B08_NIFC_300-JWH_-_Bid_Schedule_28FEB2025.pdf
PDF 96 KB Posted
- Attached to
- NIFC 300 JWH MPR Suite Federal contract opportunity
- Solicitation number
- 140L3725R0004
About this file
This document is a Bid Schedule for the NIFC 300-JWH MPR NICC Renovation and Repair project. The bid schedule is structured into two main sections: Multi-Purpose Room (MPR) Renovation and National Interagency Coordination Center (NICC) Renovation. Each section includes line items for various construction and renovation activities such as mobilization, construction management, select demolition, architectural work, HVAC, electrical and IT/COM services, fire suppression, and plumbing. The document provides a template for contractors to fill in quantities, unit costs, and total costs for each line item, with subtotals for each renovation section and a combined total at the bottom, allowing for detailed and itemized bidding on the comprehensive renovation project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L3725R0004_Amd_0005.pdf | ||
| Sol_140L3725R0004_Amd_0004.pdf | ||
| Sol_140L3725R0004_Amd_0003.pdf | ||
| NIFC_300-JWH_NICC_Drawings_R1_11x17_20250603_0003.pdf | ||
| NIFC_300-JWH_MPR_Drawings_R1_11x17_20250603_0003.pdf | ||
| NIFC_300-JWH_MPR_Specs_R1_20250602_0003.pdf | ||
| NIFC_300-JWH_NICC_Spec_R1_20250602_0003.pdf | ||
| Sol_140L3725R0004_Amd_0002.pdf | ||
| Sol_140L3725R0004_Amd_0001.pdf | ||
| A06_NIFC_300-JWH_-_NICC_Specs.pdf | ||
| A06_NIFC_300-JWH_-_MPR_Specs.pdf | ||
| B03_Wage_Determination_ID20250104_03-07-2025.pdf | ||
| SF1442_Example_Completion-Instructions-Reference.pdf | ||
| A06_NIFC_300-JWH_-_Supplemental_Info.pdf | ||
| A06_NIFC_300-JWH_-_MPR_Plans.pdf | ||
| A06_NIFC_300-JWH_-_NICC_Plans.pdf | ||
| Sol_140L3725R0004.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item No. Description Quantity Unit Unit Cost Total Cost
1 Multi‐Purpose Room Renovation (MPR)
1A Mobilization and Construction Management $ $
1B Select Demolition $ $
1C Architectural ‐ Openings, Finishes, and Specialties $ $
1D HVAC $
1E Electrical and IT/COM $
Subtotal $
2 National Interagency Coordination Center (NICC) Renovation
2A Mobilization and Construction Management
2B Select Demolition
2C
Architectural ‐ Metals, Thermal & Moisture, Openings, Finishes, Specialties, Furnishings
2D Fire Suppression
2E Plumbing
2F HVAC
2E Electrical and IT/COM
2G Bid Alternate A
Subtotal $
Combined TOTAL $