This is a bid set specifications and project manual for the City of Green Cove Springs, Florida, prepared by CPH Consulting, LLC, for the DEP SRF Pine Avenue Force Main Extension project (DEP SRF Agreement No. WW100450). The project involves constructing approximately 10,500 linear feet of 16-inch fusible PVC force main installed via directional drilling, Pump Station 2 collection system modifications, and limited decommissioning activities for the South Wastewater Treatment Facility. Bidding documents are available electronically in PDF format through the designated bidding website. A non-mandatory pre-bid conference is scheduled as indicated in the Advertisement for Bids. Bids must be submitted in sealed, plainly marked packages to the City of Green Cove Springs, Attn: Scott Schultz, 321 Walnut Street, Green Cove Springs, Florida 32043, by the deadline specified in the Advertisement for Bids. A required site visit must be conducted during normal working hours, coordinated through Scott Schultz, Water Utilities Director, at (904) 297-7500. The contract will be awarded to the responsible bidder submitting the lowest responsive bid based on unit price comparisons. The work shall be substantially completed within 300 calendar days of contract commencement and fully completed within 330 calendar days.
Bidders must be licensed by the Florida Construction Industry Licensing Board and have completed a minimum of five similar projects within the past five years, each with a contract value of at least $500,000, with at least one project exceeding $1,500,000. Bid security equal to 5 percent of the maximum bid price (base bid plus alternates) is required in the form of a bid bond. The contract price is based on unit price bidding for all work items with estimated quantities provided; final payment will be based on actual quantities. Progress payments will be made monthly at 95 percent of completed work value with 5 percent retainage until substantial completion. Liquidated damages are set at $1,000 per day for delays beyond the substantial completion date and $500 per day for delays beyond final completion. The project is subject to federal Davis-Bacon labor standards, American Iron and Steel requirements, and Build America, Buy America (BABA) requirements. A base bid and one alternate (Alternate 1 – HDPE Force Main) are included with different pipe material specifications. Bidders must submit subcontractor and supplier lists within five days of bid opening, and the City reserves the right to reject any or all bids and waive minor informalities not involving price, time, or changes to the work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida License No. 3215
Project Manual DEP SRF Pine Avenue Force Main Extension DEP SRF Agreement No. WW100450 City of Green Cove Springs, Florida Project No. M890534.003 Client No. 8905-34-3 July 2026
Prepared by:
BID SET
Florida License No. 3215
PROJECT MANUAL
FOR
DEP SRF PINE AVENUE FORCE MAIN EXTENSION
DEP SRF AGREEMENT NO. WW100450
CITY OF GREEN COVE SPRINGS, FLORIDA
Orange Park, Florida Project No. M890534.003
Client No. 8905-34-3 July 2026
DEP SRF PINE AVENUE FORCE MAIN EXTENSION
TABLE OF CONTENTS
DIVISION 0 - BIDDING AND CONTRACT REQUIREMENTS
00111 Advertisement for Bids
00200 Instructions to Bidders
00410 Bid Form
00430 Bid Bond
00510 Notice of Award
00520 Standard Form of Agreement
00610 Performance Bond
00615 Payment Bond
00620 Contractor's Application for Payment
00640 Final Affidavit and Waiver and Release of Lien (Prime Contractor)
00641 Final Waiver and Release of Lien
00645 Final Waiver and Release of Lien and Right to Claim Against the Payment Bond (Subcontractor) Final Payment
00650 Consent of Surety Company to Final Payment
00700 General Conditions
00800 Supplementary Conditions
00814 Sworn Statement Under Section 287.133(3)(a), Florida Statutes, on Public Entity Crimes
00820 FDEP SRF Supplementary Conditions (Construction Procurement), with Davis-Bacon Wage Decision and EPA OIG Poster
00900 Addenda and Modifications
8905-34-3 Table of Contentsi
DIVISION 1 - GENERAL REQUIREMENTS
01000 Abbreviations
01010 Summary of Work
01020 Contract Modification Procedures
01030 Progress Payment Procedures
01031 Project Meetings
01035 Confined Space Entry Plan
01060 Regulatory Requirements
01150 Measurement and Payment
01300 Submittals
01301 Administrative Requirements
01390 Audiovisual Documentation
01400 Quality Control
01452 Testing Services Furnished by Contractor
