITTAL REVIEW
02-14-2025 Administrative Requirements 01 3000 9 of 9
A. Submittals for Review: COR will review each submittal, and approve, or take other appropriate action.
B. Submittals for Information: COR will acknowledge receipt and review. See below for actions to be taken
C. COR's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.
D. COR's and consultants' actions on items submitted for review:
1. Authorizing purchasing, fabrication, delivery, and installation:
a. "Approved", or language with same legal meaning.
b. "Approved as Noted, Resubmission not required", or language with same legal meaning.
1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.
c. "Approved as Noted, Resubmit for Record", or language with same legal meaning.
2. Not Authorizing fabrication, delivery, and installation:
a. "Revise and Resubmit".
1) Resubmit revised item, with review notations acknowledged and incorporated.
b. "Rejected".
1) Submit item complying with requirements of Contract Documents.
E. COR's and consultants' actions on items submitted for information:
1. Items for which no action was taken:
a. "Received" - to notify the Contractor that the submittal has been received for record only.
2. Items for which action was taken:
a. "Reviewed" - no further action is required from Contractor.
02-14-2025 Quality Requirements 01 4000 1 of 4
SECTION 01 4000
QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Submittals.
B. Quality assurance.
C. References and standards.
D. Inspection agencies and services.
E. Contractor's construction-related professional design services.
F. Control of installation.
G. Manufacturers' field services.
H. Defect Assessment.
1.02 RELATED REQUIREMENTS
A. Section 01 3000 - Administrative Requirements: Submittal procedures.
B. Section 01 6000 - Product Requirements: Requirements for material and product quality.
1.03 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Designer's Qualification Statement: Submit for COR's knowledge as contract administrator, or for GSA's information.
1. Include information for each individual professional responsible for producing, or supervising production of, design-related professional services provided by Contractor.
a. Full name.
b. Professional licensure information.
c. Statement addressing extent and depth of experience specifically relevant to design of items assigned to Contractor.
C. Design Data: Submit for COR's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the contract documents, or for
GSA's information.
1. Include calculations that have been used to demonstrate compliance to performance and regulatory criteria provided, and to determine design solutions.
2. Include required product data and shop drawings.
3. Include a statement or certification attesting that design data complies with criteria indicated, such as building codes, loads, functional, and similar engineering requirements.
4. Include signature and seal of design professional responsible for allocated design services on calculations and drawings.
02-14-2025 Quality Requirements 01 4000 2 of 4
D. Test Reports: After each test/inspection, promptly submit two copies of report to COR and to
Contractor.
1. Include:
a. Date issued.
b. Project title and number.
c. Name of inspector.
d. Date and time of sampling or inspection.
e. Identification of product and specifications section.
f. Location in the Project.
g. Type of test/inspection.
h. Date of test/inspection.
i. Results of test/inspection.
j. Compliance with Contract Documents.
k. When requested by COR, provide interpretation of results.
2. Test report submittals are for COR's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the contract documents, or for GSA's information.
1.04 QUALITY ASSURANCE
A. Designer Qualifications: Where professional engineering design services and design data submittals are specifically required of Contractor by Contract Documents, provide services of a Professional Engineer experienced in design of this type of work and licensed in the State in which the Project is located.
1.05 REFERENCES AND STANDARDS
A. For products and workmanship specified by reference to a document or documents not included in the
Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.
B. Comply with reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.
C. Obtain copies of standards where required by product specification sections.
D. Maintain copy at project site during submittals, planning, and progress of the specific work, until
Substantial Completion.
E. Should specified reference standards conflict with Contract Documents, request clarification from COR before proceeding.
PART 3 EXECUTION
2.01 CONTROL OF INSTALLATION
02-14-2025 Quality Requirements 01 4000 3 of 4
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.
B. Comply with manufacturers' instructions, including each step in sequence.
C. Should manufacturers' instructions conflict with Contract Documents, request clarification from COR before proceeding.
D. Comply with specified standards as minimum quality for the work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Have work performed by persons qualified to produce required and specified quality.
F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.
G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.
2.02 TESTING AND INSPECTION
A. Testing Agency Duties:
1. Provide qualified personnel at site. Cooperate with COR and Contractor in performance of services.
2. Perform specified sampling and testing of products in accordance with specified standards.
3. Ascertain compliance of materials and mixes with requirements of Contract Documents.
4. Promptly notify COR and Contractor of observed irregularities or non-compliance of Work or products.
5. Perform additional tests and inspections required by COR.
6. Submit reports of all tests/inspections specified.
B. Limits on Testing/Inspection Agency Authority:
1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.
2. Agency may not approve or accept any portion of the Work.
3. Agency may not assume any duties of Contractor.
4. Agency has no authority to stop the Work.
C. Contractor Responsibilities:
1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.
2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.
3. Provide incidental labor and facilities:
a. To provide access to Work to be tested/inspected.
b. To obtain and handle samples at the site or at source of Products to be tested/inspected.
c. To facilitate tests/inspections.
