This document is a Contract Data Requirements List (CDRL) that specifies 23 data deliverables for a federal contract involving the production of various signals and illumination products. The contracting entity is listed as "Multiple" under contract number designation, with the requiring office being AMIM-QA and various other Army and Joint Munitions Command offices.

The CDRL encompasses comprehensive quality and production documentation requirements across multiple data item categories. Key deliverables include: Quality Program Plan (150 calendar days post-award), Critical Characteristics Control Plan (120 days), Critical Plan of Action (as required), Notification of Critical Non-Conformance Reports (within 24 hours of defect occurrence), Critical Defect Investigation Reports (as required with 3-business-day response timelines), Statistical Process Control plans (150-200 days), Measurement System Evaluation documentation (120 days), First Article Qualification Test Plans (120 days), and First Article Test Reports (270 days). Additional requirements include Lot Acceptance Test Reports (30 days after test completion), Ammunition Data Cards prepared per MIL-STD-1168, 2-D Bar Code Label Verification samples, Management Plans for bar code labeling, Failure Summary and Analysis Reports (10-30 calendar days), Contractual Baseline Reports submitted semi-annually, Test Procedures for phosphate coating (60 days pre-production), Government Furnished Material consumption reports (monthly, beginning 30 days after production commencement), Production and Shipping Progress Reports (monthly), Engineering Change Proposals, Notices of Revision, Requests for Variance, and an Operations Security Plan. Distribution of most documents goes to the Procuring Contracting Officer (PCO) and Product Quality Manager (PQM), with submission methods including email and the SAFE (Secure Access File Exchange) system at https://safe.apps.mil/. Documents must be in government-compatible software formats (Microsoft Office or PDF). Approval requirements are mandated prior to First Article Testing or production initiation for most quality-related deliverables.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

G. PREPARED BY

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

A001

Stuart Handley

1 Sept 22

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

A002

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

A003

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

A004

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A005

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sept 22

A006

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

A007

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

A008

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

A009

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A010

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A011

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A012

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A013

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A014

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A015

(1 Data Item)

16. REMARKS

C. CATEGORY:

TDP ________ TM _______ OTHER _________________________

Form Approved OMB No. 0704-0188

15. TOTAL

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, AUG 96 (EG) Page ____ of ____ Pages

A. CONTRACT LINE ITEM NO. B. EXHIBIT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

H. DATE J. DATEI. APPROVED BY

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

Designed using Perform Pro, WHS/DIOR, Aug 96

1 Sep 22

A016

(1 Data Item)

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for information Operations and reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project, (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM

VARIOUS SIGNALS, ILLUM

E. CONTRACT/ PR NO.

MULTIPLE

F. CONTRACTOR

1. DATA ITEM NO.

A017

2. TITLE OF DATA ITEM

REQUEST FOR VARIANCE (RFV)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Documentation No.)

DI-SESS-80640D

5. CONTRACT REFERENCE

SECTION C SOW

6. REQUIRING OFFICE

FCDD-ACE-SP

7. DD 250 REQ. 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

LT * ASREQ ASREQ b. COPIES

8. APP CODE 11. AS OF DATE 13. DATE OF

SUBSEQUENT

SUBMISSION

a. ADDRESSEE Draft

Final Reg Repro

N/A N/A ASREQ

16. REMARKS: ACO 0 1 0

PCO 0 1 0

DATA MUST BE IN GOVERNMENT COMPATIBLE SOFTWARE (i.e., MICROSOFT OFFICE OR PORTABLE DOCUMENT FORMAT (pdf)).

*DISTRIBUTION STATEMENT WILL BE ASSIGNED AND IMPLEMENTED BY

THE DOD CONFIGURATION CONTROL AUTHORITY. DISTRIBUTION

STATEMENT SHOULD BE THE HIGHEST LEVEL OF THE DRAWINGS.

DISTRIBUTION STATEMENT A IS THE LOWEST. FOR EXAMPLE, IF THE

DOCUMENT HAS A DISTRIBUTION STATEMENT A AND D DRAWING,

THEN THE WHOLE SUBMITTAL WILL BE LABELED "D".