01500 Construction Facilities
01570 Temporary Traffic Control
01700 Project Closeout
01710 Field Engineering
01720 Protection of Work and Property
01730 Operation and Maintenance Manuals
01781 Warranties and Bonds
DIVISION 2 - SITE WORK
02020 Underground Facilities
02115 Landscape and Tree Protection
8905-34-3 Table of Contentsii
02210 Soil Borings
02220 Demolition
02230 Site Clearing, Stripping, and Grubbing
02240 Dewatering
02300 Earthwork
02310 Finish Grading
02370 Erosion and Sedimentation Control
02441 Directional Drill
02511 Insertion Valves and Equipment
02530 Pipe Work - Gravity Sewer
02536 Precast Polymer Concrete Manholes
02539 Pipe Work - Force Mains
02750 Concrete Paving, Sidewalk, and Curb
02920 Grassing
02960 Asphaltic Pavement and Concrete Replacement
02963 Temporary Bypass Pumping Systems
DIVISION 3 - CONCRETE
Not Applicable
DIVISION 4 - MASONRY
DIVISION 5 - METALS
8905-34-3 Table of Contentsiii
DIVISION 6 - WOOD AND PLASTICS
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
Not Applicable
DIVISION 8 - DOORS AND WINDOWS
Not Applicable
DIVISION 9 - FINISHES
DIVISION 10 - SPECIALTIES
DIVISION 11 - EQUIPMENT
Not Applicable
DIVISION 12 - FURNISHINGS
Not Applicable
DIVISION 13 - SPECIAL CONSTRUCTION
DIVISION 14 - CONVEYING SYSTEMS
8905-34-3 Table of Contentsiv
DIVISION 15 - MECHANICAL
DIVISION 16 - ELECTRICAL
8905-34-3 Table of Contentsv
Modified per CPH Consulting, LLC EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-1 Instructions to Bidders
SECTION 00200
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1 — Defined Terms
Article 2— Bidding Documents
Article 3 — Qualifications of Bidders
Article 4 — Pre-Bid Conference
Article 5 — Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 6 — Bidder’s Representations and Certifications
Article 7 — Interpretations and Addenda
Article 8 — Bid Security
Article 9 — Contract Times
Article 10 — Substitute and “Or Equal” Items
Article 11 — Subcontractors, Suppliers, and Others
Article 12 — Preparation of Bid
Article 13 — Basis of Bid
Article 14 — Submittal of Bid
Article 15 — Modification and Withdrawal of Bid
Article 16 — Opening of Bids
Article 17 — Bids to Remain Subject to Acceptance
Article 18 — Evaluation of Bids and Award of Contract
Article 19 — Bonds and Insurance
Article 20 — Signing of Agreement
Article 21 — Sales and Use Taxes
Article 22 — Contracts to Be Assigned
Article 23 — Wage Rates
Article 24 — American Iron and Steel Requirements……………………………………………………………………………. 12
Article 25 — Build America, Buy America Requirements………………………………………………………………………. 12
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-2 Instructions to Bidders
ARTICLE 1—DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office—The office from which the Bidding Documents are to be issued and which registers plan holders.
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Engineer has established a Bidding Documents Website as indicated in the Advertisement for Bids.
Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by (Engineer) (Owner).
2.04 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents, or make them available for examination.
Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.
2.05 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe Portable Document Format (.pdf). It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-3 Instructions to Bidders
Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.
C. After the Contract is awarded, the Owner will provide or direct the Engineer to provide for the use of the Contractor documents that were developed by Engineer as part of the Project design process, as Electronic Documents in native file formats.
1. Electronic Documents that are available in native file format include:
a. CAD files.
2. Release of such documents will be solely for the convenience of the Contractor. No such document is a Contract Document.
3. Unless the Contract Documents explicitly identify that such information will be available to the Successful Bidder (Contractor), nothing herein will create an obligation on the part of the Owner or Engineer to provide or create such information, and the Contractor is not entitled to rely on the availability of such information in the preparation of its Bid or pricing of the Work. In all cases, the Contractor shall take appropriate measures to verify that any electronic/digital information provided in Electronic Documents is appropriate and adequate for the Contractor’s specific purposes.
