SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
RFQ IFB RFP
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF. OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NAICS:
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8 (A)
EDWOSB
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
STANDARD FORM 1449 (REV. 2/2012) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
BEP-RFP-15-0371
Conformed Unofficial Copy
TABLE OF CONTENTS:
1. Listing of Incorporated Purchase Requisitions
2. Supplies or Services and Prices/Costs
3. Packaging and Marking
4. Inspection and Acceptance Terms
5. Delivery or Performance
6. Contract Administration Data
7. List of Documents, Exhibits, and other Attachments
8. Contract Clauses
Conformed Unofficial Copy
1. Listing of Incorporated Purchase Requisitions
Incorporated Purchase Requisition Numbers:
2. Supplies or Services and Prices/Costs
Item Number
Base Item Number
Supplies/Services Quantity Unit
0001 Phase-In Training 2 MONTH Contract Type:Firm Fixed Price
Unit Price Extended Price
Description:
Purchase Requisitions
FSC Codes: S216 HOUSEKEEPING- FACILITIES OPERATIONS SUPPORT NAICS Code: 561210 Facilities Support Services
Base Item Number
Supplies/Services Quantity Unit
0002 Base Period: WWPP Operation and Maintenance Labor
10 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Conformed Unofficial Copy Item
Number Base Item Number
Supplies/Services Quantity Unit
0003 Base Period: WWPP Parts and Supplies and Ancillary Services
10 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
0004 Base Period: Process Chemicals (this CLIN is FFP with Econcomic Price
Adjustment (EPA))
10 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
0005 Base Period: Emergency Repair Parts (Optional CLIN) Not to Exceed (NTE)
$500,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Conformed Unofficial Copy
Base Item Number
Supplies/Services Quantity Unit
0006 Base Period: Process Improvements Engineering (Optional CLIN) Not to
Exceed (NTE) $10,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
1001 0002 Option Period 1: WWPP Operation and Maintenance Labor
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item
Supplies/Services Quantity Unit
Conformed Unofficial Copy 1002 0003 Option Period 1: WWPP Parts and
Supplies and Ancillary Services
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
1003 0004 Option Period 1: Process Chemicals (this CLIN is FFP with Econcomic
Price Adjustment (EPA))
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
1004 0005 Option Period 1: Emergency Repair Parts (Optional CLIN) Not to Exceed
(NTE) $300,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Base Item Number
Supplies/Services Quantity Unit
1005 0006 Option Period 1: Process Improvements Engineering (Optional
CLIN) Not to Exceed (NTE) $100,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
2001 0002 Option Period 2: WWPP Operation and Maintenance Labor
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item
Conformed Unofficial Copy 2002 0003 Option Period 2: WWPP Parts and
Supplies and Ancillary Services
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
2003 0004 Option Period 2: Process Chemicals (this CLIN is FFP with Econcomic
Price Adjustment (EPA))
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
2004 0005 Option Period 2: Emergency Repair Parts (Optional CLIN) Not to Exceed
(NTE) $300,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Base Item Number
Supplies/Services Quantity Unit
2005 0006 Option Period 2: Process Improvements Engineering (Optional
CLIN) Not to Exceed (NTE) $100,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
3001 0002 Option Period 3: WWPP Operation and Maintenance Labor
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item
Conformed Unofficial Copy 3002 0003 Optin Period 3: WWPP Parts and
Supplies and Ancillary Services
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
3003 0004 Option Period 3: Process Chemicals (this CLIN is FFP with Econcomic
Price Adjustment (EPA))
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
3004 0005 Option Period 3: Emergency Repair Parts (Optional CLIN) Not to Exceed
(NTE) $300,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Base Item Number
Supplies/Services Quantity Unit
3005 0006 Option Period 3: Process Improvements Engineering (Optional
CLIN) Not to Exceed (NTE) $100,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
4001 0002 Option Period 4: WWPP Operation and Maintenance Labor
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item
Conformed Unofficial Copy 4002 0003 Option Period 4: WWPP Parts and
Supplies and Ancillary Services
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
4003 0004 Base Period: Process Chemicals (this CLIN is FFP with Econcomic Price
Adjustment (EPA))
12 MONTH
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
Base Item Number
Supplies/Services Quantity Unit
4004 0005 Option Period 4: Emergency Repair Parts (Optional CLIN) Not to Exceed
(NTE) $300,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Base Item Number
Supplies/Services Quantity Unit
4005 0006 Option Period 4: Process Improvements Engineering (Optional
CLIN) Not to Exceed (NTE) $100,000.00
1 Each
Contract Type:Firm Fixed Price Unit Price
Extended Price
Description:
Purchase Requisitions
3. Packaging and Marking
4. Inspection and Acceptance Terms
5. Delivery or Performance
Line Item: 0001 Period Of Performance Start Date Period Of Performance End
Date Period Of Performance Address