THE PREFERRED METHOD FOR SUBMITTAL IS DD FORM 1694 LOCATED

AT www.dtic.mil/whs/directives/infomgt/forms/. SUBMIT ELECTRONICALLY TO usarmy.pica.devcom-ac.mbx.ecp-document@army.mil; COPY FURNISH

THIS SUBMITTAL TO THE GOVERNMENT CONTRACTING OFFICE.

15. TOTAL 0 2 0

G. PREPARED BY

Steven Carpenter for SDMO, FCDD-ACE-SP

H. DATE

09/14/2022

I. APPROVED BY J. DATE

DD FORM 1423-1 FEB 2001 PREVIOUS EDITIONS MAY BE USED. Page 1 of 7 Pages http://www.dtic.mil/whs/directives/infomgt/forms/

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for information Operations and reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project, (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM

VARIOUS SIGNALS, ILLUM

E. CONTRACT / PR NO.

MULTIPLE

F. CONTRACTOR

1. DATA ITEM NO.

A018

2. TITLE OF DATA ITEM

ENGINEERING CHANGE PROPOSAL (ECP)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Documentation No.)

DI-SESS-80639D

5. CONTRACT REFERENCE

SECTION C SOW

6. REQUIRING OFFICE

FCDD-ACE-SP

7. DD 250 REQ. 9. DIST 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

STATEMENT

LT REQUIRED ASREQ ASREQ b. COPIES

8. APP CODE 11. AS OF DATE 13. DATE OF

SUBSEQUENT

SUBMISSION

a. ADDRESSEE Draft Final

Reg Repro

N/A N/A ASREQ

16. REMARKS: ACO 0 1 0

PCO 0 1 0

DATA MUST BE IN GOVERNMENT COMPATIBLE SOFTWARE (i.e., MICROSOFT OFFICE OR PORTABLE DOCUMENT FORMAT (pdf)).

*DISTRIBUTION STATEMENT WILL BE ASSIGNED AND IMPLEMENTED BY

THE DOD CONFIGURATION CONTROL AUTHORITY. DISTRIBUTION

STATEMENT SHOULD BE THE HIGHEST LEVEL OF THE DRAWINGS.

DISTRIBUTION STATEMENT A IS THE LOWEST. FOR EXAMPLE, IF THE

DOCUMENT HAS A DISTRIBUTION STATEMENT A AND D DRAWING, THEN

THE WHOLE SUBMITTAL WILL BE LABELED "D".THE PREFERRED METHOD

FOR SUBMITTAL IS DD FORM 1692 LOCATED AT https:// www.dtic.mil/whs/directives/infomgt/forms/. SUBMIT ELECTRONICALLY TO usarmy.pica.devcom-ac.mbx.ecp-document@army.mil; COPY FURNISH THIS

SUBMITTAL TO THE GOVERNMENT CONTRACTING OFFICE.

15. TOTAL 0 2 0

G. PREPARED BY

Steven Carpenter for SDMO, FCDD-ACE-SP

H. DATE

09/14/2022

I. APPROVED BY J. DATE

DD FORM 1423-1 FEB 2001 PREVIOUS EDITIONS MAY BE USED. Page 2 of 7 Pages

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for information Operations and reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project, (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM

VARIOUS SIGNALS, ILLUM

E. CONTRACT / PR NO.

MULTIPLE

F. CONTRACTOR

1. DATA ITEM NO.

A019

2. TITLE OF DATA ITEM

NOTICE OF REVISION (NOR)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Documentation No.)

DI-SESS-80642D

5. CONTRACT REFERENCE

SECTION C SOW

6. REQUIRING OFFICE

FCDD-ACE-SP

7. DD 250 REQ. 9. DIST 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

STATEMENT

REQUIRED

LT * ASREQ ASREQ b. COPIES

8. APP CODE 11. AS OF DATE 13. DATE OF Final SUBSEQUENT a. ADDRESSEE Draft Reg Repro

SUBMISSION

N/A N/A ASREQ

16. REMARKS: ACO 0 1 0

PCO 0 1 0

DATA MUST BE IN GOVERNMENT COMPATIBLE SOFTWARE (i.e., MICROSOFT OFFICE OR PORTABLE DOCUMENT FORMAT (pdf)).

*DISTRIBUTION STATEMENT WILL BE ASSIGNED AND IMPLEMENTED BY

THE DOD CONFIGURATION CONTROL AUTHORITY. DISTRIBUTION

STATEMENT SHOULD BE THE HIGHEST LEVEL OF THE DRAWINGS.

