This is a Bid Tabulation Form from the Board of Regents of the University System of Georgia for Project No. CCGA-1528/CCGA-2610, titled "SAC Fascia and Soffit Replacement" at College of Coastal Georgia. The bid date was November 12, 2025, at 2:00 PM. The project involves the replacement of fascia and soffit components at the specified campus location. Two contractors submitted bids for this project, with both acknowledging surety requirements as part of their proposals.

The base bid amounts submitted were $278,396 from Anderson Environmental, Inc. and $269,350.00 from UGMS, Inc. The apparent low bidder is UGMS, Inc., with a bid amount of $269,350.00. The tabulation was certified as correct by a University System of Georgia official who verified the bids against the submitted proposal forms. No alternative bid amounts or deductions were recorded for either contractor in this tabulation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX 8 C

Board of Regents of the University System of Georgia

BID TABULATION FORM

Project No.: CCGA-1528 CCGA- 2610 Bid Date: November 12,2025 2:00PM

Project Name: SAC Fascia and Soffit Replacement Campus: College of Coastal Georgia

Contractor

Acknow. of

Surety Base Bid

Ded.

Alt. #1

Anderson Enviromental, Inc YES 278,396

UGMS, Inc. YES 269,350.00

I certify that this is a correct tabulation of bids as read aloud, and I certify that I have personnally and visually checked the bid tabulation against the proposal forms submitted.

The apparent low bidder is: UGMS, Inc Signed: