Bid amendment 1 - B-44973.docx
DOCX document 15 KB Posted
- Attached to
- IDOC - BMR - Guard Tower Door Replacement - JF
- Solicitation number
- 25-426DOC-MUDDY-B-44973
- Issued by
- Illinois
About this file
This document is a bid amendment for Request for Quotation (RFQ) #B-44973 issued by the Illinois Department of Corrections (IDOC) for the procurement of five (5) guard tower exterior doors, five (5) trap doors, and associated hardware for the Big Muddy River Correctional Center. The amendment addresses a vendor's question regarding whether the doors are in exterior walls, and provides a one-day extension for the Chief Engineer to respond. The bid is due on 10/9/24 at 2:00 pm.
The procurement is for the purchase of the doors and hardware only, as the facility's maintenance staff will be responsible for the installation. The contract does not specify any pricing terms, set-asides, incumbents, funding requirements, or other salient information beyond the product specifications and bid timeline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bobacock Davis BFDEP example and Blueprints.pdf | ||
| Existing Guard Tower Exterior Door Dimensions.pdf | ||
| Big Muddy Guard Tower Doors B-44973 BOA~2.docx | DOCX document | |
| Big Muddy Guard Tower Doors B-44973 BOA~1.docx | DOCX document | |
| Standard Terms and Conditions -FACILITY1 - v.23.2~43.pdf | ||
| Bid amendment 1 - B-44973-Revised.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DOC – BMR – Guard Tower Door Replacement Bid #25-426DOC-MUDDY-B-44973 Amendment #1 Response to Vendor’s Questions
Below is the response to the question that IDOC has received regarding the above RFQ:
1. Vendor: Are these in exterior walls? Based on the Exterior Door Dimension Sheet, that’s what I see. This doesn’t match the BFDEP that is attached as an example. Your quick response is much appreciated as it’s almost the end of the day, and it’s due by tomorrow morning-request an extension so we can work on this more accurately.
2. Agency Response: Requesting a one-day extension for Chief Engineer to answer question. Bid to come down 10/9/24 at 2:00pm.