10/1/15 11/30/15 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable Washington DC 20228-0001
US
Line Item: 0002
Date Period Of Performance Address
12/1/15 9/30/16 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 0003
Date Period Of Performance Address
12/1/15 9/30/16 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 0004
Date Period Of Performance Address
12/1/15 9/30/16 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 0005
Date Period Of Performance Address
12/1/15 9/30/16 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 0006
Date Period Of Performance Address
12/1/15 9/30/16 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 1001
Date Period Of Performance Address
10/1/16 9/30/17 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Conformed Unofficial Copy
Line Item: 1002 Period Of Performance Start Date Period Of Performance End
Date Period Of Performance Address
10/1/16 9/30/17 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 1003
Date Period Of Performance Address
10/1/16 9/30/17 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 1004
Date Period Of Performance Address
10/1/16 9/30/17 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 1005
Date Period Of Performance Address
10/1/16 9/30/17 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 2001
Date Period Of Performance Address
10/1/17 9/30/18 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 2002
Date Period Of Performance Address
10/1/17 9/30/18 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 2003
Conformed Unofficial Copy Period Of Performance Start Date Period Of Performance End
Date Period Of Performance Address
10/1/17 9/30/18 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 2004
Date Period Of Performance Address
10/1/17 9/30/18 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 2005
Date Period Of Performance Address
10/1/17 9/30/18 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 3001
Date Period Of Performance Address
10/1/18 9/30/19 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 3002
Date Period Of Performance Address
10/1/18 9/30/19 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 3003
Date Period Of Performance Address
10/1/18 9/30/19 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 3004
Date Period Of Performance Address
Conformed Unofficial Copy
10/1/18 9/30/19 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 3005
Date Period Of Performance Address
10/1/18 9/30/19 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 4001
Date Period Of Performance Address
10/1/19 9/30/20 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 4002
Date Period Of Performance Address
10/1/19 9/30/20 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 4003
Date Period Of Performance Address
10/1/19 9/30/20 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 4004
Date Period Of Performance Address
10/1/19 9/30/20 BEP-ECF
14th and C Streets, S.W.
ATTN: Accounts Payable
Line Item: 4005
Date Period Of Performance Address
10/1/19 9/30/20 BEP-ECF
14th and C Streets, S.W.
Conformed Unofficial Copy ATTN: Accounts Payable
6. Contract Administration Data
Requesting Office Address
BEP-EHS
Bureau of Engraving and Printing Office of Environmental Health & Safety 301 14th Street SW Washington DC 20228-0001 Phone: Fax:
Contact Details:
HODGE, MYRON N.
MYRON.HODGE@BEP.GOV
COTR Office Address
BEP-EHS
Bureau of Engraving and Printing Office of Environmental Health & Safety 301 14th Street SW Washington DC 20228-0001 Phone: Fax:
Contact Details:
HODGE, MYRON N.
MYRON.HODGE@BEP.GOV
Issuing Office Address
BEP-ACQUISITION
Bureau of Engraving and Printing Office of Acquisition 301 14th Street SW Washington DC 20228-0001 Phone: Fax:
Contact Details:
Johnson, Charlene Charlene.Johnson@bep.gov
7. List of Documents, Exhibits, and other Attachments
8. Contract Clauses
Section A
I. OVERVIEW
1. This is a solicitation for commercial services for Maintenance Support Services at the Bureau of
Engraving and Printing (hereafter "BEP") Eastern Currency Facility (hereafter "ECF") Wastewater Pretreatment Plant (hereafter "WWPP"). This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.
2. The solicitation number is BEP-RFP-15-0371 and is issued as Request for Proposal (RFP). Under this requirement, the Bureau of Engraving and Printing (BEP) intends to award a Firm Fixed Price (FFP) contract.
3. This solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2005-82 including amendments effective 7 May 2015.
4. This requirement is being issued for Full & Open Competition under NAICS code 561210 –Facility Support Services. Only qualified offerors may submit responses. The small business size standard is $35,500,000.00.
II. REQUIREMENT
1. Requirement-Maintenance Support Services for the BEP ECF Wastewater Pretreatment Plant.
2. To be eligible for award, the Offeror must register at https://www.sam.gov, and complete the Offeror Representations and Certifications.
3. Period of Performance – The contract includes a twelve (12) month base period and four (4) twelve (12) month option periods that may be exercised by the Government.
4. A Site Visit is scheduled for Tuesday, 14 July 2015, at 1:30PM ET. See Section L for further instructions.
5. Questions regarding the solicitation must be received no later than 3:00PM ET 20 July 2015. No questions will be accepted or considered after this time. Questions shall be submitted to the Contract Specialist C. E. John Hoddinott via email at charles.hoddinott@bep.gov. Questions will be answered in writing via amendment to the Solicitation.
