This is Addendum No. 2 to a sealed bid solicitation issued by the Town of Simsbury, Connecticut, in conjunction with the Connecticut Department of Transportation for Bid No. E26-01, State Project No. 0128-0158, the Curtiss Park Connection Multi-Use Trail project. The project involves construction of approximately 3,000 linear feet of bituminous concrete multi-use trail along the north side of Tariffville Road, extending over an existing sidewalk on the Tariffville Road bridge crossing the Farmington River to Curtiss/Pattison Parks, with an additional boardwalk section to be constructed within and adjacent to wetlands in the Farmington River riparian corridor. Addendum No. 2 extends the bid due date and bid opening date to November 24, 2026, at 2:00 p.m., held at Town Hall, 933 Hopmeadow Street, Simsbury, Connecticut. A non-mandatory pre-bid site visit will be conducted virtually via Microsoft Teams on October 27, 2026, at 10:00 a.m.; interested parties must contact Daniel Gannon at dgannon@simsbury-ct.gov by 7:00 p.m. on October 26, 2026, to obtain the meeting link. The contract is scheduled for execution on December 8, 2026, with work commencement on April 1, 2027, substantial completion by October 28, 2027, and final completion by November 5, 2027. The Town will award the contract to the lowest responsive and responsible bidder in accordance with applicable Connecticut Department of Transportation, Federal, State, and Municipal requirements.
The project is funded through the Transportation Alternatives Program (TAP) administered by the Connecticut Department of Transportation. The Disadvantaged Business Enterprise (DBE) participation goal for this contract has been established at zero percent (0%). Addendum No. 2 specifies that questions concerning the bid process and procedures will no longer be accepted. Bidders must submit all required bid surety, performance and payment bonds, insurance, labor documentation, DBE documentation, certifications, and other required forms as specified in the official Bid Documents. All contractors and subcontractors must comply with applicable Federal, State, and Municipal laws, regulations, labor requirements, nondiscrimination requirements, prevailing wage requirements, and Connecticut Department of Transportation requirements. Bid documents are available on the Town of Simsbury website at https://ct-simsbury.civicplus.com/Bids.aspx?CatID=17. The Town reserves the right to reject any or all bids in part or in whole and to waive minor informalities or technical defects when permitted by applicable law.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF PUBLIC WORKS
Bid No. 26-01 Curtiss Park Trail State Project #0128-0158
Addendum No. 2 Federal Aid Project #0315(001)
November 13, 2026 Page 1
Addendum No. 1
DATE: November 13, 2026
RE: Bid No. E26-01
State Project No. 128-158
Federal Aid Project #0315(001)
Curtiss Park Multi-Use Trail
Simsbury, Connecticut
The following information is hereby made to the contract drawings and specifications for State
Project 128-158 Curtiss Park Multi-Use Trail, Federal Aid Project No. 0315(001) dated October
2026. This Addendum No. 2 includes revisions to the bid solicitation for the above-referenced project:
1. The bid due date and bid opening date are hereby extended to November 24, 2026 at
2:00 p.m. The Sealed Bid Notice is replaced in its entirety, Page 1 of the Table of
Contents and Page 3 of the Instruction to Bidders have been revised and are included in this addendum.
2. Section 9 of the Instruction to Bidders has been replaced in its entirety to state that questions concerning the bid process and procedures will no longer be accepted. Page 6 of the Instruction to Bidders has been revised and is included in this addendum.
THIS ENDS ADDENDUM NO. 2
Bid No. E26-01
State Project #0128-0158
Federal Aid Project #0315(001)
Addendum No. 2
INVITATION TO BID
SEALED BID NOTICE
The Town of Simsbury is seeking sealed bids from qualified construction contractors to provide construction services for Bid No. E26-01 – State Project No. 128-158 Curtiss Park Trail, Federal
Aid Project No. 0315 (001). The project is funded through the Transportation Alternatives Program which is administered by the Connecticut Department of Transportation.
The project will include the construction of approximately 3,000 linear feet bituminous concrete multi-use trail which will run along the north side of Tariffville Road, over an existing sidewalk on the
Tariffville Road bridge crossing the Farmington River, to Curtiss/Pattison Parks. A boardwalk section will be constructed within and adjacent to wetlands within the Farmington River riparian corridor.
Bids will be received physically by the Director of Finance, 933 Hopmeadow Street, Simsbury, CT until the time and date listed below after which time they will be publicly opened and read aloud. Bids received after the stated date and time will not be considered. No fax or email submissions will be accepted.
Date of Bid Opening: November 24, 2026 at 2:00 PM, at Town Hall, 933 Hopmeadow Street, Simsbury, CT 06070.
Documents can be obtained from the Town of Simsbury website at:
https://ct-simsbury.civicplus.com/Bids.aspx?CatID=17
A non-mandatory Pre-Bid Site Visit will be held virtually via Microsoft Teams meeting on Tuesday, October 27, 2026, at 10:00 a.m. local time. Anyone interested in attending the meeting shall reach out to
Daniel Gannon via email at dgannon@simsbury-ct.gov to obtain a link to attend the meeting. This request to attend the meeting shall be made no later than 7:00 p.m. local time on Monday, October 26, 2026.
Bidders must demonstrate that they are qualified, properly licensed, adequately staffed, equipped, and experienced to successfully complete the work described in the official Bid Documents.
The Town will award the contract in accordance with the requirements of the official Bid Documents to the lowest responsive and responsible bidder, subject to all applicable Connecticut Department of
Transportation, Federal, State, and Municipal requirements.
The contractor and all subcontractors shall comply with all applicable Federal, State, and Municipal laws, regulations, labor requirements, nondiscrimination requirements, prevailing wage requirements, and Connecticut Department of Transportation requirements applicable to the project.
