This document is a bid tabulation for the Fischer's Forest Park Rehabilitation Project Bid Schedule, which is a state and local contract opportunity involving Clackamas County and Oregon City. The project includes the decommissioning of an existing treatment system, installation of a new east septic tank, a new recirculating treatment and subsurface drip distribution system, and other miscellaneous site improvements. The bid items cover a range of quantities for various components such as concrete tanks, pipe, UV systems, controls shelter, and subsurface drip distribution system. The original bid estimate for the total construction cost is $800,000.

The bid tabulation provides a detailed breakdown of the unit prices and total costs for each bid item, as well as a comparison of the bids received from three contractors: A-Affordable Septic, Stettler Supply, and JQ Construction. The pricing terms, set asides, and funding requirements are not explicitly stated in the document. The contract term and any renewal options are also not specified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Tab

Fischer's Forest Park Rehab Project
Bid Schedule - Addendum #1
January 18, 2023Engineer EstimateA-Afordable SepticStettler SupplyJQ Construction3 Bid Average2 Bid Average (lowest)
ITEMDESCRIPTIONUNITQUANTITYUNIT PRICESUB TOTALITEM TOTALUNIT PRICESUB TOTALITEM TOTALUNIT PRICESUB TOTALITEM TOTALUNIT PRICESUB TOTALITEM TOTALUNIT PRICESUB TOTALITEM TOTALUNIT PRICESUB TOTALITEM TOTAL
1MobilizationLS1$25,000.00$25,000.00$30,000.00$30,000.00$94,000.00$94,000.00$120,716.00$120,716.00$81,572.00$81,572.00$62,000.00$62,000.00
2Erosion ControlLS1$10,000.00$10,000.00$11,900.00$11,900.00$5,000.00$5,000.00$11,300.00$11,300.00$9,400.00$9,400.00$8,450.00$8,450.00
3By-Pass PumpingLS1$20,000.00$20,000.00$12,500.00$12,500.00$15,000.00$15,000.00$18,000.00$18,000.00$15,166.67$15,166.67$13,750.00$13,750.00
4Decommission Existing East Septic TankLS1$10,000.00$10,000.00$3,600.00$3,600.00$7,500.00$7,500.00$5,420.00$5,420.00$5,506.67$5,506.67$5,550.00$5,550.00
5Effluent Lift Station RetrofitLS1$25,000.00$25,000.00$25,632.00$25,632.00$26,887.51$26,887.51$18,605.00$18,605.00$23,708.17$23,708.17$26,259.76$26,259.76
6Decomission Existing Treatment System
a) Decomission Advantex PodsLS1$6,000.00$6,000.00$9,250.00$9,250.00$9,000.00$9,000.00$7,200.00$7,200.00$8,483.33$8,483.33$9,125.00$9,125.00
b) Remove Existing FenceLS1$6,000.00$6,000.00$4,700.00$4,700.00$2,500.00$2,500.00$2,130.00$2,130.00$3,110.00$3,110.00$3,600.00$3,600.00
c) Decomission Electrical Equipment and ControlsLS1$3,000.00$3,000.00$4,950.00$4,950.00$1,000.00$1,000.00$17,470.00$17,470.00$7,806.67$7,806.67$2,975.00$2,975.00
d) Decomission Other Structures and EquipmentLS1$3,000.00$3,000.00$5,000.00$5,000.00$2,000.00$2,000.00$7,115.00$7,115.00$4,705.00$4,705.00$3,500.00$3,500.00
Decomission Existing Treatment
Item Total (sum 7a through 7d)LS1$18,000.00$23,900.00$14,500.00$33,915.00$24,105.00$19,200.00
7East Septic Tank Installation
a) 8-inch C900 PVC Gravity Sewer PipeLF20$100.00$2,000.00$112.00$2,240.00$127.85$2,557.00$115.00$2,300.00$118.28$2,365.67$119.93$2,398.50
b) 4-inch Schedule 40 PVC PipeLF20$50.00$1,000.00$52.00$1,040.00$55.80$1,116.00$90.00$1,800.00$65.93$1,318.67$53.90$1,078.00
c) 3,000-gallon Pre-Cast Concrete Septic TankEA2$25,000.00$50,000.00$18,090.00$36,180.00$19,079.63$38,159.26$19,600.00$39,200.00$18,923.21$37,846.42$18,584.82$37,169.63
