BID Schedule of Prices CLINS.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
Saylorville Lake Mowing Federal contract opportunity
Solicitation number
W912EK25QA001
Issued by
Department of the Army Corps of Engineers Engineering District Rock Island

About this file

This is a bid schedule pricing template for mowing and trimming services at Saylorville Lake Project in Iowa, covering a base period (March-December 2025) and four option periods through December 2029. The work involves mowing and trimming at three campground locations: Bob Shetler (8 acres), Cherry Glen (12 acres), and Prairie Flower (45 acres), totaling 65 acres per round.

The contractor must complete 17 rounds of mowing and trimming during each period, with work to be performed weekly within a 5-day timeframe. Pricing is structured per acre for mowing and per area for trimming, with separate line items for each campground. The contractor must provide all labor, materials, equipment, and supplies for both mowing and trimming services. Each option period maintains the same scope and frequency requirements as the base period, with pricing to be provided for each period separately.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BID SCHEDULE

BASE CONTRACT PERIOD: 1 MARCH 2025 OR CONTRACT AWARD - 1 DECEMBER 2025
ITEM NOSERVICES#UNITPRICE/ACREPRICE PER ROUND*17 ROUND TOTAL**
001AABOB SHETLER CAMPGROUND MOWING8Acres$ - 0$ - 0
001ABCHERRY GLEN CAMPGROUND MOWING12Acres$ - 0$ - 0
001ACPRAIRIE FLOWER CAMPGROUND MOWING45Acres$ - 0$ - 0
TOTAL MOWING, BASE PERIOD$ - 0
MOWING: Provide all labor, materials, equipment, and supplies as specified to perform mowing at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
001BABOB SHETLER CAMPGROUND TRIMMING1Area$ - 0$ - 0
001BBCHERRY GLEN CAMPGROUND TRIMMING1Area$ - 0$ - 0A single mowing round consists of 65 acres of improved grounds mowing and trimming of three areas (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground) completed during the weekly timeframe. * - Price per round is the cost to complete one round of mowing or trimming. Mowing and trimming are separate costs for this contract. Mowing is priced per acre and trimming is priced per area. See Technical Exhibit #1 for Maps of each area. ** - 17 round total is the cost to complete 17 rounds of mowing
001BCPRAIRIE FLOWER CAMPGROUND TRIMMING1Area$ - 0$ - 0
TOTAL TRIMMING, BASE PERIOD$ - 0
TRIMMING: Provide all labor, materials, equipment, and supplies as specified to perform trimming at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
A single mowing round consists of 65 acres of improved grounds mowing and trimming of three areas (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground) completed during the weekly timeframe (5 Days).
* - Price per round is the cost to complete one round of mowing or trimming. Mowing and trimming are separate costs for this contract. Mowing is priced per acre and trimming is priced per area. See Technical Exhibit #1 for Maps of each area.
** - 17 round total is the cost to complete 17 rounds of mowing or trimming for a given area (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground). For mowing, multiply the price per round by 17 to get the 17 round total. Trimming price per area and price per round will be equal. For trimming, multiply the price per round by 17 to get the 17 round total.
TOTAL FOR ITEM NO'S. 001AA THRU 001BC:$ - 0
OPTION PERIOD 1: 1 MARCH 2026 - 1 DECEMBER 2026
ITEM NOSERVICES#UNITPRICE/ACREPRICE PER ROUND*17 ROUND TOTAL**
002AABOB SHETLER CAMPGROUND MOWING8Acres$ - 0$ - 0
002ABCHERRY GLEN CAMPGROUND MOWING12Acres$ - 0$ - 0
002ACPRAIRIE FLOWER CAMPGROUND MOWING45Acres$ - 0$ - 0
TOTAL MOWING, OPTION PERIOD 1$ - 0
MOWING: Provide all labor, materials, equipment, and supplies as specified to perform mowing at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
002BABOB SHETLER CAMPGROUND TRIMMING1Area$ - 0$ - 0
002BBCHERRY GLEN CAMPGROUND TRIMMING1Area$ - 0$ - 0
002BCPRAIRIE FLOWER CAMPGROUND TRIMMING1Area$ - 0$ - 0
TOTAL TRIMMING, OPTION PERIOD 1$ - 0
TRIMMING: Provide all labor, materials, equipment, and supplies as specified to perform trimming at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
A single mowing round consists of 65 acres of improved grounds mowing and trimming of three areas (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground) completed during the weekly timeframe (5 Days).
* - Price per round is the cost to complete one round of mowing or trimming. Mowing and trimming are separate costs for this contract. Mowing is priced per acre and trimming is priced per area. See Technical Exhibit #1 for Maps of each area.
** - 17 round total is the cost to complete 17 rounds of mowing or trimming for a given area (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground). For mowing, multiply the price per round by 17 to get the 17 round total. Trimming price per area and price per round will be equal. For trimming, multiply the price per round by 17 to get the 17 round total.
TOTAL FOR ITEM NO'S. 002AA THRU 002BC:$ - 0
OPTION PERIOD 2: 1 MARCH 2027 - 1 DECEMBER 2027
