B2603ADD2.pdf

PDF 135 KB Posted

Attached to
Sperling Sports Complex Parking Improvements
Solicitation number
B-26-03
Issued by
Florida

About this file

This is Addendum #2 to the bid package for the Sperling Sports Complex Parking Improvements project issued by the City of DeLand, Florida Finance Department. The project encompasses improvements to the existing asphalt parking lot and addition of durable drive aisles, with key items including mobilization, sediment barrier installation, clearing and grubbing, excavation (750 cubic yards each of regular and borrow), concrete paving (76 square yards of 6-inch thick), turf sodding (6,635 square yards of Bahia sod), permeable turf stabilizer grid installation (27,939 square feet), fencing (880 linear feet), concrete bumper guards (174 units), pavement markings and thermoplastic striping, and ground sign assembly and relocation. The proposal opening date and time is December 16, 2025 at 3:00 p.m.

This addendum provides clarification regarding the permeable grid paver specifications and installation requirements. The unit bid requires the Ecoraster E40 permeable grid pavers installed per the Construction Plans using sandy loam fill at 70-80% compaction to accommodate Bahia sod root establishment, with technical assistance available from Ferguson's Eric Smith at (407) 276-2607. An approved alternate product, TrueGrid ROOT, is also permitted, and bidders must provide both a unit price and extended price for the complete installation of this alternate product as line item 999-5, as it differs in cost and installation methodology. The addendum includes a summary of all pay items with quantities and space for unit and extended pricing, along with a 5 percent contingency allowance. All other terms and conditions of the original bid package remain unchanged.

View the file

Other files

File Type Posted
B2603SimpleTab.pdf PDF
B2603ADD3.pdf PDF
B2603ADD2Attachment.xlsx XLSX spreadsheet
B2603ADD1.pdf PDF
B2603Specs.pdf PDF
B2603Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Finance Department 120 S. Florida Ave.

2nd Floor

DeLand, FL 32720

Sperling Sports Complex Parking Improvements B-26-03

December 11, 2025 Addendum #2

TO ALL PROSPECTIVE CONTRACTORS

This is an Addendum to and shall be considered as part of the original Bid package for the above-mentioned Bid. Contractors are requested to acknowledge receipt of this Addendum with their

Submission.

CLARIFICATION TO QUESTIONS ASKED RECEIVED:

1. Question: There isn't a line item for the rock to fill in the pavers. Should we just include that in the overall BID is there a specific stone you prefer?

Answer:

Ecoraster E40

The Permeable Grid Pavers for the Unit Bid (Ecoraster E40) are to be installed as per the method outlined on sheet 7 of the project’s Construction Plans under Permeable Turf Stabilizer Grid

Sequence of Construction. This is based on the “Ecoraster Green” method with DIY Greened filling as described in the product’s installation guide. The fill is to be soil that accommodates

Bahia Sod root establishment yet can also be compacted to a rate that provides stability to the grid; such as Sandy Loam at 70-80%. Detailed product information and installation planning assistance can be obtained from the manufacturer or Eric Smith at Ferguson, (407) 276-2607.

https://ecorastergrid.com/product/e40/

TrueGrid ROOT (Approved Equal/Alternate via Addendum #1)

The Permeable Grid Pavers for the approved, alternate product (TrueGrid ROOT) are to be installed as per the product’s installation guide. The base material/soil should be compacted to a rate that provides stability yet still accommodates Bahia Sod root establishment. Detailed product information and installation planning assistance can be obtained from the manufacturer’s

Engineer, Chris White, P.E., at (832) 292-5121. https://www.truegridpaver.com/products/root/

*Please note there is a difference in cost and installation method/sequence for these two products.

The Unit Bid is to include the Ecoraster E40 permeable grid. Please provide an alternate unit and extended price for line item #999-5 for the complete installation of the approved equal/alternate product TrueGrid ROOT permeable grid.

https://ecorastergrid.com/product/e40/ https://www.truegridpaver.com/products/root/