d) Install New 3-foot Deep, Flat Top ManholeEA1$10,000.00$10,000.00$15,000.00$15,000.00$4,500.00$4,500.00$4,280.00$4,280.00$7,926.67$7,926.67$9,750.00$9,750.00
e) Abandon Existing 8-inch Sewer PipeLF10$50.00$500.00$570.00$5,700.00$150.00$1,500.00$390.00$3,900.00$370.00$3,700.00$360.00$3,600.00
f) Abandon Existing ManholeEA1$1,000.00$1,000.00$4,800.00$4,800.00$1,200.00$1,200.00$1,600.00$1,600.00$2,533.33$2,533.33$3,000.00$3,000.00
East Septic Tank Installation
Item Total (Sum 8a through 8d)LS$1.00$64,500.00$64,960.00$49,032.26$53,080.00$55,690.75$56,996.13
8Recirculating Treatment and Subsurface Drip Distribution System
a) 3,000-gallon Pre-Cast Concrete Recirculation TankEA3$25,500.00$76,500.00$26,950.00$80,850.00$31,669.93$95,009.79$21,413.00$64,239.00$26,677.64$80,032.93$29,309.97$87,929.90
b) AdvanTex AX100 Textile Filter UnitsEA3$50,000.00$150,000.00$51,662.00$154,986.00$56,935.59$170,806.77$43,053.00$129,159.00$50,550.20$151,650.59$54,298.80$162,896.39
c) 2-inch Schedule 40 PVC Pressure Effluent Sewer Pipe
(Recirculation Tank C to Treatment units)LF90$30.00$2,700.00$25.00$2,250.00$19.03$1,712.70$37.00$3,330.00$27.01$2,430.90$22.02$1,981.35
d) 4-inch Schedule 40 PVC PipeLF90$50.00$4,500.00$30.00$2,700.00$15.80$1,422.00$40.00$3,600.00$28.60$2,574.00$22.90$2,061.00
e) Custom Primary Flow Splitter BasinLS1$6,000.00$6,000.00$6,842.00$6,842.00$5,866.51$5,866.51$4,177.00$4,177.00$5,628.50$5,628.50$6,354.26$6,354.26
f) Ultra-Violet UnitsEA3$7,500.00$22,500.00$13,178.00$39,534.00$3,407.73$10,223.19$1,773.00$5,319.00$6,119.58$18,358.73$8,292.87$24,878.60
g) Custom Secondary Flow Splitter BasinLS1$6,000.00$6,000.00$7,040.00$7,040.00$6,162.99$6,162.99$3,370.00$3,370.00$5,524.33$5,524.33$6,601.50$6,601.50
h) 3,000-gallon Pre-Cast Dripfield Dosing TankEA1$25,500.00$25,500.00$26,268.00$26,268.00$33,612.46$33,612.46$25,048.00$25,048.00$28,309.49$28,309.49$29,940.23$29,940.23
i) Concrete pad for Controls ShelterLS1$8,000.00$8,000.00$5,000.00$5,000.00$7,500.00$7,500.00$9,200.00$9,200.00$7,233.33$7,233.33$6,250.00$6,250.00
j) Orenco Durafiber Controls ShelterLS1$75,000.00$75,000.00$79,587.60$79,587.60$109,297.83$109,297.83$147,200.00$147,200.00$112,028.48$112,028.48$94,442.72$94,442.72
k) Custom Telemetry Control and Alarm PanelLS1$50,000.00$50,000.00$42,842.40$42,842.40$50,635.63$50,635.63$33,414.00$33,414.00$42,297.34$42,297.34$46,739.02$46,739.02
l) 1-inch Schedule 40 PVC Pressure Effluent Sewer PipingEA30$20.00$600.00$22.00$660.00$10.94$328.20$662.00$19,860.00$231.65$6,949.40$16.47$494.10
m) 1.5-inch Schedule 40 PVC Pressure Effluent Sewer and Drip Field Manifold PipeLF1,420$25.00$35,500.00$23.00$32,660.00$11.51$16,344.20$16.25$23,075.00$16.92$24,026.40$17.26$24,502.10
n) 2-inch Schedule 40 PVC Pressure Drip Field Flush Main PipingLF500$30.00$15,000.00$25.00$12,500.00$12.03$6,015.00$26.00$13,000.00$21.01$10,505.00$18.52$9,257.50
o) 52,000 sq. ft. of Netafim Subsurface Drip Distribution SystemLS1$130,000.00$130,000.00$49,594.00$49,594.00$35,569.23$35,569.23$114,993.00$114,993.00$66,718.74$66,718.74$42,581.62$42,581.62
p) Hydraulic Unit and Disc Filter HeadworksLS1$15,000.00$15,000.00$17,120.00$17,120.00$23,438.46$23,438.46$15,566.00$15,566.00$18,708.15$18,708.15$20,279.23$20,279.23
Recirculating Treatment System
Item Total (Sum 9a through 9p)LS$1.00$622,800.00$560,434.00$573,944.96$614,550.00

