Bid Sheets Group 1.pdf
PDF 161 KB Posted
- Attached to
- Count Station Maintenance
- Solicitation number
- RFB 605 2300000729 1
- Issued by
- Elliott County, Kentucky
About this file
This is a bid sheet for Group 1 covering Districts 1, 2, 3, and 4 for a Station Maintenance Request for Bid (RFB) dated April 28, 2023. The project involves the furnishing and installation of traffic signal and electrical infrastructure components across four districts. Work items include bore and jack pipe installation, conduit installation in various sizes, electrical service installation, cabinet installation (galvanized steel and pad/pole mount types), junction box installation in multiple configurations, piezoelectric sensor installation, wooden pole and post installation, trench excavation and backfill, cable and loop wire installation, saw slot and fill work, lane and shoulder closure management, and sidewalk removal and replacement. District 1 and 2 each contain identical line items with quantities including 50 linear feet of 2-inch pipe, 400 linear feet of 1-inch conduit, 200 linear feet of 2-inch conduit, 1,400 linear feet of saw slot and fill, 8,000 linear feet of loop wire, and various other components. District 3 contains similar items with increased quantities in most categories, including 500 linear feet of 1-inch conduit, 250 linear feet of 2-inch conduit, 1,750 linear feet of saw slot and fill, and 10,000 linear feet of loop wire. District 4 contains the smallest scope with reduced quantities across all line items.
The bid sheet provides line-item quantities for unit pricing but does not contain completed unit prices or extended price calculations in the document provided. Bidders are required to complete the Unit Price and Extended Price columns for each line item across all four districts, with separate totals calculated for each district and a final Group 1 total. The document indicates this is part of a larger bidding process referenced as "Bid Count Station Maintenance RFB 04-28-23.pdf," suggesting multiple bid groups or divisions exist for this project. No information regarding pricing terms, set-asides, incumbent contractors, funding sources, or contract term details is provided within this bid sheet document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| District Map.pdf | ||
| Final_RFB_605_2300000729_1_SO_FORM.PDF | ||
| FHWA-1273.pdf | ||
| How to Submit an Online Response - March 2023.pdf | ||
| Annual Affidavit for Bidders, Offerors and Contractors - Jan 2023.docx | DOCX document | |
| Drawings.pdf | ||
| Bid Sheets Group 4.pdf | ||
| Bid Sheet Group 2.pdf | ||
| Buy America Clause.pdf | ||
| Bid Sheets Group 3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Group 1 – Districts 1, 2, 3, and 4
Group 1: District 1
Item Description Unit D01 Quantity
D01 Unit Price
D01 Extended
Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50
2 Furnish and Install Conduit 1¼ Inch LIN FT 400
3 Furnish and Install Conduit 2 Inch LIN FT 200
4 Furnish and Install Electrical Service EACH 2
5 Furnish and Install Galvanized Steel Cabinet EACH 2
6 Install Pad Mount Cabinet EACH 2
7 Install Pole Mount Cabinet EACH 2
8 Furnish and Install Junction Box 10x8x4 EACH 2
9 Furnish and Install Junction Box Type A EACH 12
10 Furnish and Install Junction Box Type B EACH 12
11 Saw Slot and Fill LIN FT 1400
12 Furnish, Install and Remove Lane Closure EACH 16
13 Furnish, Install and Remove Shoulder Closure EACH 8
14 Furnish and Install Piezoelectric Sensor EACH 12
15 Install Piezoelectric Sensor EACH 12
16 Furnish and Install 35’ Wooden Pole EACH 2
17 Excavate Trench and Backfill LIN FT 600
18 Furnish and Install Cable No. 14/1 Pair LIN FT 400
19 Furnish and Install Loop Wire LIN FT 8000
20 Furnish and Install Ground Wire LIN FT 40
