Bid Summary.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- Streets East Facility Boiler Replacement
- Solicitation number
- 14081-0-2025-BG
- Issued by
- Dane County, Mattoon Village, Wisconsin
About this file
This is a Bid Summary document from the City of Madison Engineering Department for Request for Bids (RFB #14081-0-2025-BG) regarding a Streets East Facility Boiler Replacement project located at 4602 Sycamore Avenue, Madison, Wisconsin. The procurement seeks qualified vendors to complete a fixed-price contract for comprehensive boiler replacement services at the Streets East Facility. Two mandatory site visits were scheduled for October 14th at 11:00 AM CST and October 22nd at 1:00 PM CST to allow potential bidders to fully understand project requirements. Bid responses were due on October 27th, 2025 at 2:00 PM CST, with vendor questions required to be submitted by October 22nd, 2025. The contract was awarded to Southport Engineered Systems, LLC.
Five vendors submitted bids for the boiler replacement work, with total costs ranging from $98,700.00 to $155,000.00. The winning bidder, Southport Engineered Systems, LLC, submitted a total cost of $105,790.00. Three of the five bidders qualified as local vendors under the City of Madison's local vendor preference purchasing policies. Local vendor totals were calculated for qualifying bidders, with amounts ranging from $104,732.10 to $153,450.00. The procurement included provisions for small business enterprises, required compliance with affirmative action requirements for vendors employing 15 or more employees with annual City business exceeding $50,000, and incorporated cooperative purchasing options available for other municipalities. The City of Madison's tax-exempt registration number is 008-1020421147-08 with federal tax ID #39-6005507.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFB 14081.pdf | ||
| Addendum 1.pdf | ||
| RFB 14081 Award Recommendation.pdf | ||
| RFB 14081.pdf.crdownload | CRDOWNLOAD file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFB 14081-0-2025-BG | 1901 Inc | Mechanical Inc dba Helm Service | Hooper Corporation | IKM | Southport Engineered Systems, LLC. | Sun Mechanical LLC | |
| Awarded to: Southport Engineered Systems, LLC. | |||||||
| Item | Description | Total Cost | Total Cost | Total Cost | Total Cost | Total Cost | Total Cost |
| 1 | Streets East Facility Boiler Replacement in |
conformance with the specifications described in this
| solicitation. | $155,000.00 | $114,380.00 | $105,790.00 | $122,125.00 | $98,700.00 | $110,000.00 | ||
| Local Vendor | Yes | No | Yes | Yes | No | No | ||
| Local Vendor Total | $153,450.00 | $104,732.10 | $120,903.75 |