Barracks Camera System PWS.docx
DOCX document 45 KB Posted
- Attached to
- Barracks Camera Systems
- Solicitation number
- M6700126Q0145
- Issued by
-
United States Marine Corps
About this file
This is a Performance Work Statement (PWS) for the acquisition, professional installation, configuration, and testing of a complete security surveillance system at Marine Corps Air Station (MCAS) New River barracks. The current surveillance infrastructure is failing and compromising personnel safety and property security, necessitating a comprehensive upgrade to a turn-key solution featuring uninterrupted high-resolution visual coverage and secure footage storage.
The contractor must deliver and install eight Network Video Recorders (NVRs), nine 5-megapixel IP cameras, five 500VA Uninterruptible Power Supplies (UPS), and seven 22-inch HD monitors across 11 locations at MCAS New River within a 90-day performance period. All equipment must be NDAA Section 889 and Trade Agreement Act (TAA) compliant, excluding prohibited manufacturers such as Huawei, ZTE, Hytera, Hikvision, and Dahua. The PWS specifies acceptable COTS equipment options (QND-7082R cameras, QRN-1630S NVRs, SMART500RT1U UPS units, and VG2239Smh-2 monitors) or equivalent compliant alternatives. Service requirements include professional installation with knowledgeable technicians using ladders for interior work and lifts for exterior three-story building access, system configuration for independent network operation with 24-hour continuous recording retaining 30 days of rolling footage, full hardware integration, and comprehensive functional testing of all camera feeds, recording triggers, UPS battery transitions, and monitor outputs. The contractor must obtain all necessary Defense Biometrics Identification System (DBIDS) enrollment and base access credentials for personnel prior to work commencement, with all costs for travel, lodging, and local transportation the responsibility of the contractor. A standard one-year warranty covering maintenance and upkeep is required following installation completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Barracks Camera System PWS_0002.docx | DOCX document | |
| QandA 0002.docx | DOCX document | |
| QandA 0001.docx | DOCX document | |
| Barracks Camera System RFQ_0001.docx | DOCX document | |
| Barracks Camera System PWS_0001.docx | DOCX document | |
| Barracks Camera System RFQ.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.0 Introduction Marine Corps Air Station (MCAS) New River is requesting the acquisition, professional installation, configuration, and testing of security surveillance equipment across multiple barracks locations. This requirement arisied due to the current security surveillance infrastructure failing, presenting operational deficiencies that compromise the safety of personnel and property.
1.1 Background The security surveillance infrastructure at the MCAS New River barracks is currently failing, presenting operational deficiencies that compromise the safety of personnel and property. To address these technical issues, this requirement establishes a complete repair and upgrade of the barracks surveillance system. The project funds the procurement, installation, and integration of reliable, high-definition recording and monitoring equipment.
1.2 Scope The scope of this requirement encompasses the acquisition, professional installation, configuration, and testing of security surveillance equipment across multiple barracks location at MCAS New River. This upgrade will directly impact the living environments of residing military personnel and secure military property by establishing uninterrupted, high-resolution visual coverage and secure storage of evidentiary footage.
2.0 Requirement
The contractor shall deliver a complete, turn-key surveillance solution. The systems must meet the salient characteristics for the following technical parameters and component counts:
· Eight (8) Network Video Recorders (NVRs)
· Nine (9) High-resolution 5-Megapixel (5MP) cameras
· Five (5) 500VA Uninterruptible Power Supplies (UPS)
· Seven (7) 22" High-Definition Monitors
· Two (2) CAT5 Wiring
· All serviceable cabling in good condition shall be re-used.
· Complete professional labor including installation, system programming, and operational testing. Any items for disposal become property of the contractor.
· A standard (1) Year warranty is required to upkeep and maintain for the first year after installation.