6. Submit electronic copies to the Contract Specialist, C. E. John Hoddinott, via email at charles.hoddinott@bep.gov.
7. Proposals are due on or before 5:00PM Eastern Time on 7 August 2015.
8. Pricing should be submitted using the applicable Schedule B.
9. Proposals must be valid for ninety (90) days after due date.
10. Any amendment(s) issued to this RFP will be published on this website. Therefore, it the Offeror's responsibility to visit this website frequently for updates on this procurement.
mailto:charles.hoddinott@bep.gov mailto:charles.hoddinott@bep.gov
Section C
1.0 BACKGROUND
The Bureau of Engraving & Printing's (BEP) Facility is a component of the United
States Department of the Treasury that designs, engraves, and prints U.S. currency banknotes and other U.S. security products. U.S. currency banknote manufacturing occurs at BEP's District of Columbia Facility (DCF) located in Washington, DC. BEP's primary customer is the Federal Reserve Board (FRB). As part of the manufacturing process various industrial wastewater streams are generated as well as storm water streams. These waste streams must be either pretreated through the BEP Wastewater Pretreatment Plant (WWPP) in order to comply with environmental regulations that allow for their discharge into the sanitary sewer or must be otherwise managed in compliance with applicable regulations.
1.1 Objective
The Bureau of Engraving & Printing's (BEP) Facility located in Washington, DC contains an Industrial Wastewater Pretreatment Plant (WWPP). BEP's objective is to procure contractor services to manage, operate, maintain supplies and perform maintenance and provide engineering support for the Wastewater and Storm Water Programs. The WWPP requires services to support the BEP on a 24/7 basis. The WWPP currently consists of three (3) systems: (1) Wiping Solution Wastewater Pretreatment Plant (WSWPP), (2) Plating Wastewater Pretreatment Plant (PWPP) and
(3) Grease Trap Wastewater Pretreatment Plant (GTWPP). The WWPP includes an on-site lab and a materials storage area. Refer to Attachments 2, 3, and 4 for descriptions of the three (3) existing systems as well as Attachment 9 and 10 for listings of the equipment that are part of the existing WSWPP and PWPP, respectively.
In FY 2015, BEP is installing a Wiping Solution Recycling Plant that contains three (3) separate, yet interrelated systems: (1) Wiping Solution Recycling Plant (WSRP), (2) Wiping Solution make-up/Manufacturing Plant (WSMMP), (3) Wiping Solution Wastewater Pretreatment Plant (WSWPP). The new WSWPP will replace the current WSWPP. The current PWPP may be replaced during the performance period. Refer to Attachments 5 and 6 for descriptions of the three (3) new systems. In addition to all of these full systems, additional small systems are currently being researched that will be included in scope of this requirement. These processes will be limited to elementary neutralization.
1.2 References
The Contractor shall comply with and perform all Services associated with the contract in accordance with any and all applicable Regulations/ Publications/ Codes. The Contractor is solely responsible for ensuring it is complying with and performing in accordance with any such amendments, supplements to such Regulations/ Publications/ Codes as well as any and all superseding documents issued or enacted during the life of the contract. The following is a listing of applicable Regulations/ Publications/ Codes governing the management, operation, supply, maintenance, and engineering of the BEP Plant. This list is not all inclusive.
REGULATION/
PUBLICATION
ORGANIZATION/
FEDERAL/STATE/LOCAL
AGENCY
WEBSITE/ LOCATION
Federal, State, Local and Organizational Regulations/ Publications/ Codes
All applicable regulations as prescribed under
CFR
1910.
Occupational Safety and Health
Standards
(OSHA),
Department of
Labor http://www.osha.gov/ http://www.osha.gov/
Applicable
S t a n d a r d s a n d c o d e s i n c l u d i n g t h e
National
E l e c tr i c
Code
NEC)
c o d e s
National Fire
Protection Agency
(NFPA)
http://www.nfpa.org/
Applicable s t a n d a r d s
American National Standards Institute
(ANSI)
http://www.ansi.org/ http://www.nfpa.org/ http://www.ansi.org/
Conformed Unofficial Copy r e l a t e d t o s a f e t y a n d h e a lt h a n d
ANSI/ASQC
Q91-1987
Quality y s t e ms
Model f o r
Assurance i n
Design/Development, P r o d u c ti o n I n
Conformed Unofficial Copy s t a ll a ti o n a n d S e r v i c i n g
All a p p li c a b l
Washington
D.C.
r e g u l a ti o n s r e l a t e d t o a ir s o li d
District of
Columbia, Office of Documents and Administrative
Issuance.
