This document is a bid schedule for a federal construction project to install new underfloor return air ductwork at a Department of the Interior Fish and Wildlife Service facility in Wisconsin. The base bid work includes designing and installing two insulated ductwork trunks with laterals in the office foundation crawl space to replace existing wall returns, avoiding existing floor structure and installing new return air locations as proposed. Ductwork will be tested and balanced to compare to pre-existing return air flow. Existing wall air returns will be modified as well. The solicitation number is provided for reference.

View the file

Other files for this federal contract opportunity

Other files attached to WI LEOPOLD WMD HVAC, newest first.
File Type Posted
A06-Crawlspace_piping_to_water_softener_photo.JPG JPG image
B08-Table_of_Contents.pdf PDF
Wage_Determination.pdf PDF
A06-UTILITY_ROOM_RELOCATES_Model_drawing.pdf PDF
A06-Foundations_Drawing.pdf PDF
A06-Return_air_box-typical_photo.JPG JPG image
B08-Pre-Con_Safety_FWS_Form_3-2199_(5-03).pdf PDF
A06-Furnace_2_photo.JPG JPG image
B08-Submittals_Report.pdf PDF
A06-Test_Report_22-02-16_ESA_T_B_report.pdf PDF
A06-Specifications.pdf PDF
B08-York_Submittal.pdf PDF
A06-Drawing_EXISTING-Proposed_HVAC_PAGE.pdf PDF
A06-Furnance_1_photo.JPG JPG image
A06-Crawl_space_area_photo_example.JPG JPG image
Sol_140FC223Q0035.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STANDARD FORM 36, JULY 1966 REF NO OF DOC BEING CONT'D PAGE 1 OF 1

GENERAL SERVICES ADMINISTRATION

FED PROC. REG. (41 CFR) 1-16.101

NAME OF OFFEROR OR CONTRACTOR

BID SCHEDULE

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Furnish all labor, tools, equipment, materials, superintendence and transportation necessary to construct the project in accordance with the Technical Specifications, Drawings, and terms and conditions contained herein as follows:

SCHEDULE 1

1-1 The Base Bid work includes but is not limited to: 1 LS

Designing and installing two underfloor return air insulated ductwork trunks, with laterals, in the office foundation crawl space which will replace the existing two wall returns. Ductwork trunks/laterals will be installed to avoid existing floor structure/framing members which are covered with insulation/barrier. Floor return locations will be proposed by bidder. Return air flow will be tested/balanced and compared to pre-existing return air flow. Existing wall air returns will be modified as noted.