About this file
This is a bid form for the City of Palo Alto Utilities (CPAU) Electric Substation Equipment Painting project, a comprehensive surface preparation and protective coating services solicitation for equipment located within seven electric substations across the City's distribution system. The project encompasses cleaning, surface preparation, corrosion treatment, priming, and application of high-performance protective coatings on transformers, circuit breakers, switchgear, steel structures, bus supports, capacitor houses, control cabinets, and associated components across the Colorado, Hansen Way, Quarry, Park Boulevard, Maybell, Hanover, and Adobe Creek substations, with equipment inventories ranging from 3 to 29 items per location. A non-mandatory pre-bid meeting and site walk is scheduled for April 15, 2026, at 9:00 a.m. at the Colorado Substation; written questions must be submitted by April 17, 2026, at 1:00 p.m.; and electronic bids are due April 24, 2026, at 3:00 p.m. through the City's OpenGov procurement portal. Work is anticipated to commence July 1, 2026, with a completion deadline of 1,095 working days from the Notice to Proceed, and the City reserves the right to award the contract to a single contractor or multiple contractors.
The bid form requires submission of a base bid on a lump-sum basis covering all labor, equipment, materials, transportation, applicable taxes, profit, insurance, bonds, and overhead, with provisions for supplemental unit pricing, additive alternate bids, and deductive alternate bids as specified in the project documents. Bid security requirements include a bid bond of no less than 10 percent of the aggregate bid amount for bids exceeding $25,000, and the selected contractor must provide performance and payment surety bonds each in the amount of 100 percent of the contract sum within 10 business days of the Notice of Award. Based on the engineering estimate, Year 1 painting costs total approximately $940,500 (including $100,000 in mobilization costs), with subsequent annual expenditures ranging from $274,000 to $327,000 over a four-year project timeline. All contractors must be duly licensed as a contractor with the State of California, comply with California prevailing wage requirements under Labor Code Sections 1720 et seq., maintain registration with the California Department of Industrial Relations, and provide evidence of full site inspection and project knowledge, strong technical expertise, and a proven safety record. Liquidated damages are assessed at $500 per day for failure to achieve final completion within the contract time, and the City will retain 10 percent of undisputed amounts on each progress payment, with payment due within thirty days of receipt of properly submitted applications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Electric_Substation_Equipment_Painting_(Addendum_#2_Revision).pdf | ||
| Electric_Substation_Equipment_Painting_(Addendum_#1_Revision).pdf | ||
| Appendix_VII_Maybell.docx | DOCX document | |
| Appendix_VIII_Quarry_Substation.docx | DOCX document | |
| Appendix_X_Hanover_Substation.docx | DOCX document | |
| Appendix_XI_Hansen_Way.docx | DOCX document | |
| Appendix_IX_ParkBlvd.docx | DOCX document | |
| Appendix_V_Colorado_Substation.docx | DOCX document | |
| Bid_Bond_Form.docx | DOCX document | |
| Appendix_VI_Adobe_Creek.docx | DOCX document | |
| Performance_Bond.docx | DOCX document | |
| Payment_Bond.docx | DOCX document | |
| REVISED_Equipment_list_2025_(1).xlsx | XLSX spreadsheet | |
| Substation_Painting_Specs.docx | DOCX document | |
| Equipment_list_2025.xlsx | XLSX spreadsheet | |
| Bid_Form_For_Substation_Equipment_Painting.docx | DOCX document | |
| Construction_Contract,_General_Conditions,_and_Change_Orders.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID FORM
City Council/City Manager Name of Company ______________________________ City of Palo Alto Palo Alto, California
In response to this Invitation For Bids (IFB), the undersigned, as Bidder, declares that the only persons or parties interested in this Bid as principals are those named herein; that this Bid is made without collusion with any other person, firm or corporation; that the Bidder has carefully examined the location of the proposed work and the plans and specifications herein referred to; and that the Bidder proposes and agrees, if this Bid is accepted, to contract with the City of Palo Alto (City), to provide all necessary materials, equipment, tools, apparatus, and other means of transport services, and to do all the Work and comply with all the specified requirements in this IFB, in the manner herein prescribed and for the prices stated in the following Bid:
Project Title: _______________________________________, Invitation for Bids (IFB) Number ______________
Note: All of the approximate quantities provided by City on this Bid Form are estimated amounts for bidding purposes only. Actual quantities may be greater or less than the estimated amount depending on circumstances encountered during construction of the Project, and the resulting Contract Sum will be subject to adjustment for actual quantities pursuant to Section 7.2.9 of the General Conditions.
A. Base Bid: Provide all labor, equipment material, transportation and applicable taxes, profit, insurance, bonds and other overhead to perform the Work in accordance with the Project Plans and Technical Specifications, herein:
| BID ITEM |
| APPROX.QTY. |
| UNIT |
| DESCRIPTION, WITH UNIT PRICE IN WORDS |
(EACH BID ITEM SHALL INCLUDE ALL APPLICABLE TAXES, PROFIT, INSURANCE, BONDS, AND OTHER OVERHEAD)
| UNIT PRICE |
| TOTAL ITEM PRICE |
| 001 |
| 1 |
| Lump Sum |
Base Bid will provide manpower and equipment to perform items as described in scope.
| $ |
| $ |
| N/A |
| N/A |
| N/A |
N/A
| $ |
| $ |
Base Bid Total (item 001)
(Total in words: ______________________________________________________)
B. Supplemental Unit Pricing (SUP): Provide Supplemental Unit Pricing fully inclusive of all labor, equipment, material, transportation and applicable taxes, profit, insurance bonds and other overhead to perform the potential SUP work specified below, which will be a binding unit price only if the City elects to add the SUP work to the Project requirements by Field Order and/or Change Order based on conditions arising following award of the Contract as further specified in the Special Provisions, and in accordance with the Project Plans and Technical Specifications, herein:
| BID ITEM |
| APPROX.QTY. |
| UNIT |
| DESCRIPTION, WITH UNIT PRICE IN WORDS |
(EACH BID ITEM SHALL INCLUDE ALL APPLICABLE TAXES, PROFIT, INSURANCE, BONDS, AND OTHER OVERHEAD)
| UNIT PRICE |
| TOTAL ITEM PRICE |
1.