http://ddoe.dc.gov/service/regulations-and-legislative-affairs http://ddoe.dc.gov/service/regulations-and-legislative-affairs waste a d water q u a li t y
All a p p li c a b l e r e g u l a ti o n s i n c l u d i n g b u t n o t li mited t o
•40
CFR
Discharge of Oil
United States
Environmental Protection
Agency
(EPA)
http://www.epa.gov/ http://www.epa.gov/
Conformed Unofficial Copy
•40
CFR
Oil
Pollution Prevention
•40
CFR
and •40
CFR
•40
CFR
through •40
CFR
through •40
CFR
Standards for
Universal Waste
Management •40
CFR
Standards for the
Management of
Used Oil •40
CFR
and
Releases to the
Environment •40
CFR
Hazardous Chemical Reporting:
Conformed Unofficial Copy
Community Right-to-Know
•40
CFR
Toxic Chemical Release
Reporting:
Community
Right-to-Know •40
CFR
General Pretreatment Regulations for Existing and New
Sources of
Pollution •40
CFR
433.15 Pretreatment
Standards for
Existing Sources
•NPDES
Multi-Sector
General Permit for Storm Water
Discharges Associated
With Industrial Activities
•NPDES
General Permit for Discharges from Construction
Activities
• 49
CFR
171-180
United States
Department of
Transportation http://www.dot.gov/ http://www.dot.gov/
Conformed Unofficial Copy
(DOT)
BEP's Wastewater Discharge
Permit
DC
Water
(DCWASA)
Attachment 1
BEP Regulations/ Publications/ Codes
BEP's
WWPP
Wiping o l u ti o n
Wastewater
P r e tr e a t ment
P l a n t
WSWPP)
P r o c e s s
Description
BEP Attachment 2
T r e a t ment
BEP Attachment 3
Conformed Unofficial Copy P r o c e s s P l a ti n g
Wastewater
P r e tr e a t ment
P l a n t P
WPP)
P r o c e s s
Description r e a t ment
P r o c e s s
Grease
BEP Attachment 4
Conformed Unofficial Copy T r a p
Wastewater
P r e tr e a t ment
P l a n t
GTWPP)
P r o c e s s
Description r e a t ment
P r o c e s s
Wiping
S o l u ti o n
Recycling
P
BEP Attachment 5
Conformed Unofficial Copy l a n t
WSRP)/
o l u ti o n make-up/Manufacturing
P l a n t
WSMMP)
P r o c e s s
Description
NEW
o l u ti o n
Wastewater
P r e tr e a t ment
P l
BEP Attachment 6
Conformed Unofficial Copy n t
WSWPP)
P r o c e s s
Description
NEW
BEP
E n v ir o ment, Health, n d S a f e t y
Requirement f o r
Construction a n d S e r v i c e s
BEP Attachment 8
Wage
Determination
D O L
Attachment 11
BEP
E n v
B
EP
Provided to the successful contractor after award.
Conformed Unofficial Copy ir o ment, Health, n d S a f e t y P o li c y
Management y s t m
Manual
B
EP
Provided to the successful contractor after award
BEP's
E n v ir o mental
Management y s t e m
B
Provided to the successful contractor after award
Conformed Unofficial Copy Manual
BEP
Operational
Control
Management o f
Hazardous
Waste
D-03.0-04
B
EP
Provided to the successful contractor after award
BEP's
SPCC
Plan
75D-02.0-01
B
EP
Provided to the successful contractor after award
BEP's
E mergency
Action
F ir e P r e v e n ti o n P l a n
D-04.0-01
B
EP
Provided to the successful contractor after award
E s c o rt P r o c e
B
Provided to the successful contractor after award
Conformed Unofficial Copy d u r e
BEP
S e c u ri t y
Manual
Chapter
The Contractor shall notify in writing the Contracting Officer (hereinafter "CO") and Contracting Officer Representative (hereinafter "COR") of any change to an applicable Regulation/ Publication/ Codes and any impact it may have on the contract price. Before implementing any change that will result in a decrease or no change in the contract price, the Contractor shall submit to the CO a proposal no later than fifteen (15) calendar days following receipt of the notification of the change by the Contractor. The Contractor shall implement those changes that result in a decrease or no change in the contract price as directed by the CO. Before implementing any change that will result in an increase in the contract price, the Contractor shall submit to the CO a proposal no later than fifteen (15) calendar days following receipt of the notification of the change by the Contractor. The Government and the Contractor shall then negotiate the change into the contract under the terms and provisions of the contract.
1.3 Acronyms and Definitions
The terms set forth below shall have the following meanings throughout this document:
1.3.1 "BEP" or "Bureau" means the Bureau of Engraving and Printing, U.S. Department of the Treasury.
1.3.2 "Contractor personnel" means all Contractor employees, including subcontractor employees, or any other person(s) acting for or on behalf of the Contractor to perform the Services as specified herein.
1.3.3 "Chemical Process" means a process by which a chemical is manufactured or a process that is inherently chemical in nature such as manufacturing processes that require the physical management of chemical usages in the process and require associated quality control techniques to maintain the process. Examples of chemical processes would be substrate coating operations, painting operations, pharmaceutical operations, water treatment operations, etc. Specifically excluded from this definition is the process of the use of chemicals in boiler treatment or the process of the use of chemicals in cooling tower treatment or chiller facilities.
1.3.4 "Double shift" means two (2) times the normal time period of the contractor's single shift. If the Contractor's normal shift is 12 hours, a double shift is 24 hours consecutively. If the Contractor's normal shift is 8 hours, a double shift is 16 hours consecutively.
1.3.5 "Facilities and/or Facility" means BEP's District of Columbia facility (hereinafter "DCF"), including the Plant, and any changes or improvements thereto, located at 301 14th Street, S.W., Conformed Unofficial Copy
Washington, DC 20228-0001.
