About this file

This is a bid form for the Western Destin Dune Vegetation Project, a FEMA-funded initiative by the Board of County Commissioners of Okaloosa County, Florida. The project encompasses the furnishing of labor, materials, equipment, and performance of all operations related to dune vegetation, sand fencing, signage, and post and rope installation. The bid schedule includes four primary work items: dune planting (130,814 estimated units), sand fencing (3,610 linear feet), post and rope installation (458 linear feet), and signage (78 units). A 15 percent contingency is applied to the total project cost. The county reserves the right to adjust the final contract price based on actual quantities installed, with the successful bidder responsible for providing accurate documentation of all work performed.

Bidders must establish unit prices for each work item that, when combined, represent the total price for completing the project in its entirety. Any work items not explicitly listed in the bid schedule must be included under related pay items to reflect the comprehensive cost of project completion. The bid form notes that all estimated quantities are subject to variation, and contractors should account for this variability in their pricing submissions. Funding is provided through FEMA resources allocated for the dune restoration and coastal protection effort in Okaloosa County.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPC

Bid Schedule
Western Destin Dune Vegetation Project
EstimatedTotal
ItemDescriptionUnitQty.Unit PriceCost [$]
1Dune PlantingEA130,814
2Sand FencingLF3,610
3Post and RopeLF458
4SignageEA78
Contingency (+15%)ERROR:#REF!
General Notes:
1. Quantities shown are estimated. Actual quantities may vary. The County reserves the right to adjust the final Contract Price by the actual quantity of planting units, sand fencing, post and rope, and signage installed (+ or -) and it shall be the successful bidder’s responsibility to provide accurate documentation of the actual quantity installed.
2. Bid prices for the various work items are intended to establish a total price for completing the project in its entirety. The Contractor shall include in the Bid, any item for which a separate pay item has not been established in the Bid Schedule (under any related pay item), to reflect the total price for completing the project in its entirety.

&8Page 1 of 1