Supplemental Unit Pricing Total (item 1)
C. Additive Alternate Bid: Provide all labor, equipment material, transportation and applicable taxes, profit, insurance, bonds and other overhead to perform the Work in accordance with the Project Plans and Technical Specifications, herein:
| BID ITEM |
| APPROX.QTY. |
| UNIT |
| DESCRIPTION, WITH UNIT PRICE IN WORDS |
(EACH BID ITEM SHALL INCLUDE ALL APPLICABLE TAXES, PROFIT, INSURANCE, BONDS, AND OTHER OVERHEAD)
| UNIT PRICE |
| TOTAL ITEM PRICE |
Additive Alternate Bid Total (items ______ through ______)
D. Deductive Alternate Bid Total: Provide all labor, equipment material, transportation and applicable taxes, profit, insurance, bonds and other overhead to perform the Work in accordance with the Project Plans and Technical Specifications, herein:
| BID ITEM |
| APPROX.QTY. |
| UNIT |
| DESCRIPTION, WITH UNIT PRICE IN WORDS |
(EACH BID ITEM SHALL INCLUDE ALL APPLICABLE TAXES, PROFIT, INSURANCE, BONDS, AND OTHER OVERHEAD)
| UNIT PRICE |
| TOTAL ITEM PRICE |
Deductive Alternate Bid Total (items ______ through ______)
E. Addenda:
During the Bid process there may be changes to the Contract Documents, which would require an issuance of an addendum or addenda. City disclaims any and all liability for loss, or damage to any Bidder who does not receive any addendum issued by City in connection with this IFB. Any Bidder in submitting a Bid is deemed to waive any and all claims and demands Bidder may have against City on account of the failure of delivery of any such addendum to Bidder. Any and all addenda issued by City shall be deemed included in this IFB, and the provisions and instructions therein contained shall be incorporated to any Bid submitted by Bidder.
To assure that all Bidders have received each addendum, the following acknowledgment and sign-off is required. Failure to acknowledge receipt of an addendum/addenda may be considered an irregularity in the Bid:
| Addendum: | Date Received: | Addendum: | Date Received: | ||||
| #01 | _____________ | #06 | _____________ | ||||
| #02 | _____________ | #07 | _____________ | ||||
| #03 | _____________ | #08 | _____________ | ||||
| #04 | _____________ | #09 | _____________ | ||||
| #05 | _____________ | #10 | _____________ |
Or, □ _____ No Addendum/Addenda Were Received (check and initial).
F. The Bidder represents that it has not retained a person to solicit or secure a City contract (upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee) except for retention of bona fide employee or bona fide established commercial selling agencies for the purpose of securing business.
G. Bidder's Representations and Warranties. The Bidder represents and warrants:
1. That any information submitted by the Bidder prior to the award of Contract, or thereafter, upon request, whether or not submitted under a continuing obligation by the terms of the Contract to do so, is true and correct at the time such information is submitted or made available to the City;
2. That the Bidder has not colluded, conspired, or agreed, directly or indirectly, with any person in regard to the terms and conditions of the Bidder's Bid, except as may be permitted by this Invitation for Bids;
3. That the Bidder has the power and authority to enter into this Contract with the City, that the individual(s) executing this Contract are duly authorized to do so by appropriate resolution (if applicable), and that this Contract shall be executed, delivered and performed pursuant to the power and authority conferred upon the person or persons authorized to bind the Bidder;
4. That the Bidder has not attempted to exert undue influence with the Purchasing Manager, Contract Administrator, Project Manager or any other person who has directly participated in the decision to award the Contract to the Bidder;
5. That the Bidder has furnished and will furnish true and accurate statements, records, reports, resolutions, certifications, and other written information as may be requested of the Bidder by the City during the term of this Contract;
6. That the Bidder and all its subcontractors performing work on this Project are duly licensed as a contractor with the State of California as required by California Business & Professions Code Section 7028, as amended;
7. That the Bidder has fully examined and inspected the Project site and has full knowledge of the physical conditions of the Project site; and,
8. That there are no claims or disputes between the Bidder and the City which would materially affect the Bidder's ability to perform under the Contract.
Bidder’s Designated Contact Person:
| Name: | ______________________________________________________________________ |
| Title: | ______________________________________________________________________ |
| Phone: | ______________________________________________________________________ |
| Fax: | ______________________________________________________________________ |
| Email: | ______________________________________________________________________ |
H. Subcontractor Listing. The Bidder will complete the Subcontractor Listing form included below.
I. Bidder Acknowledgement. By submitting a Bid, the Bidder acknowledges that it has received the Instructions to Bidders and agrees to its terms and to the terms of all other Contract Documents.
Firm: ____________________________________________________________________________
Signature*: ________________________________