1.3.6 "Immediate or Immediately" means within fifteen (15) minutes, unless otherwise specified.
1.3.7 "Janitorial Supplies" means any and all supplies that may be used by personnel to keep the Plant and the personnel clean. Examples of janitorial supplies include, but are not limited to:
paper towels, toilet paper, any bathroom supplies, hand soaps, sanitizers, mops, mop buckets, brooms, dust pans, and components, any floor mats sent for periodic cleaning service, trash bags, etc.
1.3.8 "Key Personnel" means Contractor personnel or positions who/which are considered vital to the performance of the Contract. Those roles that are considered to be Key are the Plant Manager, Assistant Plant Manager, Maintenance Manager, On-site Daily Support Engineer, Maintenance Technician, Supervisor and Operator.
1.3.9 "Materials" means the consumables (e.g. chemicals [lab reagents, support, and process]), supplies (e.g. spare and repair parts and components) and other necessary materials (e.g.
equipment, lubricants and containers) used to perform these services.
1.3.10"Maintenance" includes work to repair and maintain as well as installation of process improvements. This includes work undertaken to prevent damage to equipment, a system or component thereof that otherwise would be more costly to completely overhaul or replace, to maintain Plant equipment and systems in a specified condition, or to restore equipment, systems or components to initial or usable condition by overcoming the effects of breakdowns, wear and tear, damage or deterioration, or work to correct an inoperable, broken, damaged, or worn system or component to a condition such that it operates in the manner in which it was intended or is restored to its "as built" condition and may consist of refurbishing and replacing systems or components as necessary in order to ensure reliable, long-term and safe and efficient operation of the Plant.
However, work performed under Maintenance shall be classified as follows:
1.3.10.1"Preventive/Predictive Maintenance" Preventive/Predictive maintenance is maintenance that is routinely scheduled and performed prior to the failure of equipment.
1.3.10.2"Non-Routine Maintenance" Non-routine maintenance is unscheduled maintenance performed to correct items, which do not adversely affect production or jeopardize compliance with Regulations/ Publications/ Codes, specifically the Discharge Permit or constitute immediate danger to people, property or the environment, but if left unrepaired would result in failure of equipment, systems and/or other issues.
1.3.10.3"Emergency Maintenance" Emergency maintenance is unscheduled maintenance performed to correct failures, which constitute an immediate danger to people, property, the environment or impact production or jeopardize compliance with compliance with Regulations/ Publications/ Codes, specifically the Discharge Permit.
1.3.11"Monitoring and Testing" Monitoring and Testing is performed to provide reasonable assurance that Plant equipment is functioning as designed and that the equipment functions properly under both normal and emergency conditions so that adequate treatment is provided to meet Regulations/ Publications requirements.
1.3.12"Normal Operating Hours" means twenty four (24) hours a day, seven (7) days a week, three hundred sixty-five (365) days a year, including all Federal Holidays and BEP's Shutdown Period. The BEP's Shutdown Period typically occurs between December 25th and January 1st of each year. The COR will notify the Contractor of any change to the schedule.
1.3.13"Oxidation-Reduction Potential or ORP" means tendency of a chemical species to acquire electrons and thereby be reduced. ORP is expressed in millivolts or mV.
1.3.14"Permit" means BEP's Wastewater Discharge permit and future revisions. Refer to Attachment 1 of this document for a copy of the current Permit.
1.3.15"Personal Protective Equipment or PPE" means any type of device, material or equipment that is used to protect an individual from environmental or occupational harm that may be present due to conditions of normal operation or abnormal operation. Examples of these include but are not limited to: safety shoes, safety glasses, gloves, hearing protection, hard hats, protective suits, lotions or creams, etc.
1.3.16"pH" means the negative log of the hydrogen ion concentration of an aqueous material expressed in Standard Units or S.U..
Conformed Unofficial Copy
1.3.17"Plant" means BEP's Industrial Wastewater Pretreatment Plant located at the BEP Washington, DC Facility and any changes, replacement or improvements thereto. The Plant currently consists of three (3) systems: (1) Wiping Solution Wastewater Pretreatment Plant (hereinafter "WSWPP"), (2) Plating Wastewater Pretreatment Plant (hereinafter "PWPP") and (3) Grease Trap Wastewater Pretreatment Plant (hereinafter "GTWPP"). In addition, the Plant includes an on-site lab and Materials storage area. When the new systems are installed as noted herein, they become part of the Plant as well.
1.3.18"Plant shutdown or Plant stoppage" occurs when the Plant is out of operation due to a mechanical, electrical or operational failure, lack of treatment chemicals, or inadequate volume in the treatment tanks. Plant shutdown or Plant stoppage does not occur when the plant is intentionally shut off by the Government because the BEP is not in operation or resulting from a planned shutdown/ stoppage that does not affect BEP operations.