02-14-2025 Quality Requirements 01 4000 4 of 4
d. To provide storage and curing of test samples.
4. Notify COR and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.
5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.
6. Arrange with GSA's agency and pay for additional samples, tests, and inspections required by
Contractor beyond specified requirements.
D. Re-testing required because of non-compliance with specified requirements shall be performed by the same agency on instructions by COR.
E. Re-testing required because of non-compliance with specified requirements shall be paid for by
Contractor.
2.03 DEFECT ASSESSMENT
A. Replace Work or portions of the Work not complying with specified requirements.
02-14-2025 Temporary Facilities and Controls 01 5000 1 of 2
SECTION 01 5000
TEMPORARY FACILITIES AND CONTROLS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Temporary sanitary facilities.
B. Temporary Controls: Barriers, enclosures, and fencing.
C. Security requirements.
D. Waste removal facilities and services.
1.02 TEMPORARY UTILITIES
A. GSA will provide the following:
1. Electrical power and metering, consisting of connection to existing facilities.
2. Water supply, consisting of connection to existing facilities.
1.03 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.
B. Maintain daily in clean and sanitary condition.
1.04 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
1.05 INTERIOR ENCLOSURES
A. Provide temporary partitions as indicated to separate work areas from occupied areas, to prevent penetration of dust and moisture into occupied areas, and to prevent damage to existing materials and equipment.
B. Construction: Framing and reinforced polyethylene sheet materials with closed joints and sealed edges at intersections with existing surfaces:
1.06 VEHICULAR ACCESS AND PARKING
A. Comply with regulations relating to use of streets and sidewalks, access to emergency facilities, and access for emergency vehicles.
B. Provide and maintain access to fire hydrants, free of obstructions.
1.07 WASTE REMOVAL
A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.
B. Provide containers with lids. Remove trash from site periodically.
C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless
02-14-2025 Temporary Facilities and Controls 01 5000 2 of 2 otherwise approved by the authorities having jurisdiction.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
02-14-2025 Product Requirements 01 6000 1 of 3
SECTION 01 6000
PRODUCT REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General product requirements.
B. Re-use of existing products.
C. Transportation, handling, storage and protection.
D. Product option requirements.
E. Substitution limitations.
F. Maintenance materials, including extra materials, spare parts, tools, and software.
1.02 RELATED REQUIREMENTS
A. Section 01 1000 - Summary: Lists of products to be removed from existing building.
B. Section 01 2500 - Substitution Procedures: Substitutions made during procurement and/or construction phases.
1.03 SUBMITTALS
A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.
B. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
C. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.
1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.
PART 2 PRODUCTS
2.01 EXISTING PRODUCTS
A. Specific Products to be Reused: The reuse of certain materials and equipment already existing on the project site is required.
1. See drawings for list of items required to be salvaged for reuse and relocation.
2.02 NEW PRODUCTS
A. Provide new products unless specifically required or permitted by the Contract Documents.
2.03 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.
02-14-2025 Product Requirements 01 6000 2 of 3
B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.
C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions: Submit a request for substitution for any manufacturer not named.
PART 3 EXECUTION
3.01 SUBSTITUTION LIMITATIONS
A. See Section 01 2500 - Substitution Procedures.
3.02 TRANSPORTATION AND HANDLING
A. Package products for shipment in manner to prevent damage; for equipment, package to avoid loss of factory calibration.
B. If special precautions are required, attach instructions prominently and legibly on outside of packaging.
C. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.
D. Transport and handle products in accordance with manufacturer's instructions.
E. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas.
F. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.
G. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage, and to minimize handling.
H. Arrange for the return of packing materials, such as wood pallets, where economically feasible.
3.03 STORAGE AND PROTECTION
A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication. See Section 01 7419.
B. Store and protect products in accordance with manufacturers' instructions.
C. Store with seals and labels intact and legible.
D. Store sensitive products in weathertight, climate-controlled enclosures in an environment favorable to product.
E. For exterior storage of fabricated products, place on sloped supports above ground.
F. Protect products from damage or deterioration due to construction operations, weather, precipitation, humidity, temperature, sunlight and ultraviolet light, dirt, dust, and other contaminants.
G. Comply with manufacturer's warranty conditions, if any.
H. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.
02-14-2025 Product Requirements 01 6000 3 of 3
I. Prevent contact with material that may cause corrosion, discoloration, or staining.
J. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.
K. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.
02-14-2025 Execution and Closeout
Requirements 01 7000 1 of 7
SECTION 01 7000
EXECUTION AND CLOSEOUT REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Examination, preparation, and general installation procedures.
B. Requirements for alterations work, including selective demolition.
C. Cutting and patching.
D. Cleaning and protection.
E. Closeout procedures, including Contractor's Correction Punch List, except payment procedures.
F. General requirements for maintenance service.
1.02 RELATED REQUIREMENTS
A. Section 01 1000 - Summary: Limitations on working in existing building; continued occupancy; work sequence; identification of salvaged and relocated materials.