4. In no case will the Contractor be entitled to additional compensation or time for completion due to any differences between the actual Contract Documents and any related document in native file format.
ARTICLE 3—QUALIFICATIONS OF BIDDERS
3.01 To be considered qualified, bidder shall be licensed to engage in the business of contracting in the State of Florida by the Construction Industry Licensing Board. Additionally, a qualified bidder shall have successfully completed as prime contractor, a minimum of 5 projects of a similar nature within the past 5 years, each having a minimum contract value of $500,000, with at least one project having a contract value in excess of $1,500,000. To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within five (5) days of Owner’s request, Bidder must submit the following information:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. Evidence that Bidder is authorized to do business in the state where the Project is located.
C. Bidder’s State of Florida contractor license number.
D. Subcontractor and Supplier qualification information.
E. List of similar projects completed within the most recent five (5) years. Provide brief description of project, date completed, original contract amount, final contract amount, contact names and phone numbers of Owners and Engineers.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-4 Instructions to Bidders
F. List of currently active projects with project description, contract amount, percent complete, contact names and phone numbers of Owners and Engineers.
G. Other required information regarding qualifications.
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A non-mandatory pre-bid conference will be held at the time and location indicated in the Advertisement for Bids. Representatives of Owner and Engineer will be present to discuss the Project. Engineer will transmit to all prospective bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference.
4.02 Information presented at the pre-bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-bid conference. Information presented and statements made at the pre-bid conference will not be binding or legally effective unless incorporated as an Addendum.
ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
5.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:
a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.
b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-5 Instructions to Bidders
c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
4. Geotechnical Report: The Bidding Documents contain a Geotechnical Report (GR).
a. As set forth in the Supplementary Conditions, the GR describes certain select subsurface conditions that are anticipated to be encountered by Contractor during construction in specified locations. The GR is a Contract Document.
b. The Conditions in the GR are intended to reduce uncertainty and the degree of contingency in submitted Bids. However, Bidders cannot rely solely on the Report Conditions. Bids should be based on a comprehensive approach that includes an independent review and analysis of the GR, all other Contract Documents, Technical Data, other available information, and observable surface conditions.
Not all potential subsurface conditions are represented in the GR.
c. Nothing in the GR is intended to relieve Bidders of the responsibility to make their own determinations regarding construction costs, bidding strategies, and Bid prices, nor of the responsibility to select and be responsible for the means, methods, techniques, sequences, and procedures of construction, and for safety precautions and programs incident thereto.
B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
5.03 Other Site-related Documents
A. In addition to the documents regarding existing Site conditions referred to in Paragraph 5.02.A, the following other documents relating to conditions at or adjacent to the Site are known to Owner and made available to Bidders for reference:
1. None.
Owner will make copies of these other Site-related documents available to any Bidder on request.
B. Owner has not verified the contents of these other Site-related documents, and Bidder may not rely on the accuracy of any data or information in such documents. Bidder is responsible for any interpretation or conclusion Bidder draws from the other Site-related documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-6 Instructions to Bidders
C. The other Site-related documents are not part of the Contract Documents.
D. Bidders are encouraged to review the other Site-related documents, but Bidders will not be held accountable for any data or information in such documents. The requirement to review and take responsibility for documentary Site information is limited to information in (1) the Contract Documents and (2) the Technical Data.
E. No other Site-related documents are available.
5.04 Site Visit and Testing by Bidders
A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.
B. A Site visit is scheduled following the pre-bid conference, if applicable.
C. Bidders visiting the Site are required to arrange their own transportation to the Site.
D. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner contact for visiting the Site: Scott Schultz, Water Utilities Director, (904) 297-7500. Bidder must conduct the required Site visit during normal working hours.
E. Bidder is not required to conduct any subsurface testing or exhaustive investigations of Site conditions.
F. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.
G. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
H. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
5.05 Owner’s Safety Program – Not Applicable
5.06 Other Work at the Site – Not Applicable
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-7 Instructions to Bidders review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
ARTICLE 7—INTERPRETATIONS AND ADDENDA
7.01 Owner, on its own initiative, may issue Addenda to clarify, correct, supplement, or change non-technical aspects of the Bidding Documents.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows:
A. Jason R. Shepler, P.E., Jason.Shepler@cphcorp.com
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven (7) days prior to the date for opening of Bids may not be answered.
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.
ARTICLE 8—BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5% of Bidder’s maximum Bid price (determined by adding the base bid and all additive alternates) and in the form of a Bid Bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid Bond will be issued in the form included in the Bidding Documents.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 business days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum Bid Bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-8 Instructions to Bidders
ARTICLE 9—CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.
9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for all major component and construction disciplines of the Work within five (5) days after Bid opening.
11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.
Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-9 Instructions to Bidders
ARTICLE 12—PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form must be completed in non-erasable ink and the Bid Form signed in non-erasable ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”
12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½-inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.
12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature). The corporate address and state of incorporation must be shown.
12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature). The official address of the partnership must be shown.
12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person. The state of formation of the firm and the official address of the firm must be shown.
12.06 A Bid by an individual must show the Bidder’s name and official address.
12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.08 All names must be printed in ink below the signatures.
12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located in the form of a valid business license number, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.12 After bid opening, Owner may request evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-10 Instructions to Bidders
12.13 Bidder must be licensed to engage in the business of contracting in the State of Florida by the Construction Industry Licensing Board. Bidder’s state contractor license number must be shown on the Bid Form.
ARTICLE 13—BASIS OF BID
13.01 Unit Price
A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
13.02 Allowances
A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
ARTICLE 14—SUBMITTAL OF BID
14.01 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement for Bids and must be enclosed in a plainly marked package with the Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid must be addressed to the City of Green Cove Springs, Attn: Scott Schultz, 321 Walnut Street, Green Cove Springs, Florida 32043.
14.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.
14.03 Bids may not be submitted electronically.
ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID
15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-11 Instructions to Bidders
15.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.
15.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.
ARTICLE 16—OPENING OF BIDS
16.01 Bids will be opened at the time and place indicated in the Advertisement for Bids and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE
17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.
18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.
18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.
18.05 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.
B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00200-12 Instructions to Bidders
18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 19—BONDS AND INSURANCE
19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing Bid Bonds as part of the bidding process.
ARTICLE 20—SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one (1) fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
ARTICLE 21—SALES AND USE TAXES – NOT APPLICABLE
ARTICLE 22—CONTRACTS TO BE ASSIGNED – NOT APPLICABLE
ARTICLE 23 – WAGE RATES
23.01 Project is subject to Federal Labor Standards Provisions (Davis-Bacon). See Appendix C of Section 00820 “FDEP SRF Supplementary Conditions” and attached Wage Decision.
ARTICLE 24 – AMERICAN IRON AND STEEL REQUIREMENTS
24.01 This project is subject to American Iron and Steel requirements. See Appendix D of Section 00820, “FDEP Supplementary Conditions”.
ARTICLE 25 – BUILD AMERICA, BUY AMERICA REQUIREMENTS
25.01 This project is subject to American Iron and Steel requirements. See Appendix E of Section 00820, “FDEP Supplementary Conditions”.
END OF SECTION
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00410-1 Bid Form
SECTION 00410
BID FORM
DEP SRF PINE AVENUE FORCE MAIN EXTENSION
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.
ARTICLE 1—BIDDER
SUBMITTED BY: DATE:
Company Name (printed or typed)
Address
City, State, Zip
BIDDER’S CONTACT:
Name
PHONE NO.:
FAX NO.:
EMAIL ADDRESS:
CONTRACTOR’S FLORIDA LICENSE NO.:
ARTICLE 2—OWNER
2.01 This Bid is submitted to:
City of Green Cove Springs 321 Walnut Street Green Cove Springs, Florida 32043
2.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00410-2 Bid Form
ARTICLE 3—ATTACHMENTS TO THIS BID
3.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid security;
B. If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign;
ARTICLE 4—BASIS OF BID—LUMP SUM BID AND UNIT PRICES
4.01 Unit Price Bids
A. Bidder will perform the following Work at the indicated unit prices:
Item Description Est.
