BID RFI Q_A _2.pdf

PDF 637 KB Posted

Attached to
Modular Complex Bid
Solicitation number
PE-55185-NONST-2024-000000001
Issued by
Schley County, Georgia

About this file

This document is a bid request for information (RFI) related to the construction of a modular complex for the Southwest Georgia STEM Charter School in Sumter County, Georgia. The RFI outlines several key requirements, including the need for a sprinkler system, fire-rated walls and doors, a T-grid ceiling system, three-phase electrical panels and HVAC, and an expansion tank for the hot water heater. The RFI also addresses the requirement for a bid bond and clarifies that a full-time project manager is not required on-site, but the contractor must be available as needed. Additionally, the RFI notes that a new building floor plan is being provided as an attachment.

The RFI does not provide details on pricing terms, set-asides, incumbents, funding requirements and sources, or contract renewal options. However, it is clear that this is a state and local contract opportunity in Georgia, specifically for the construction of a modular complex for the Southwest Georgia STEM Charter School in Sumter County.

View the file

Other files

File Type Posted
Mod Complex Materials.pdf PDF
Bid RFI Q_A.pdf PDF
Mod Complex layout__ Clearer.pdf PDF
Classrooms_18_classroom Model.pdf PDF
BID RFI _4.pdf PDF
Mod Bid Bidders _ Google Docs.pdf PDF
Modular Complex Entrance Design Bid.pdf PDF
Modular _ Questions and Answers.pdf PDF
Modular _ Request for Sealed Bids (1).pdf PDF
April 24 Board Meeting Minutes.pdf PDF
BID RFI _3.pdf PDF
Modular Bidder List.pdf PDF
Modular Complex layout.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Southwest Georgia Stem Charter School Bid Questions

1. Are you aware that a sprinkler system is required by GA Building Code as well as the State Fire Marshall? With the sprinkler system you’re not required to have fire rated walls and doors. I have been informed that the janitor closet must be fire rated.

2. Specifications call for a hard ceiling. The best ceiling to use for a sprinkler system would be T’Grid. Bidders may list an option for a T-Grid hallway.

3. With this being a large building, the electrical panel boxes need to be three phase with the HVAC wired for 208. This will allow the service to be three phase and allow you to diversify your total load which will be less expensive for the new service.

4. By code, the hot water heater will require an expansion tank.

5. Is a bid Bond Required? Yes, please see bid documentation.

6. Do you require a project manager employed by the General Contractor to be onsite at all times? An project manager is not required. However, SGSC will need to be able to contact the General Contractor as needed.

7. The Building Floor plan with the office center protruding out 3’ does not match the picture included in the package. It looks like it should be 6 sections. Should we go with the floor plan or picture? A new layout is being added to the bid. Please see the new attachment.

File details come from the government source that posted it. Updated .