ITEM NOSERVICES#UNITPRICE/ACREPRICE PER ROUND*17 ROUND TOTAL**
003AABOB SHETLER CAMPGROUND MOWING8Acres$ - 0$ - 0
003ABCHERRY GLEN CAMPGROUND MOWING12Acres$ - 0$ - 0
003ACPRAIRIE FLOWER CAMPGROUND MOWING45Acres$ - 0$ - 0
TOTAL MOWING, OPTION PERIOD 2$ - 0
MOWING: Provide all labor, materials, equipment, and supplies as specified to perform mowing at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
003BABOB SHETLER CAMPGROUND TRIMMING1Area$ - 0$ - 0
003BBCHERRY GLEN CAMPGROUND TRIMMING1Area$ - 0$ - 0
003BCPRAIRIE FLOWER CAMPGROUND TRIMMING1Area$ - 0$ - 0
TOTAL TRIMMING, OPTION PERIOD 2$ - 0
TRIMMING: Provide all labor, materials, equipment, and supplies as specified to perform trimming at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
A single mowing round consists of 65 acres of improved grounds mowing and trimming of three areas (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground) completed during the weekly timeframe (5 Days).
* - Price per round is the cost to complete one round of mowing or trimming. Mowing and trimming are separate costs for this contract. Mowing is priced per acre and trimming is priced per area. See Technical Exhibit #1 for Maps of each area.
** - 17 round total is the cost to complete 17 rounds of mowing or trimming for a given area (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground). For mowing, multiply the price per round by 17 to get the 17 round total. Trimming price per area and price per round will be equal. For trimming, multiply the price per round by 17 to get the 17 round total.
TOTAL FOR ITEM NO'S. 003AA THRU 003BC:$ - 0
OPTION PERIOD 3: 1 MARCH 2028 - 1 DECEMBER 2028
ITEM NOSERVICES#UNITPRICE/ACREPRICE PER ROUND*17 ROUND TOTAL**
004AABOB SHETLER CAMPGROUND MOWING8Acres$ - 0$ - 0
004ABCHERRY GLEN CAMPGROUND MOWING12Acres$ - 0$ - 0
004ACPRAIRIE FLOWER CAMPGROUND MOWING45Acres$ - 0$ - 0
TOTAL MOWING, OPTION PERIOD 3$ - 0
MOWING: Provide all labor, materials, equipment, and supplies as specified to perform mowing at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
004BABOB SHETLER CAMPGROUND TRIMMING1Area$ - 0$ - 0
004BBCHERRY GLEN CAMPGROUND TRIMMING1Area$ - 0$ - 0
004BCPRAIRIE FLOWER CAMPGROUND TRIMMING1Area$ - 0$ - 0
TOTAL TRIMMING, OPTION PERIOD 3$ - 0
TRIMMING: Provide all labor, materials, equipment, and supplies as specified to perform trimming at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
A single mowing round consists of 65 acres of improved grounds mowing and trimming of three areas (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground) completed during the weekly timeframe (5 Days).
* - Price per round is the cost to complete one round of mowing or trimming. Mowing and trimming are separate costs for this contract. Mowing is priced per acre and trimming is priced per area. See Technical Exhibit #1 for Maps of each area.
** - 17 round total is the cost to complete 17 rounds of mowing or trimming for a given area (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground). For mowing, multiply the price per round by 17 to get the 17 round total. Trimming price per area and price per round will be equal. For trimming, multiply the price per round by 17 to get the 17 round total.
TOTAL FOR ITEM NO'S. 004AA THRU 004BC:$ - 0
OPTION PERIOD 4: 1 MARCH 2029 - 1 DECEMBER 2029
ITEM NOSERVICES#UNITPRICE/ACREPRICE PER ROUND*17 ROUND TOTAL**
005AABOB SHETLER CAMPGROUND MOWING8Acres$ - 0$ - 0
005ABCHERRY GLEN CAMPGROUND MOWING12Acres$ - 0$ - 0
005ACPRAIRIE FLOWER CAMPGROUND MOWING45Acres$ - 0$ - 0
TOTAL MOWING, OPTION PERIOD 4$ - 0
MOWING: Provide all labor, materials, equipment, and supplies as specified to perform mowing at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
005BABOB SHETLER CAMPGROUND TRIMMING1Area$ - 0$ - 0
005BBCHERRY GLEN CAMPGROUND TRIMMING1Area$ - 0$ - 0
005BCPRAIRIE FLOWER CAMPGROUND TRIMMING1Area$ - 0$ - 0
TOTAL TRIMMING, OPTION PERIOD 4$ - 0
TRIMMING: Provide all labor, materials, equipment, and supplies as specified to perform trimming at above campground locations, Saylorville Lake Project, Iowa, in Iowa in accordance with the statement of work and other attachments.
A single mowing round consists of 65 acres of improved grounds mowing and trimming of three areas (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground) completed during the weekly timeframe (5 Days).
* - Price per round is the cost to complete one round of mowing or trimming. Mowing and trimming are separate costs for this contract. Mowing is priced per acre and trimming is priced per area. See Technical Exhibit #1 for Maps of each area.
** - 17 round total is the cost to complete 17 rounds of mowing or trimming for a given area (Bob Shetler Campground, Cherry Glen Campground, Prairie Flower Campground). For mowing, multiply the price per round by 17 to get the 17 round total. Trimming price per area and price per round will be equal. For trimming, multiply the price per round by 17 to get the 17 round total.
TOTAL FOR ITEM NO'S. 005AA THRU 005BC:$ - 0
TOTAL FOR ITEM NO'S. 001AA THRU 005BC:$ - 0

File details come from the government source that posted it. Updated .