This document is a series of questions and answers related to a Request for Information (RFI) for a modular classroom project in Sumter County, Georgia. The project involves the construction of a modular complex with approximately five units that will serve as a middle-high school facility. The RFI covers various design and technical specifications, including the need for aluminum ramps and stairs, gutters and downspouts, suspended ceilings, fire sprinkler systems, and HVAC dehumidification. The RFI also clarifies that the customer will not provide a rough sketch of the site location, and the terms and conditions for the award are not yet available.
Regarding pricing and other commercial terms, the document indicates that the customer will select the color for the front entrance after the award, and the bidder will be responsible for completing the final connections for the fire sprinkler system on-site. The RFI also confirms that the customer will not provide the low-voltage systems, such as data, fire alarm, and PA systems.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI’s for the Southwest Georgia STEM Modular Classroom Bid
1. Can we get a google map view (rough sketch) showing approximate location of new modular classroom? SGSC will not be providing a rough sketch. A site visit is required.
2. Is it possible to see a copy of the contract and/or T&Cs that would govern an award?
SGSC does not have the terms and conditions available at this time.
3. Will any stormwater management be required from the state or local approving authorituies? No
4. Are any canopies needed on doors at end of hallway? Yes
5. Are Aluminum ramps and stairs are suitable? Yes. Our bid asks for aluminum.
a. Do the posts of those need to be on footings or can they rest on abs pads or solid block? The posts can rest on on abs pads or solid block.
6. Are gutters and downspouts and splash blocks on grade required? Yes. Front and rear.
Do not need one on the front canopy.
7. All modules in the building are to 13’ 8” wide, correct? Yes
8. Can we option a suspended ceiling in the hallway for ease of wiring on site above in the cavity for fire alarm, sprinkler crossovers and data/voice? Yes.
9. Is the water for the fire sprinkler system going to be under the separate utility invitation for bid.
10. We will furnish a fire sprinkler roughed in from the modular factory, will the customer make the mate line and all final connections on site? No. This must be completed by the Bidder's crew.
11. Concerning the front entrance design, should we include powder coating in our price?
a. Customer will pick color after award. The aluminum or like product will need to be colored.
Yes.
12. On the front entrance, should we assume a total of 5 modular units wide as shown on the customer design? Yes. We would like it as similar of the bid photo as possible,
13. Is dehumidification required for the HVAC units? Yes
14. Your questions and answers mention kindergarten through 12th grade. Should we assume standard plumbing fixtures in the restrooms? Yes. We are a K-12 campus but this building will be a middle-high facility.
15. Is the customer providing all the low voltage systems (data, fire alarm, PA, etc....)?