B. Section 01 3000 - Administrative Requirements: Submittals procedures, Electronic document submittal service.
C. Section 01 4000 - Quality Requirements: Testing and inspection procedures.
D. Section 01 7800 - Closeout Submittals: Project record documents, operation and maintenance data, warranties, and bonds.
1.03 REFERENCE STANDARDS
A. NFPA 241 - Standard for Safeguarding Construction, Alteration, and Demolition Operations; 2019.
1.04 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Cutting and Patching: Submit written request in advance of cutting or alteration that affects:
1. Structural integrity of any element of Project.
2. Integrity of weather exposed or moisture resistant element.
3. Efficiency, maintenance, or safety of any operational element.
4. Visual qualities of sight exposed elements.
5. Work of GSA or separate Contractor.
1.05 PROJECT CONDITIONS
A. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.
B. Noise Control: Provide methods, means, and facilities to minimize noise produced by construction operations.
1. At All Times: Excessively noisy tools and operations will not be tolerated inside the building at any time of day; excessively noisy includes jackhammers, pile drivers, and pneumatic hammers.
Execution and Closeout
Requirements 01 7000 2 of 7
1.06 COORDINATION
A. Coordinate scheduling, submittals, and work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.
B. Notify affected utility companies and comply with their requirements.
C. Verify that utility requirements and characteristics of new operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.
D. Coordinate space requirements, supports, and installation of mechanical and electrical work that are indicated diagrammatically on drawings. Follow routing indicated for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
E. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.
F. Coordinate completion and clean-up of work of separate sections.
PART 2 PRODUCTS
2.01 PATCHING MATERIALS
A. New Materials: As specified in product sections; match existing products and work for patching and extending work.
B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.
C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01 6000 - Product Requirements.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work. Start of work means acceptance of existing conditions.
B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached.
C. Examine and verify specific conditions described in individual specification sections.
D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication.
E. Verify that utility services are available, of the correct characteristics, and in the correct locations.
F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions
Execution and Closeout
Requirements 01 7000 3 of 7 affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions.
3.02 PREPARATION
A. Clean substrate surfaces prior to applying next material or substance.
B. Seal cracks or openings of substrate prior to applying next material or substance.
C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.
3.03 GENERAL INSTALLATION REQUIREMENTS
A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement.
B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated.
C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated.
D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated.
E. Make neat transitions between different surfaces, maintaining texture and appearance.
3.04 ALTERATIONS
A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only.
1. Verify that construction and utility arrangements are as indicated.
2. Report discrepancies to COR before disturbing existing installation.
3. Beginning of alterations work constitutes acceptance of existing conditions.
B. Remove existing work as indicated and as required to accomplish new work.
1. Remove items indicated on drawings.
2. Relocate items indicated on drawings.
3. Where new surface finishes are to be applied to existing work, perform removals, patch, and prepare existing surfaces as required to receive new finish; remove existing finish if necessary for successful application of new finish.
4. Where new surface finishes are not specified or indicated, patch holes and damaged surfaces to match adjacent finished surfaces as closely as possible.
C. Services (Including but not limited to HVAC, Plumbing, Fire Protection, Electrical, and
Telecommunications): Remove, relocate, and extend existing systems to accommodate new construction.
1. Maintain existing active systems that are to remain in operation; maintain access to equipment and operational components; if necessary, modify installation to allow access or provide access panel.
Execution and Closeout
Requirements 01 7000 4 of 7
2. Where existing systems or equipment are not active and Contract Documents require reactivation, put back into operational condition; repair supply, distribution, and equipment as required.
3. Where existing active systems serve occupied facilities but are to be replaced with new services, maintain existing systems in service until new systems are complete and ready for service.
a. Disable existing systems only to make switchovers and connections; minimize duration of outages.
b. Provide temporary connections as required to maintain existing systems in service.
4. Verify that abandoned services serve only abandoned facilities.
5. Remove abandoned pipe, ducts, conduits, and equipment , including those above accessible ceilings; remove back to source of supply where possible, otherwise cap stub and tag with identification; patch holes left by removal using materials specified for new construction.
D. Protect existing work to remain.
1. Prevent movement of structure; provide shoring and bracing if necessary.
2. Perform cutting to accomplish removals neatly and as specified for cutting new work.
3. Repair adjacent construction and finishes damaged during removal work.
E. Adapt existing work to fit new work: Make as neat and smooth transition as possible.
F. Patching: Where the existing surface is not indicated to be refinished, patch to match the surface finish that existed prior to cutting. Where the surface is indicated to be refinished, patch so that the substrate is ready for the new finish.
G. Refinish existing surfaces as indicated:
1. Where rooms or spaces are indicated to be refinished, refinish…