2.1 NDAA-Compliant Equipment & Market Research Reference:
· To comply with NDAA Section 889 and the Trade Agreement Act (TAA), the prohibition on procuring or using telecommunications, video surveillance equipment, or services from certain covered manufacturers (e.g., Huawei, ZTE, Hytera, Hikvision, Dahua) as a substantial or essential component or critical technology in any system
· The following table provides verified, NDAA-compliant Commercial Off-The-Shelf (COTS) equipment that meets or exceeds the specifications outlined in Section 4.0:
· The items mentioned below will need to installed in a server closet if available in the dedicated barracks with the following dimensions 24” X 24” X 60”. If server closet is not available in the barracks the installation will be conducted in the barracks lounge area.
· Camaras will be mounted on a brick wall on the exterior and a similar material in the inside.
· All monitors and NVR components must be compatible with any existing equipment and will be located on a table, or in a dedicated mounting rack. Every building will have one or the other so monitor or NVR will not need to be mounted.
· The listed items below are the equipment that we have knowledge that meet the NDAA & TAA compliant. Any other equipment/manufacturer that meets the criteria is acceptable.
| PWS Component |
| Part Number |
| Minimum Salient Characteristics |
| 5MP Camera (Qty: 9) |
| QND-7082R or equal |
| • Network/IP dome camera • Minimum 5 MP resolution • Motorized varifocal lens, approximately 3–10 mm or range sufficient for required field of view • Integrated IR/night illumination • PoE capable • H.265 and/or H.264 video compression • Vandal-resistant construction suitable for barracks/common-area installation • Compatible with proposed NVR/VMS |
| NVR / Recorder (Qty: 8) |
| QRN-1630S or equal |
| • Minimum 16 IP camera channels • Supports 5 MP or greater camera recording • Minimum 128 Mbps aggregate recording/input bandwidth • Integrated PoE/PoE+ switch sufficient to support connected cameras • Supports H.265/H.264 • Local monitor/video output • Network connectivity for configuration/playback • Compatible with proposed cameras • NDAA-compliant, if required by the acquisition |
| 500VA UPS (Qty: 5) |
| SMART500RT1U |
or equal
• Minimum 500 VA / 300 W output capacity • Line-interactive UPS • Rack-mountable, maximum 1U • Automatic voltage regulation (AVR) • Battery backup and surge protection • Input/output compatible with installed equipment and facility power • TAA compliant, if applicable to the acquisition
22" HD Monitor (Qty: 7)
| VG2239Smh-2 or equal |
| • Minimum 21.5-inch viewable display • Minimum 1920 × 1080 (Full HD) native resolution • LED-backlit LCD or equivalent • Digital video input compatible with proposed NVR (e.g., HDMI or DisplayPort) • Suitable for extended commercial-duty operation • TAA compliant, if applicable to the acquisition |
2.2 Service Requirements
· Professional Installation: Knowledgeable technicians shall securely mount and install all cameras, NVRs, power supplies, and monitors will not be mounted but will be standing on a desk. In order to make the process easier we suggest a site visit/ walkthrough to get a better gage of equipment needed or what the contractor deems necessary to complete the job in the safest way possible.
· The installation process will require both ladders for interior work and lift for exterior work to reach height of three-story building.
· System Configuration: The system shall operate on an independent network with no external internet or server connectivity. Technicians shall configure the system for continuous 24-hour recording on all channels, retaining a minimum of 30 days of footage on a rolling bases before automatically overwriting the oldest data.
· System Integration: All hardware components must be fully integrated to function as a unified, stable system and function with any existing equipment or cabling.
· Functional Testing: The contractor must perform operational verification testing on every camera feed, recording trigger, UPS battery transition, and monitor output to ensure optimal performance prior to government acceptance. As well as functional updating and upkeep of the newly installed cameras to maintain a functional and operational system.
