B08_Pricing_Sheet.xlsx
XLSX spreadsheet 1 MB Posted
- Attached to
- FORESTRY STEWARDSHIP IDIQ, OREGON Federal contract opportunity
- Solicitation number
- 140L4326R0009
About this file
This is a Pricing Sheet for a 10-year Indefinite Delivery/Indefinite Quantity (IDIQ) forestry stewardship contract with the Bureau of Land Management Oregon-Washington, running from August 31, 2026 through August 30, 2036. The pricing sheet provides estimated annual work quantities and unit prices across three geographic regions: South, North, and East.
The contract covers 27 line items for forestry and road maintenance services organized into two primary categories. Forestry services include ground-based and cable/tethered logging, mechanical and manual brushing and thinning, mechanical cut and pile operations, grinding/chipping and hauling, blow-down tree clearing, individual tree removal and retention, snag creation, and manual hand piling, with quantities measured in acres (AC) or individual trees (EA) and tons (TN). Road-related services encompass grading and maintenance, spot rocking, temporary/primitive road building, culvert installation/removal, road brushing, full decommission, barricade installation, slide removal, and snow plowing, measured in miles (MI) or cubic yards (CY). Unit prices and estimated annual work volumes vary significantly by region and service type, with some items showing substantial variation across regions (for example, mechanical brushing ranges from 100 units in the North to 3,000 units in the South). The pricing structure remains consistent across all 10 contract years with identical quantities and unit prices, though the coversheet notes that the Government may still consider offerors who cannot cover all geographic areas, though comprehensive coverage will be evaluated more favorably.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L4326R0009_Amd_0003.pdf | ||
| Sol_140L4326R0009_Amd_0002.pdf | ||
| Sol_140L4326R0009_Amd_0001.pdf | ||
| B03_SCLS_Wage_Determination_1977-0079.pdf | ||
| Sol_140L4326R0009.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Coversheet
| If an offeror cannot cover all areas, the Government may still consider the offeror for award. | ||
| Year 1 | 08/31/2026 – 08/30/2027 | The Government will evaluate an offer that can cover all areas more favorably. |
| Year 2 | 08/31/2027 – 08/30/2028 | |
| Year 3 | 08/31/2028 – 08/30/2029 | |
| Year 4 | 08/31/2029 – 08/30/2030 | |
| Year 5 | 08/31/2030 – 08/30/2031 | |
| Year 6 | 08/31/2031 – 08/30/2032 | |
| Year 7 | 08/31/2032 – 08/30/2033 | |
| Year 8 | 08/31/2033 – 08/30/2034 | |
| Year 9 | 08/31/2034 – 08/30/2035 | |
| Year 10 | 08/31/2035 – 08/30/2036 |
Year 1
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 2
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 3
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 4
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 5
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 6
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 7
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 8
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 9
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |
Year 10
| South | North | East | ||||||
| Item # | Schedule A- Services | Units | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price | Estimated Annual Work | Unit Price |
| 1 | Ground-Based Logging | AC | 1500 | 750 | 1500 | |||
| 2 | Cable/Tethered Logging | AC | 3000 | 1100 | 100 | |||
| 3 | Mechanical Brushing (Mow, Slashbust) | AC | 3000 | 100 | 1000 | |||
| 4 | Mechanical Cut & Pile | AC | 1500 | 400 | 500 | |||
| 5 | Mechanical Piling | AC | 750 | 200 | 100 | |||
| 6 | Mechanical Grind/Chip and Haul | TN | 10000 | 5000 | 10000 | |||
| 7 | Blow down tree clearing | EA | 1500 | 500 | 200 | |||
| 8 | Blow down tree clearing | MI | 50 | 25 | 2 | |||
| 9 | Individual Tree Cut and Remove | EA | 2000 | 500 | 500 | |||
| 10 | Individual Tree Cut and Remove | MI | 50 | 25 | 5 | |||
| 11 | Individual Tree Cut and Leave | EA | 2000 | 500 | 300 | |||
| 12 | Manual Thinning | AC | 2000 | 500 | 600 | |||
| 13 | Manual Hand Piling | AC | 1000 | 500 | 300 | |||
| 14 | Manual Brushing | AC | 1000 | 500 | 300 | |||
| 15 | Snag Creation-Climb and Top | EA | 200 | 1000 | 1 | |||
| 16 | Snag Creation-Girdling | EA | 500 | 5000 | 1 | |||
| 17 | Grading Road Surface & Shoulders | MI | 100 | 100 | 10 | |||
| 18 | Road Maintenance (grading, ditching,culvert cleaning, brushing) | MI | 100 | 250 | 25 | |||
| 19 | Spot Rocking with Contractor supplied rock | CY | 5000 | 4000 | 5000 | |||
| 20 | Spot Rocking with BLM supplied rock | CY | 1000 | 2000 | 1000 | |||
| 21 | Temporary/Primitive Road Building | MI | 30 | 20 | 5 | |||
| 22 | Culvert Installation/Removal | EA | 60 | 200 | 5 | |||
| 23 | Road Brushing | MI | 200 | 200 | 50 | |||
| 24 | Road Full Decommission | MI | 200 | 200 | 1 | |||
| 25 | Barricade Roads (Natural Barriers) | EA | 50 | 50 | 10 | |||
| 26 | Slide Removal | CY | 1000 | 1000 | 1 | |||
| 27 | Snow Plowing | MI | 60 | 30 | 10 |