The bidder shall comply with all applicable Disadvantaged Business Enterprise (DBE) requirements established by the Connecticut Department of Transportation and Federal Highway Administration. The
DBE participation goal for this contract is zero percent (0%).
All required bid surety, performance and payment bonds, insurance, labor documentation, DBE documentation, certifications, and other required forms shall be submitted in the manner and within the time periods specified in the official Bid Documents.
Federal Aid Project #0315(001)
Addendum No. 2
The Town of Simsbury reserves the right to reject any or all bids in part or in whole, to waive minor informalities or technical defects when permitted by applicable law and the official Bid Documents, or to accept any bid if it is determined to be in the best interest of the Town of Simsbury.
Amy Meriwether, Director of Finance
Town of Simsbury
An Equal Opportunity/Affirmative Action Employer
CURTISS PARK CONNECTION MULTI-USE TRAIL TABLE OF CONTENTS
INVITATION TO BID
TOWN OF SIMSBURY
(EQUAL OPPORTUNITY EMPLOYER)
Project: CURTISS PARK CONNECTION MULTI-USE TRAIL
PROJECT NO. E26-01
STATE PROJECT NO. 0128-0158
Sealed bids, endorsed "Curtiss Park Connection Multi-Use Trail" will be received at the office of the
Finance Director, 933 Hopmeadow St., Simsbury, Connecticut, until November 24, 2026 at 2:00 PM
(EST) at which time they will be opened in public by the Director of Finance. Bids received after the time set for the opening may be rejected.
The project will include the construction of approximately 3,000 linear feet bituminous concrete multi-use trail which will run along the north side of Tariffville Road, over an existing sidewalk on the Tariffville
Road bridge crossing the Farmington River, to Curtiss/Pattison Parks. A boardwalk section will be constructed within and adjacent to wetlands within the Farmington River riparian corridor.
The project is funded by the Transportation Alternatives Program (TAP). The goal for Disadvantaged
Business Enterprises (DBE) participation in this contract has been established at zero percent (0%). The
Contractor must ensure that employees and applicants for employment are not discriminated against as set forth in the bid documents.
A non-mandatory Pre-Bid Site Visit will be held virtually via Microsoft Teams meeting on Tuesday, October 27, 2026, at 10:00 a.m. local time. Anyone interested in attending the meeting shall reach out to Daniel Gannon via email at dgannon@simsbury-ct.gov to obtain a link to attend the meeting. This request to attend the meeting shall be made no later than 7:00 p.m. local time on Monday, October 26, 2026.
Documents can be obtained from the Town of Simsbury website at:
https://ct-simsbury.civicplus.com/Bids.aspx?CatID=17
The right is reserved to reject any or all bids or to waive defects in same if it be deemed in the best interest of the Town of Simsbury.
The Town of Simsbury is an Affirmative Action/Equal Opportunity Employer. MBE’s, WBE’s and
SBE’s are encouraged to apply.
Amy Meriwether
Director of Finance / Treasurer
CURTISS PARK CONNECTION MULTI-USE TRAIL INSTRUCTION TO BIDDERS
1. INTRODUCTION
The Town of Simsbury (the “Town”) is soliciting bids for Curtiss Park Connection Multi-Use Trail.
This Invitation is not a contract offer.
The scope of this project is described more particularly in the Invitation for Bid that is a part of this bid package.
The location, general characteristics and principal details of the work are indicated on record drawings.
The drawings are the contract drawings, referred to herein as the "Drawings".
The Technical Specifications are contained in this Project Manual and are listed in the Table of
Contents.
Interested parties should submit a bid response in accordance with the requirements and directions set forth in this bid package.
The Town will return, unopened, any bid received after the date and time of bid opening.
If there are any conflicts between the provisions of these Instructions to Bidders and any other document(s) comprising this bid package, these Instructions to Bidders shall prevail.
2. KEY DATES
Invitation to Bid issued: October 15, 2026
Pre-Bid Conference: October 27, 2026 (non-mandatory, Microsoft Teams)
Bid Opening: November 24, 2026 @ 2:00 p.m. (Town Hall)
Notice of Conditional Award: December 1, 2026
Contract Execution: December 8, 2026
Commencement of Work: April 1, 2027
Substantial Completion: October 28, 2027
Final Completion: November 5, 2027
3. PROJECT COMPLETION
The contractor is advised that time is of the essence for this project. The Contractor shall provide a detailed work schedule for approval by the Town prior to execution of the Contract. The work schedule shall be updated weekly for the duration of the construction.
CURTISS PARK CONNECTION MULTI-USE TRAIL INSTRUCTION TO BIDDERS
with liquidated damages or any excess cost when the delay in completion of the Work is due to acts of God and other similar circumstances beyond his control.
9. QUESTIONS
Questions concerning the bid process and procedures will no longer be accepted.
10. ADDENDA
The Town will post an addendum or addenda, which shall be a part of this Invitation and the resulting Contract, containing all questions received as provided for above and decisions regarding same. At least three (3) calendar days prior to the receipt of bids, the Town will post a copy of the addendum at the Town of Simsbury Public Bids and RFPs webpage at the following website:
https://ct-simsbury.civicplus.com/Bids.aspx?CatID=17. Each bidder is responsible for checking the website to determine if the Town has issued an addendum and, if so, to complete its bid in accordance with the Invitation as modified by the addendum.
11. COSTS FOR PREPARING BID
This Invitation does not commit the Town to pay any costs incurred by bidders in preparing their responsive bids. Each bidder agrees that all costs it incurs in developing its bid are its sole responsibility.
12. OWNERSHIP OF BIDS
All bids submitted become property of the Town.