2.3 Place/Period of Performance:
| Place of Performance |
| Item/Service Description |
| Period of Performance |
| Location 1 |
| · NVR (Qty 1) |
· Camera (Qty 4)
· Wire & Connector (Qty 1) 90 days ARO
| Location 2 |
| · NVR (Qty 1) |
· UPS 500VA (Qty 1) 90 days ARO
| Location 3 |
| · NVR (Qty 1) |
· UPS 500va (Qty 1)
· 22” Monitor (Qty 1)
· Cameras 5mp (2) 90 days ARO
| Location 4 |
| · 22’ Monitor (Qty 2) |
| 90 days ARO |
| Location 5 |
| · NVR (Qty 1) |
· UPS 500va (Qty 1)
· 22” Monitor (Qty 1) 90 days ARO
| Location 6 |
| · NVR (Qty 1) |
· UPS 500va (Qty 1)
· 22” Monitor (Qty 1) 90 days ARO
| Location 7 |
| · NVR (Qty 1) |
· 22” Monitor (Qty 1)
· UPS 500va (Qty 1) 90 days ARO
| Location 8 |
| · 22” Monitor (Qty 1) |
| 90 days ARO |
| Location 9 |
| · Wire & Connector (Qty 1) |
| 90 days ARO |
| Location 10 |
| · NVR (Qty 1) |
| 90 days ARO |
| Location 11 |
| · NVR (Qty 1) |
· 22” Monitor (Qty 1)
· Camera 5mp (Qty 3) 90 days ARO
3.0 Inventory of current CCTV System
CCTV hardware configuration is standardized across all barracks. The only dynamic variable is the DVR, which has been updated on an as-need basis to replace obsolete units.
1. Security Camera: (3-4) per barracks Nest Cam 2k or 4k total: 44
2. Digital Video Recorder: TruVision DVR 30 (1) per barracks: 11
3. System Monitor: 27in LG monitor computer (1) per barracks total: 11
4. Cabling & connectors: CAT5 total (1 lot) 11 lots in total
5. Uninterrupted Power Supply: 120V type A: multiple in storage room: (1) imitate in barracks lounge
4.0 Base and Flightline access instructions for MCAS New River
The contractor is responsible for obtaining all necessary base access credentials for personnel and vehicles prior to the start of work. No flightline access is required or authorized for this project. A list of basic items needed to get base access.
4.1 Requirements for individual Workers
· (2) valid forms of ID (Real ID, driver’s license, Passport)
· SECNAV From 5512/1 (Base access pass registration form
· DBIDS pre-enrollment
· Social Security Card
-Contractors must be registered in the Defense Biometrics Identification System (DBIDS). It is the Contractor’s responsibility to ensure all their employees and/or subcontractors are properly registered within DBIDS.
-DBIDS credentials will be valid for the duration of your contract, not to exceed three years; however, re-vetting of individuals' information will occur each year.
-Contractors requiring access for over 60 days will receive a credential valid for up to one year.
-Contractors requiring access for less than 60 days will receive a temporary paper pass.
-Contractor Common Access Card (CAC) Eligibility: Contractor personnel authorized CACs are exempt from DBIDS enrollment.
Performance Work Statement
-If you have questions regarding base access, Contractor CACs, or DBIDS requirements, contact the Contractor Vetting Office (CVO). The CVO is located in Bldg. 818 adjacent to the Camp Lejeune Main Gate on Holcomb Blvd, just off NC Highway 24. The CVO is open Monday through Friday from 6 a.m. to 2 p.m. and closed on weekends and holidays.
Contractor Vetting Office - Appointments: 910-451-5977 Contractor Vetting Office - Questions: 910-451-0284/0289 Taxi Vetting: 910-449-4208 Vetting Office Email: lejeunecontractorvetting@usmc.mil DBIDS email: https://dbids-global-enroll.dmdc.mil/preenrollui/#!/
-Contractors will report to the Contractor Vetting Office (CVO) to confirm their access requirements, undergo a background check and receive their credential/pass.
PLEASE NOTE: Individuals with active warrants may be subject to arrest on the spot
**The Government will not be responsible for any contractor access delays. Delays that may result from inadequate planning are strictly the responsibility of the contractor.
4.2 Additional Information
· All parking and equipment can be staged at each barracks parking lot.
· Commands will be notified to ensure adequate space.
· No unauthorized photos or videos are allowed anywhere on MCAS New River without the written consent of the CG (Commanding General).
· Work shall not take place at any time on the flightline. The Government will NOT provide any travel, lodging, or local transportation in connection with this contract.
End of Performance Work Statement