Nathan Seaver: Nathan Seaver:

Total for Item 8 from the submitted bid is $614,517.00. I think this is an adding error as I tripple checked the hand written subtotals match the subtotals in this table $582,976.32 Nathan Seaver: Nathan Seaver:

Total for Item 8 from the submitted bid is $614,517.00. I think this is an adding error as I tripple checked the hand written subtotals match the subtotals in this table $567,189.48

9New Water Service
a) 1-inch Water Service Line and heat tapeLF100$40.00$4,000.00$25.00$2,500.00$11.73$1,173.00$29.00$2,900.00$21.91$2,191.00$18.37$1,836.50
b) 1-inch Reduced Pressure Backflow Preventor & Pressure Reducer and heat tapeLS1$900.00$900.00$1,750.00$1,750.00$1,395.03$1,395.03$4,300.00$4,300.00$2,481.68$2,481.68$1,572.52$1,572.52
c) Frost Free HydrantLS1$1,000.00$1,000.00$1,500.00$1,500.00$743.46$743.46$1,619.00$1,619.00$1,287.49$1,287.49$1,121.73$1,121.73
New Water Service
Item Total (Sum 10a through 10c)LS$1.00$5,900.00$5,750.00$3,311.49$8,819.00$5,960.16$4,530.75
10Miscellaneous Site Improvements
a) Chainlink FenceLF360$30.00$10,800.00$57.45$20,682.00$75.00$27,000.00$93.50$33,660.00$75.32$27,114.00$66.23$23,841.00
b) Gravel Access Road Crushed Rock and GeofabricSF2,500$4.00$10,000.00$7.50$18,750.00$8.27$20,675.00$5.25$13,125.00$7.01$17,516.67$7.89$19,712.50
Miscellaneous Site Improvements
Item Total (Sum 11a through 11b)LS1$20,800.00$39,432.00$47,675.00$46,785.00$44,630.67$43,553.50
TOTAL CONSTRUCTION COST (IN $)$822,000.00$778,108.00$836,851.22$931,190.00

Nathan Seaver: Nathan Seaver:

Total from bid is $931,157. The difference is due to a discrepancy in item 8.

Nathan Seaver: Nathan Seaver:

Total for Item 8 from the submitted bid is $614,517.00. I think this is an adding error as I tripple checked the hand written subtotals match the subtotals in this table $848,716.41 Nathan Seaver: Nathan Seaver:

Total from bid is $931,157. The difference is due to a discrepancy in item 8.