December 11, 2025 Addendum #2

SPERLING SPORTS COMPLEX PARKING IMPROVEMENTS - SUMMARY OF PAY ITEMS

PAY ITEM NO. PAY ITEM DESCRIPTION UNIT QTY UNIT PRICE

EXTENDED

PRICE

101-1 MOBILIZATION LS 1

104-10-3 SEDIMENT BARRIER LF 816

104-15 SOIL TRACKING PREVENTION DEVICE EA 1

104-18 INLET PROTECTION SYSTEM EA 2

110-1-1 CLEARING & GRUBBING LS 1

110-21 TREE PROTECTION BARRIER LF 294

120-1 REGULAR EXCAVATION CY 750

120-2 BORROW EXCAVATION CY 750

522-2 CONCRETE PAVING 6" THICK SY 76

550-10-210 FENCING, TYPE B, 0.0-5.0', STANDARD LF 880

542-70 CONCRETE BUMPER GUARD FOR PARKING LOT EA 174

570-1-2 PERFORMANCE TURF, SOD SY 6,635

700-1-111

SINGLE COLUMN GROUND SIGN ASSEMBLY, F&I

GROUND MOUNT, LESS THAN 12 SF AS 6

700-1-500 SINGLE COLUMN GROUND SIGN ASSEMBLY, RELOCATE AS 1

710-90

PAINTED PAVEMENT MARKING, STANDARD WHITE,

SOLID, 6" LF 3,263

710-11-160

PAINTED PAVEMENT MARKING, STANDARD WHITE,

HANDICAPPED SYMBOL EA 7

710-11-170

PAINTED PAVEMENT MARKING, STANDARD WHITE,

SOLID, ARROW EA 7

711-11-123

THERMOPLASTIC, STANDARD WHITE, SOLID, 12" FOR

CROSSWALK LF 459

711-11-125

THERMOPLASTIC, STANDARD WHITE, SOLID, 24" FOR

STOP BAR LF 41

999-1 PERMEABLE TURF STABILIZER GRID (ECORASTER E40) SF 27,939

999-2

HANDICAPPED PARKING SIGN, FENCE MOUNT,

RELOCATE EA 2

999-3 HANDICAPPED PARKING SIGN, F&I FENCE MOUNT EA 2

999-4 CONTINGENCY (5%) LS 5%

TOTAL PRICE $0.00

SUMMARY OF ALTERNATE PAY ITEMS

PAY ITEM NO. PAY ITEM DESCRIPTION UNIT QTY UNIT PRICE

EXTENDED

PRICE

999-5 PERMEABLE TURF STABILIZER GRID (TrueGrid ROOT) SF 27,939

PAY ITEM

NOTES

101-1 INCLUDES THE COST FOR CONTRACTOR QUALITY CONTROL (CQC) TESTING

FOR ANY OF THE FOLLOWING THAT ARE NECESSARY TO COMPLETE THE

December 11, 2025 Addendum #2

CONSTRUCTION OF THIS PROJECT: ASPHALT, CONCRETE EARTHWORK.

INCLUDES THE COST OF CAPPING AND REPAIR OF ANY EXISTING IRRIGATION

SYSTEM LOCATED WITHIN THE R/W. INCLUDES THE COST OF TEMPORARY

DRAINAGE DURING CONSTRUCTION TO ELIMINATE ANY FLOODING OF PRIVATE

PROPERTY AND TO MAINTAIN EXISTING FLOWS WITHIN R/W.

110-1-1 INCLUDES, BUT NOT LIMITED TO, THE REMOVAL AND DISPOSAL OF ALL

OBSTRUCTIONS, VEGETATION, DEBRIS, TRIMMING OF TREES AND SHRUBS,

ROOT REMOVAL, EXISTING ASPHALT PAVEMENT, BASE AND DRAINAGE

STRUCTURES, SIDE DRAINS, AS REQUIRED, TO CONSTRUCT THE PROJECT.

NO TREES ARE TO BE REMOVED WITHOUT APPROVAL FROM CITY ENGINEER.

522-2 INCLUDES COST OF WATER VALVE ADJUSTMENTS AND OTHER UTILITY ADJUSTMENTS

570-1-2 VERTICAL ROOT SOD (BAHIA)

700-1-111 INCLUDES TWO (2) "HANDICAP" SIGNS, FOUR (4) "COMPACT CAR PARKING ONLY" SIGNS

Please note that the proposal opening date and time remains December 16, 2025 @ 3:00 P.M.

All other terms and conditions remain unchanged.

Sincerely, Corey McMillen, CPPB Purchasing Manager

END OF ADDENDUM #2

Sperling Sports Complex Parking Improvements
B-26-03
December 11, 2025
Addendum #2
TO ALL PROSPECTIVE CONTRACTORS
CLARIFICATION TO QUESTIONS ASKED RECEIVED:

File details come from the government source that posted it. Updated .