B08_SOL_Attachment_2_Group_2_Sample_Project_1__SOW.docx
DOCX document 676 KB Posted
- Attached to
- NPS Electrical Services IDIQ-JOC
- Solicitation number
- 140D0426R0073
About this file
This is a Statement of Work (SOW) attachment for a sample project under the NPS Electrical Services IDIQ-JOC solicitation. The document provides project specifications and requirements for electrical services work to be performed at National Park Service facilities within the National Capital Region. The SOW outlines the scope of work, performance standards, deliverables, and technical requirements that contractors must follow when executing task orders issued under the resultant IDIQ contracts.
The sample project SOW establishes baseline expectations for minor construction commercial electrical services, including maintenance, repair, installation, and emergency response work. It details specific performance metrics, quality assurance standards, safety requirements, and coordination procedures contractors must implement. The document serves as a reference example demonstrating the format and level of detail contractors can expect in actual task order SOWs, helping bidders understand the nature and complexity of electrical services required across NPS facilities. This attachment is intended to clarify the type and scope of work that will be ordered under the five-year IDIQ contract vehicles being solicited, with work to be performed in compliance with federal standards and NPS operational requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_SOL_Attachment_8__Q_A_Template.xlsx | XLSX spreadsheet | |
| B08_SOL__Attachment_1_IDIQ-JOC__Statement_of_Work_(SOW).docx | DOCX document | |
| B08_SOL_Attachment_4__Designated_Park_Groups.xlsx | XLSX spreadsheet | |
| B08_SOL_Attachment_5_Coefficient__Spreadsheet.xlsx | XLSX spreadsheet | |
| B08_SOL_Attachment_6_No_Conflict_of_Interest_Certificate.pdf | ||
| B08_SOL_Attachment_3__Group_1_Sample_Project_2_SOW.pdf | ||
| Sol_140D0426R0073.pdf | ||
| B08_SOL_Attachment_7_Non-Disclosure_Agreement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
National Capital Region
Parking Lot Lighting Repairs
Task Order
Statement of Work
NATIONAL PARK SERVICE HISTORIC PRESERVATION TRAINING CENTER
1.0 GENERAL
The National Capital Region (NCR) is the administrative hub for dozens of park units, historic sites, and natural areas in and around the Washington, D.C. metropolitan area. The Headquarters Office Building is located at 1100 Ohio Drive SW, Washington, DC 20242.
2.0 PURPOSE AND BACKGROUND
This project entails troubleshooting and repairing the inoperable parking lot lights that serve the Headquarters Office Building located at 1100 Ohio Drive SW, Washington, DC 20242. Park reports that the underground raceway and conductors have been cut inadvertently at some point with an excavator causing 10 light pole fixtures to be inoperable. The purpose of this task order is to restore the power to the 10 parking lot lights and replace light bulbs with new bulbs at each fixture.
3.0 SCOPE OF WORK
The Contractor shall perform all tasks necessary to deliver a fully functional parking lot lighting system:
3.1 Electrical Site Investigation and Troubleshooting
The Contractor shall inspect and troubleshoot current existing condition and determine what repairs need to be made and document findings.
3.2 Underground electrical repairs
The Contractor shall locate precisely where conduit needs to be excavated and confirm if other utilities are present by using locating services prior to excavation work.
3.3 Excavation and repair
The Contractor shall excavate area where conduit and wire damage has occurred. Remove failed conductors and if underground conduit is compromised and replace per the National Electrical Code (NEC), install new conductors, conduit, and restore power to light poles per (NEC). No conductor splices will be allowed in the conduit. All splices, if necessary, must be terminated in an enclosure. If excavation is required within the critical root zone of any tree, then a contractor provided certified arborist must be present during excavation.
3.4 Site Restoration
The Contractor shall backfill, compact, and restore disturbed surfaces to match existing conditions. The Contractor shall replace to match existing in areas that contain grass, flowers, plants or other vegetation, conditions.
3.5 Replace light bulbs
The Contractor shall replace 10 light bulbs in the NPS identified light poles.
4.0 SAFETY
All work shall comply with OSHA 29 CFR Part 1926, NPS Director’s Order 50B, MUTCD, and applicable codes.
5.0 GOVERNMENT-FURNISHED INFORMATION
Limited utilities and existing documentation as available and by request.
6.0 ADDITIONAL CONTRACTOR REQUIREMENTS
The Contractor shall designate on-site supervisor, maintain work logs, and provide a one-year warranty.
7.0 WORK CONDITIONS AND LIMITATIONS
The Contractor shall coordinate work to minimize visitor disruption in a high-visibility public setting.
8.0 PERIOD OF PERFORMANCE
Work shall begin within 10 days of Notice to Proceed and be completed by determined date.
9.0 HOURS OF OPERATION
Normal business hours unless otherwise approved.
10.0 ROLE OF GOVERNMENT PERSONNEL
Only the Contracting Officer may modify the contract; the COR provides technical oversight.
11.0 INVOICING
Invoices shall be submitted through the Department of Treasury Invoice Processing Platform (IPP).
12.0 ATTACHMENTS
Site map image1.png image2.png