BGSP_USNO_PRICE SCHEDULE.pdf

PDF 81 KB Posted

Attached to
DBB USNO BOOTHS, GATES, AND SECURE PARKING, NAVAL OBSERVATORY, WASHINGTON DC
Solicitation number
N4008023R0020
Issued by

About this file

This document is a Price Schedule for a Design-Bid-Build contract opportunity for the United States Naval Observatory (USNO) in Washington, DC. The contract includes the replacement and relocation of several deficient security booths, entry control facilities, motorized gates, and vehicle barriers across multiple buildings at the USNO campus.

The Price Schedule lists 14 contract line items (CLINs), including the base bid for Buildings U, M, and E, as well as 11 optional CLINs for additional buildings. Offerors must provide firm fixed prices for all CLINs, and the award will be based on the total price of the base bid and any selected options. The contract duration is 60 months from FY25 to FY30, and the Government has 180 days after award to execute any options. This procurement is restricted to the NAVFAC Washington LMACC contractors.

View the file

Other files

File Type Posted
USNO_Sequencing_Narrative.pdf PDF
SPECIAL NOTICE FOR BGSP-USNO TO LMACC.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

DESIGN-BID-BUILD (DBB) USNO BOOTHS,

GATES, AND SECURE PARKING, NAVAL

OBSERVATORY, WASHINGTON DC

ITEM DESCRIPTION PRICE

0001 Basis of Bid for Item 0001 includes entire work for Building U, complete and in accordance with the drawings and specifications, but excluding work described in Contract Line Items (CLIN) 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, 0013, and 0014.

TOTAL PRICE FOR ITEM 0001 $_______

Basis of Bid for Item 0002 shall be the entire work for Building M, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0003, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, 0013, and 0014.

TOTAL PRICE FOR ITEM 0002 $_______

Basis of Bid for Item 0003 shall be the entire work for Building E, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, 0013, and 0014.

TOTAL PRICE FOR ITEM 0003 $_______

TOTAL BASE BID PRICE FOR ITEM 0001-0003 $_______

0004 Option 1 Basis of Bid for Item 0002 shall be the entire work for Building H, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, TOTAL PRICE FOR ITEM 0004 Option 1 $_______

0005 Option 2 Basis of Bid for Item 0005 shall be the entire work for Building P, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0006, 0007, 0008, 0009, 0010, 0011, 0012, TOTAL PRICE FOR ITEM 0005 Option 2 $_______

0006 Option 3 Basis of Bid for Item 0006 shall be the entire work for Building F, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0007, 0008, 0009, 0010, 0011, 0012, TOTAL PRICE FOR ITEM 0006 Option 3 $_______

0007 Option 4 Basis of Bid for Item 0007 shall be the entire work for Building G, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0008, 0009, 0010, 0011, 0012, TOTAL PRICE FOR ITEM 0008 Option 4 $_______

0008 Option 5 Basis of Bid for Item 0008 shall be the entire work for Building K, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0009, 0010, 0011, 0012, TOTAL PRICE FOR ITEM 0008 Option 5 $_______

0009 Option 6 Basis of Bid for Item 0009 shall be the entire work for Building C, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0010, 0011, 0012, TOTAL PRICE FOR ITEM 0009 Option 6 $_______

0010 Option 7 Basis of Bid for Item 0010 shall be the entire work for Building D, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0011, 0012, TOTAL PRICE FOR ITEM 0010 Option 7 $_______

0011 Option 8 Basis of Bid for Item 0011 shall be the entire work for Building A, complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0012, TOTAL PRICE FOR ITEM 0011 Option 8 $_______

0012 Option 9 Basis of Bid for Item 0012 shall be the entire work for Building B complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, TOTAL PRICE FOR ITEM 0012 Option 9 $_______

0013 Option 10 Basis of Bid for Item 0013 shall be the entire work for Building N complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, and 0014.

TOTAL PRICE FOR ITEM 0013 Option 10 $_______

0014 Option 11 Basis of Bid for Item 0014 shall be the entire work for Building J complete and in accordance with the drawings and specifications, but excluding work described in 0001, 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, and 0013.

TOTAL PRICE FOR ITEM 0014 Option 11 $_______

TOTAL PRICE FOR ITEMS 0001 - 0014 $_______

NOTES:

1. Award will be made on the total sum of Contract Line Items (CLINS) 0001 - 0003, and the sum of the extensions under Contract Line Items 0004, 0005, 0006, 0007, 0008, 0009, 0010, 0011, 0012, 0013, and 0014.

2. Offeror shall provide a price for all items on the Price Schedule. The Offeror shall provide a firm fixed price for Items 0001 through 0014. No provisions will be made for economic adjustments.

3. Options will be evaluated in accordance with FAR 52.217-5 Evaluation of Options. Evaluation of the Options will not obligate the Government to execute any or all of the Options. Option items may be awarded at time of award or within 180 days of award.

4. The Offeror’s price is valid for 60 days from the receipt of proposals.

5. Contract duration is 60 months: FY25 – FY30.

Name & Address of Firm Submitting Offer:

Print Name:__________________________________

Signature:___________________________________

ACKNOWLEDGEMENT OF AMENDMENT(S):___________________________