21 Furnish and Install Wood Post EACH 6
22 Remove and Replace Sidewalk SQYD 1
23 Loop Test EACH 1
Group 1: District 1 Total
Group 1: District 2
Item Description Unit D02 Quantity
D02 Unit Price
D02 Extended
Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50
2 Furnish and Install Conduit 1¼ Inch LIN FT 400
3 Furnish and Install Conduit 2 Inch LIN FT 200
4 Furnish and Install Electrical Service EACH 2
5 Furnish and Install Galvanized Steel Cabinet EACH 2
6 Install Pad Mount Cabinet EACH 2
7 Install Pole Mount Cabinet EACH 2
8 Furnish and Install Junction Box 10x8x4 EACH 2
9 Furnish and Install Junction Box Type A EACH 12
10 Furnish and Install Junction Box Type B EACH 12
11 Saw Slot and Fill LIN FT 1400
12 Furnish, Install and Remove Lane Closure EACH 16
13 Furnish, Install and Remove Shoulder Closure EACH 8
14 Furnish and Install Piezoelectric Sensor EACH 12
15 Install Piezoelectric Sensor EACH 12
16 Furnish and Install 35’ Wooden Pole EACH 2
17 Excavate Trench and Backfill LIN FT 600
18 Furnish and Install Cable No. 14/1 Pair LIN FT 400
19 Furnish and Install Loop Wire LIN FT 8000
20 Furnish and Install Ground Wire LIN FT 40
21 Furnish and Install Wood Post EACH 6
22 Remove and Replace Sidewalk SQYD 1
Group 1: District 2 Total
Group 1: District 3
Item Description Unit D03 Quantity
D03 Unit Price
D03 Extended
Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50
2 Furnish and Install Conduit 1¼ Inch LIN FT 500
3 Furnish and Install Conduit 2 Inch LIN FT 250
4 Furnish and Install Electrical Service EACH 2
5 Furnish and Install Galvanized Steel Cabinet EACH 3
6 Install Pad Mount Cabinet EACH 2
7 Install Pole Mount Cabinet EACH 2
8 Furnish and Install Junction Box 10x8x4 EACH 2
9 Furnish and Install Junction Box Type A EACH 15
10 Furnish and Install Junction Box Type B EACH 15
11 Saw Slot and Fill LIN FT 1750
12 Furnish, Install and Remove Lane Closure EACH 20
13 Furnish, Install and Remove Shoulder Closure EACH 10
14 Furnish and Install Piezoelectric Sensor EACH 15
15 Install Piezoelectric Sensor EACH 15
16 Furnish and Install 35’ Wooden Pole EACH 2
17 Excavate Trench and Backfill LIN FT 750
18 Furnish and Install Cable No. 14/1 Pair LIN FT 500
19 Furnish and Install Loop Wire LIN FT 10000
20 Furnish and Install Ground Wire LIN FT 50
21 Furnish and Install Wood Post EACH 8
22 Remove and Replace Sidewalk SQYD 1
Group 1: District 3 Total
Group 1: District 4
Item Description Unit D04 Quantity
D04 Unit Price
D04 Extended
Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50
2 Furnish and Install Conduit 1¼ Inch LIN FT 250
3 Furnish and Install Conduit 2 Inch LIN FT 125
4 Furnish and Install Electrical Service EACH 1
5 Furnish and Install Galvanized Steel Cabinet EACH 1
6 Install Pad Mount Cabinet EACH 1
7 Install Pole Mount Cabinet EACH 1
8 Furnish and Install Junction Box 10x8x4 EACH 1
9 Furnish and Install Junction Box Type A EACH 7
10 Furnish and Install Junction Box Type B EACH 7
11 Saw Slot and Fill LIN FT 875
12 Furnish, Install and Remove Lane Closure EACH 10
13 Furnish, Install and Remove Shoulder Closure EACH 5
14 Furnish and Install Piezoelectric Sensor EACH 10
15 Install Piezoelectric Sensor EACH 10
16 Furnish and Install 35’ Wooden Pole EACH 1
17 Excavate Trench and Backfill LIN FT 375
18 Furnish and Install Cable No. 14/1 Pair LIN FT 250
19 Furnish and Install Loop Wire LIN FT 5000
20 Furnish and Install Ground Wire LIN FT 25
21 Furnish and Install Wood Post EACH 3
22 Remove and Replace Sidewalk SQYD 1
Group 1: District 4 Total
Group 1: Districts 1, 2, 3 and 4
District 1 Total
District 2 Total
District 3 Total
District 4 Total
Group 1 Total Bid
| Count Station Maintenance RFB 04-28-23.pdf |
| Item |
| Item |
| Item |
| Item |
File details come from the government source that posted it. Updated .