Nathan Seaver: Nathan Seaver:

Total for Item 8 from the submitted bid is $614,517.00. I think this is an adding error as I tripple checked the hand written subtotals match the subtotals in this table$807,479.61
TOTAL PROJECT CONSTRUCTION COST (WRITTEN):

Original Bid Estimate

Fischer's Forest Park Rehab Project
Bid Schedule

October 5, 2022

ITEMDESCRIPTIONUNITQUANTITYUNIT PRICESUB TOTALITEM TOTALVSE Comment
1MobilizationLS1$25,000.00$25,000.00Incorporated into Overall estimate
2Erosion ControlLS1$10,000.00$10,000.00Incorporated into Overall estimate
3By-Pass PumpingLS1$20,000.00$20,000.00Incorporated into Overall estimate, asumming constructing in a sequence that minimizes time for tie-over into new system.
4Decommission Existing East Septic TankLS1$10,000.00$10,000.00
5Effluent Lift Station RetrofitLS1$25,000.00$25,000.00
6Decomission Existing Treatment System
a) Decomission Advantex PodsLS1$6,000.00$6,000.00Cost of excavating and transporting to landfill - unsure on cost estimate
b) Remove Existing FenceLS1$6,000.00$6,000.00Cost of excavating and transporting to landfill - unsure on cost estimate
c) Decomission Electrical Equipment and ControlsLS1$3,000.00$3,000.00Cost of excavating and transporting to landfill - unsure on cost estimate
d) Decomission Other Structures and EquipmentLS1$3,000.00$3,000.00Cost of excavating and transporting to landfill - unsure on cost estimate
Decomission Existing Treatment - Item Total
(sum 7a through 7d)LS1$18,000.00
7East Septic Tank Installation
a) 8-inch D-3034 PVC Gravity Sewer PipeLF20$100.00$2,000.00
b) 4-inch Schedule 40 PVC PipeLF20$50.00$1,000.00
c) 3,000-gallon Pre-Cast Concrete Septic TankEA2$25,000.00$50,000.00
d) Install New ManholeEA1$12,000.00$12,000.00WES to provide spec/estimate
East Septic Tank Installation - Item Total
(Sum 8a through 8d)LS$1.00$65,000.00
8Recirculating Treatment System
a) 3,000-gallon Pre-Cast Concrete Recirculation TankEA3$25,500.00$76,500.00
b) AdvanTex AX100 Textile Filter UnitsEA3$50,000.00$150,000.00
c) 2-inch Schedule 40 PVC PipeLF90$30.00$2,700.00
d) 4-inch Schedule 40 PVC PipeLF90$50.00$4,500.00
e) Custom Flow Splitter BasinLS1$6,000.00$6,000.00
f) Orenco UV SystemEA3$7,500.00$22,500.00
g) 3,000-gallon Pre-Cast Dripfield Dosing TankEA1$25,500.00$25,500.00
h) Concrete pad for Orenco Durafiber ShelterLS1$8,000.00$8,000.00
h) Orenco Durafiber Controls ShelterLS1$75,000.00$75,000.00
i) Custom Telemetry Control and Alarm PanelLS1$50,000.00$50,000.00
j) 1-inch Schedule 40 PVC Pressure Effluent Sewer PipingEA30$20.00$600.00
k) 1.5-inch Schedule 40 PVC Pressure Effluent Sewer and Drip Field Manifold PipeLF1,420$25.00$35,500.00
l) 2-inch Schedule 40 PVC Pressure Drip Field Flush Main PipingLF500$30.00$15,000.00
m) 52,000 sq. ft. of Netafim Subsurface Drip Distribution SystemLS1$130,000.00$130,000.00
Recirculating Treatment System - Item Total
(Sum 9a through 9m)LS$1.00$601,800.00
9New Water Service
a) 1-inch Water Service LineLF100$20.00$2,000.00
b) 1-inch Reduced Pressure Backflow Preventor & Pressure ReducerLS1$900.00$900.00
c) Heat TapeLS1$2,500.00$2,500.00Is this for the entire length of water line piping? I've assumed so and applied $25/per linear foot (cell D41)
d) Frost Free HydrantLS1$1,000.00$1,000.00
New Water Service - Item Total
(Sum 10a through 10d)LS$1.00$6,400.00
10Miscellaneous Site Improvements
a) Chainlink FenceLF360$30.00$10,800.00
b) GeofabricSF2,500$0.20$500.00
c) Crushed Rock Surface for Gravel Access RoadCY60$125.00$7,500.00
Miscellaneous Site Improvements - Item Total
(Sum 11a through 11c)LS1$18,800.00

TOTAL CONSTRUCTION COST (IN $) $800,000.00

TOTAL PROJECT CONSTRUCTION COST (WRITTEN):