Qty Unit
Unit Price Amount
1 Mobilization/Demobilization (< 5%) 1 LS $ $
2 General Conditions 1 LS $ $
3 PVC Force Main (Open Cut) a 12-inch 120 LF $ $ b 16-inch 2,890 LF $ $
4 Directionally Drilled Mains – FPVC a 12-inch (DR 18) 270 LF $ $ b 16-inch (DR 18) 7,130 LF $ $
5 Ductile Iron Fittings 20,500 LBS $ $
6 Gate Valve and Box a 12-inch 2 EA $ $ b 16-inch 8 EA $ $
7 Connection to Existing Main a Coupling, Fitting, Existing Valve, etc. 2 EA $ $ b 12" Tapping Sleeve and Valve 2 EA $ $
8 Air Release Valves a 2" Automatic ARV Assembly 16 EA $ $
9 Locate Wire Boxes 13 EA $ $
10 InsertValves a 12" Ductile Iron Resilient Wedge 2 EA $ $
11 Removal and Replacement of Unsuitable Soils 500 CY $ $
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00410-3 Bid Form
Item Description Est.
Qty Unit
Unit Price Amount
12 Concrete Encasement and Specials 150 CY $ $
13 Removal & Replacement of:
a Full-depth Asphalt Pavement (1.5” Asphalt/8” Limerock/12” Subgrade) 2,900 SY $ $ b Stabilized Driveway 410 SY $ $ c Concrete Driveway 250 SY $ $ d Asphalt Mill and Overlay (1”) 3,000 SY $ $ e Concrete Curb & Gutter 100 LF $ $
14 Audiovisual Documentation 1 LS $ $
15 Grassing a Sodding 3,000 SY $ $
16 Utility Locating & Coordination 1 LS $ $
17 Pump Station 2 Collection System Improvements 1 LS $ $
18 SWWTF Decommissioning Allowance 1 LS $100,000 $100,000
BASE BID TOTAL $
ALTERNATE 1 – HDPE FORCE MAIN
4 Directionally Drilled Mains – HDPE a 14-inch (DR 11) 270 LF $ $ b 18-inch (DR 11) 7,130 LF $ $
5 DI Fittings 23,500 LBS $ $
The City will review and utilize the above line-item pricing at their sole discretion. The above pricing would replace the denoted Base Bid line item pricing.
A. Bidder acknowledges that:
1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and
2. estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.
ARTICLE 7—TIME OF COMPLETION
7.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
7.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00410-4 Bid Form
ARTICLE 8—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF
ADDENDA
8.01 Bid Acceptance Period
A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
8.02 Instructions to Bidders
A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.
8.03 Receipt of Addenda
A. Bidder hereby acknowledges receipt of the following Addenda:
Addendum Number Addendum Date
ARTICLE 9—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
9.01 Bidder’s Representations
A. In submitting this Bid, Bidder represents the following:
1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.
2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.
5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and
(c) Bidder’s (Contractor’s) safety precautions and programs.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00410-5 Bid Form
7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.
8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
12. Bidder is licensed to engage in the business of contracting in the State of Florida by the Construction Industry Licensing Board.
9.02 Bidder’s Certifications
A. The Bidder certifies the following:
1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.
2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
3. Bidder has not solicited or induced any individual or entity to refrain from bidding.
4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 7.02.A:
a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.
b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.
c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.
d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8905-34-3 00410-6 Bid Form
BIDDER hereby submits this Bid as set forth above:
Bidder:
(typed or printed name of organization)
By: Attest:
(individual’s signature) (individual’s signature)
Name: Name:
(typed or printed) (typed or printed)
Title: Title:
Date: Date:
Address for giving notices:
Bidder’s Business License No. _____________________________________________________________
Affix corporate seal, if applicable.
EJCDC® C-430, Bid Bond (Penal Sum Form).
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 8905-34-3 00430-1 Bid Bond
SECTION 00430
BID BOND (PENAL SUM FORM)
Bidder Surety
Address (principal place of business): Address (principal place of business):
Owner Bid
Name: City of Green Cove Springs, Florida Project (name and location):
Address (principal place of business): DEP SRF Pine Avenue Force Main Extension DEP SRF Agreement No.