1.3.19"Regulations/ Publications/ Codes" means any and all applicable Federal, State, Local and Organizational laws, regulations, codes, ordinances and conditions (i.e. public and occupational health, safety, and environmental protection, pretreatment regulations, etc.) as well as any and all BEP policies, procedures, guidelines and requirements that govern the management, maintenance and operation of the Plant. A listing of applicable Regulations/ Publications/ Codes is provided in Section 1.2 of this document.
1.3.20"Repair or Repairs" means emergency repairs and minor repairs that are performed (1) in the event that any component or part, including equipment of the Plant should fail or not perform in accordance with Regulations/ Publications and/or equipment specifications, (2) by knowledgeable, trained, certified and experienced personnel utilizing proper equipment and tools and (3) to provide reliable, long-term and safe and efficient operation of the Plant. Repairs are classified as follows:
1.3.20.1"Emergency Repairs": Emergency repairs are required to correct failures which constitute an immediate danger to workers, property, and impact production or jeopardize the Plant's compliance with Regulations/ Publications, specifically the Permit. The Contractor shall assess the situation, immediately (within 15 minutes of becoming aware of the issue) notify the COR or designee and provide a plan of action, and once approved, proceed with completing such repairs in a safe and expeditious manner.
1.3.20.2"Repairs": Repairs are required to correct failures which do not adversely affect production or constitute immediate danger to workers, property, and impact production or jeopardize the Plant's compliance with Regulations/ Publications, specifically the Permit. The Contractor shall assess the situation, notify the COR or designee and provide a plan of action within twenty-four (24) hours of being alerted or becoming aware of failure or situation, and once approved, proceed with completing the repair in a safe and expeditious manner.
1.3.21"SCADA" Supervisory Control and Data Acquisition software and associated hardware. This is also referred to as Human-Machine Interface software or HMI. This is the equipment control software used for operational control in most of the Plant systems.
1.3.22"Maximo" A BEP provided enterprise asset management application software through which asset lifecycle maintenance is performed. All materials, supplies and spare parts are managed through the storeroom function and all maintenance activities including PMs, calibrations, monitoring and measuring activities are managed through the service request and work order system. Although Maximo is a BEP wide application, the Plant will utilize a separate subset of the system that is not visible to the rest of BEP on a generalized basis.
1.3.23"Services" means the Contractor providing throughout the performance of the contract any and all labor and resources such as, but not limited to; Management, Operations, Engineering, Maintenance, Sampling and Testing, Monitoring, Measuring, Repairs, Process improvements, Transportation as well as any Tools and Equipment and Materials furnished by or utilized by the Contractor in the performance of this effort for the safe, clean, orderly, efficient and successful operation, management and maintenance during Normal Operating Hours the BEP Plant.
1.3.24"Tools and Equipment" means the tools and equipment furnished by the Contractor to perform the Services.
For example, the Contractor is to identify and provide its personnel with the necessary respiratory and Personnel Protective Equipment (hereinafter "PPE") as required by OSHA regulations. The Contractor is responsible for identifying the Tools and Equipment needed to perform these Services.
2.0 SCOPE
The Contractor shall perform any and all Services necessary for the safe, neat, clean, orderly, efficient and successful management, operation, maintenance, and engineering during Normal Operating Hours of the BEP's Industrial Wastewater
Conformed Unofficial Copy Pretreatment Plant (hereinafter "Plant") which includes small ancillary treatment systems, existing and installed, during the performance of this contract located in Washington, DC in addition to assigned Storm water activities.
The Government's objectives are to obtain Services of exceptional value that afford it the opportunity to continuously improve, reduce costs and develop effective and efficient means to manage, operate, and maintain the Plant. Therefore, the Contractor shall implement the necessary controls, plans, processes, etc. to ensure such value. The contractor shall ensure that prudent engineering and operating practices are utilized at all times; with prudent engineering and operating practices meaning the practices, methods, and acts that at a particular time, in the exercise of reasonable judgment in light of the facts known or that should have been known at the time a decision was made, would be expected to accomplish the desired result in a manner consistent with law, regulation, reliability, safety, environmental protection, and the written recommendations of the equipment manufacturers. The Government will continue to implement improvements to the Plant throughout the duration of this effort and future efforts; thus it is expected that the Contractor is able to continuously tailor their controls, plans, processes, etc. to the needs of the BEP. The Contractor is expected to perform in accordance with the contract and performance requirements contained herein and in the attachments. The separation of the Contractor's responsibility and BEP' s responsibility is the point at which a given utility (electricity, air, water, wastewater, and IT supplies) is provided to the equipment in the Plant. Once the utility is attached to the Plant equipment, the remainder of the responsibility belongs to the Contractor and is as such, then governed by the requirements prescribed herein.
2.1 Contract Line Item Number (CLIN) Structure and Definitions:
The Contract Line Items (CLINs) are defined as follows:
2.1.1 CLIN 001: Firm Fixed Price (FFP) - Phase-in and Training.
Description: This CLIN will provide for all of the labor and expenses associated with Phase-in for the existing Plant and training on the new systems. (Ref. Sections 3.25., 5.2., 5.12.1).
2.1.2 CLIN 002 (and subsequent options if exercised): Firm Fixed Price (FFP) - Operation and Maintenance Labor.
Description: This CLIN will provide for all of the labor for Management, Operations, Daily On-site Engineering and Maintenance of the new plant and the remaining equipment along with the equipment that will go away ( the current Wiping Solution Wastewater Pretreatment Plant) while the new equipment is being brought up on line. Examples of the labor requirements included in this CLIN would be operating the systems, labor for managing parts and supplies in Maximo, identifying new spare parts requirements for the new equipment, setting up and maintaining Maximo for the Plant, cleaning all equipment in the plants, calibrating probes, changing malfunctioning probes, performing all maintenance on all of the plant equipment, recording data, collecting samples for operational control and performing operational control testing, collecting compliance samples, sending compliance samples to the lab, and preparing deliverables.
The scope of this CLIN will also include labor to install process improvements associated with the new equipment where the improvements fall clearly in line with the required capabilities of the maintenance personnel, such as installing system equivalent pumps, tanks and control equipment as well as decontaminating and removing obsolete equipment as applicable. (Ref. Sections 3.4.3., 3.5., 3.25., 4.10.)
2.1.3 CLIN 003 (and subsequent options if exercised): FFP - Parts and Supplies and Ancillary Services.
Description: This CLIN provides for all parts, supplies, and ancillary services for the current systems that will remain (PWPP, GTWPP) and the supplies and ancillary services for the systems that remain which will be used on the new systems (WSWPP, WSRP, WSMMP) and are currently used excluding process or treatment chemicals used in the current and new equipment which would be covered by a separate CLIN.
This CLIN includes current lubricants, plant deodorizers, and laboratory supplies and chemicals. This CLIN also includes the ancillary services that are normally performed by outside sub-contractors.
Ancillary Services include the following: outside laboratory analysis, process control equipment and scale calibrations, confined space meter calibrations and service, laboratory equipment calibrations, SCBA tank testing and service, outfall flow measurement (only in FY 2017) and corrosion monitoring for sulfuric acid storage and piping. (Ref. Sections 3.3.3., 3.22., 3.27., 3.28., 3.29., 3.32.1., 3.36.)
2.1.4 CLIN 004 (and subsequent options if exercised): FFP - Process Chemicals.
Description: This CLIN provides for all process and treatment chemicals used to recycle the used wiping solution, make-up new wiping solution, treat the non-recycled wiping solution, and treat the plating wastewater. A listing of materials and their annual usage estimates are provided in Attachment 22. (Ref.
Section 3.3.3.)
2.1.5 CLIN 005 (and subsequent options if exercised): Not To Exceed (NTE), and unfunded $ -
Conformed Unofficial Copy
Emergency Repair Parts and Service; New Equipment Spare Parts; and Process Improvement Parts
Description: This CLIN provides for emergency repair parts and service where the prime Contractor does not have the specialized skills or equipment to perform emergency repairs, an example might be welding on a stainless steel tank to fix a leak, another example would be if something happened to the SCADA software and IT could not fix the problem. This would also include spare parts for the new equipment that are not presently known; for example the new equipment has pumps. These pumps will require periodic maintenance. The maintenance will require unknown parts in order to rebuild the pump so that it may be placed back into service. The contractor is required to identify the spare parts for the new equipment and set up the information in WWPP Maximo system and provide the information to BEP. As a quotation is provided for the list of new equipment spare parts, a new requisition would need to be written so that the parts would be charged for under this CLIN. As the new system parts are identified, in time they will be added to Section 2.1.3. Finally this CLIN will provide the parts needed for process improvements. As noted in Section 2.1.2, the prime contractor will already be required to provide installation labor for process improvements. (Ref. Sections 3.3.1., 3.25., 3.31., 3.28.)
2.1.6 CLIN 006 (and subsequent options if exercised): NTE, and unfunded $ - Process Improvements Engineering.
Description: This CLIN provides for the engineering labor to develop process improvements. The Contractor may suggest Process Improvements and submit a quotation, or the government can request the Contractor to provide a quotation for a Process Improvement. These would be in terms of a Task Order (TO) or a Delivery Order (DO). It is important to understand that any equipment, part, or supply needed for a Process Improvement would be covered under Section 2.1.5 type description and the installation labor would already be covered under the Section 2.1.2 type description. If the Process Improvement is decided to go forward with, a requisition would be written to cover the cost for the engineering labor here and the parts under Section 2.1.5. It should be also understood that only 1 or 2 Process Improvement projects would be undertaken in a year, after the new equipment warranty is out on the equipment. Therefore there would be no Process Improvements requiring engineering in the base period. (Ref. Sections 3.5., 3.25., 3.34., 4.10.)
3.0 Contractor Responsibilities:
The Contractor shall be responsible for, but not limited to:
3.1 General: Managing, operating, and maintaining the Plant in a neat, clean, orderly, efficient and professional fashion during Normal Operating Hours, to include furnishing required supplies and equipment in performance of this contract.
3.1.1 Fines and Penalties: The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel, security, and environmental management within the Contractor's control during the execution of work, and shall hold the BEP harmless for any action on its part or that of its employees or subcontractors including but not limited to illness, injury, death or fines. If the Contractor fails to operate the Plant in compliance with the BEP Discharge Permit or any applicable regulation and any fines or penalties are assessed against the BEP, the Contractor shall reimburse the BEP the amount of these fines and penalties and the cost of any legal defense against them.
3.1.1.1 Plant Shutdown: The Contractor shall fully recognize that the services covered by this contract are vital to BEP's mission; that continuation of the services shall be maintained at the utmost proficiency without interruption since the operation, management and maintenance of the Plant is vital to the BEP's mission. If the Contractor fails to maintain the Plant in 100% operational status and/or in compliance with the Regulations/Publications/Codes, except when such conditions are beyond the control of the Contractor (e.g. acts of God, civil unrest, labor disputes, military events) or when directed by the BEP, resulting in shutdowns/stoppages and/or fines or penalties being levied against the BEP, the BEP will assess damages and pass that amount onto the Contractor for reimbursement. These damages will be determined by and based upon the amount of down-time, the number of presses affected, and any direct support to the affected area(s) as well as the actual amount of any the fine(s) and/or penalty(ies) levied against the BEP. Current BEP labor rates will be used where applicable and other costs will be based upon actual costs.
Example: $1,000.00 fines or penalties were assessed, one (1) hour down-time, affecting one (1) press with direct support being Plate Printer at $50.40/hr and a Foreman at $71.47/hr and
Conformed Unofficial Copy production cost of $500.00. Therefore, the amount that would be assessed against the Contractor would be as follows:
Information:
Penalties/ Fines = $1,000.00
Plate Printer $50.40/hr x One (1) hour = $50.40
Foreman $71.47/hr x One (1) hour = $71.47
Production cost $500.00 x One (1) hour = $500.00
Formula
$1,000.00 + ($500.00 +$50.40 + $71.47) = $1,621.87 (Total amount of Damages to be assessed against the Contractor.)
House Keeping: This includes keeping waste to a minimum as well as keeping the Plant work area free of all foreign materials. Control cabinets are not to be used for storage and all maintenance items (tools, excess parts, used parts, waste materials, etc.) are to be placed in their proper location at the end of the operations or maintenance event.
Odor Control: The Contractor shall ensure that no malodorous odors escape from the plant. There are processes internal to the plant, which periodically generates malodorous odors. These odors must be controlled inside of the plant before they exit the plant by the use of odor control agents.
Roll – up Doors: All roll-up doors must be kept closed unless transferring materials or equipment. The doors must be closed within 15 minutes of using the door, unless the doors are being used by the Office of Security. If a separate government contractor is causing the doors to be opened periodically, it is still the responsibility of the Plant Contractor to ensure that the doors are opened and closed as prescribed herein.
Maintenance of Plant Documentation: The Contractor will update Plant documentation (all associated documents, forms, and electronic drawings) as changes in equipment, materials, and processes occur or as directed by the COR. The documentation must be updated after changes are completed so that the documentation is updated to the final level of the change. The updated document must be sent to the COR for review and approval within 15 calendar days of the completion of the change. The changes in the documentation will be highlighted so as to be easily recognizable with new or additional information in light blue and obsolete information struck through. Once the changes are approved by the COR, the Contractor will remove the obsolete information, leaving the highlighted information until the next change.
A change record will be maintained for each document in accordance with standard ISO document control methodologies and BEP policies.
3.2 Workforce and Personnel:
The Contractor shall hire, train, administer, manage and supervise the workforce necessary to perform the Services.
Under no circumstances shall any contract employee be hired to fulfill the requirements of the position for which they have applied that they do not already meet the requirements for the position unless otherwise noted. The BEP Plant is not to be a training facility. A contractor employee should only need to become familiarized with the work prescribed herein for which they will be performing and require the training as prescribed herein.
If after hiring a contract employee, the Contractor finds that the employee does not or cannot fulfill the requirement for the positions for which they were hired, the Contractor must remove the contractor employee from this contract and will be required to replace the removed contractor employee at the Contractor's full expense.
The Contractor is required to have a system by which they evaluate all contract employees to ensure that they are performing to the expected level of the position for which they are employed as
Conformed Unofficial Copy prescribed herein.
If the COR observes a contract employee that appears to not be performing to the required level of performance as prescribed herein, that action will be brought to the attention of the appropriate level of management of the Contractor for corrective action as appropriate. The Contracting Officer reserves the right to remove personnel from this contract if they do not meet the qualifications and/or performance of the required position.
The Contractor shall maintain satisfactory standards of personnel competency, conduct, appearance, and integrity and shall be responsible for taking such disciplinary action with respect to their personnel as necessary.
Ensuring there is sufficient personnel to perform Services at all times throughout the performance of…