DISTRIBUTION STATEMENT A IS THE LOWEST. FOR EXAMPLE, IF THE

DOCUMENT HAS A DISTRIBUTION STATEMENT A AND D DRAWING, THEN

THE WHOLE SUBMITTAL WILL BE LABELED "D". THE PREFERRED

METHOD FOR SUBMITTAL IS DD FORM 1695 LOCATED AT https:// www.dtic.mil/whs/directives/infomgt/forms/. SUBMIT ELECTRONICALLY TO usarmy.pica.devcom-ac.mbx.ecp-document@army.mil; COPY FURNISH THIS

SUBMITTAL TO THE GOVERNMENT CONTRACTING OFFICE.

15. TOTAL 0 2 0

G. PREPARED BY

Steven Carpenter for SDMO, FCDD-ACE-SP

H. DATE

09/14/2022

I. APPROVED BY J. DATE

DD FORM 1423-1 FEB 2001 PREVIOUS EDITIONS MAY BE USED. Page 3 of 7 Pages

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for information Operations and reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project, (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM

VARIOUS SIGNALS, ILLUM

E. CONTRACT / PR NO.

MULTIPLE

F. CONTRACTOR

1. DATA ITEM NO.

A020

2. TITLE OF DATA ITEM

Operations Security (OPSEC) Plan

3. SUBTITLE

4. AUTHORITY (Data Acquisition Documentation No.)

DI-MGMT-80934C

5. CONTRACT REFERENCE

OPSEC SOW

6. REQUIRING OFFICE

AMSJM-FP/G2

7. DD 250 REQ. 9. DIST 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

STATEMENT

REQUIRED

XX D ONE/R ASREQ b. COPIES

8. APP CODE 11. AS OF DATE 13. DATE OF Final SUBSEQUENT a. ADDRESSEE Draft Reg Repro

A ASREQ SUBMISSION

ASREQ

16. REMARKS: JMC OPSEC 0 1 0

PCO 0 1 0

DELETE REFERENCE 'APPLYING OPSEC TO U.S. GOVERNMENT

CONTRACTS'. REPLACE WITH REFERENCE 'SAMPLE ACQUISITIONS

OPSEC PLAN'. 10 CALENDAR DAYS REQUIRED FOR GOVERNMENT

REVIEW AND APPROVAL. 30 CALENDAR DAYS AFTER THE

CONTRACTING OFFICER PROVIDES THE LIST OF KNOWN CRITICAL

INFORMATION (CI)/THREAT INFORMATION. RESUBMIT 10

CALENDAR DAYS AFTER GOVERNMENT REVIEW. SUBMIT

ELECTRONICALLY TO usarmy.ria.jmc.mbx.OPSEC-FD@mail.mil.

15. TOTAL 0 2 0

G. PREPARED BY

Steven Carpenter for SDMO, FCDD-ACE-SP

H. DATE

09/14/2022

I. APPROVED BY J. DATE

DD FORM 1423-1 FEB 2001 PREVIOUS EDITIONS MAY BE USED. Page 4 of 7 Pages mailto:usarmy.ria.jmc.mbx.OPSEC-FD@mail.mil

CONTRACT DATA REQUIREMENTS LIST Form Approved OMB No. 0704-0188 (1 Data Item)

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM

VARIOUS SIGNALS, ILLUM

E. CONTRACT /

PR NO. MULTIPLE

F. CONTRACTOR

1. DATA ITEM NO.

A021

3. SUBTITLE 17. PRICE

GROUP

2. TITLE OF DATA ITEM

TEST PROCEDURE-PHOSPHATE COATING PRE-PRODUCTION PROCEDURE

5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

TOTAL PRICE

4. AUTHORITY (Data Acquisition Document No.)

DI-NDTI-80603A TT-C-490, TYPE 1, PARAS 3.2.1, 3.2.2 FCDD-ACE-QP

7. DD 250 REQ

9. DIST

STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

XX ONE/R ASREQ

a. ADDRESSEE

b. COPIES

8. APP CODE N/A

11. AS OF DATE

13. DATE OF SUBSEQUENT SUBMISSION

Draft

Final

Reg Repro A N/A N/A

16. REMARKS

SUBMIT PROCEDURE FOR APPROVAL 60 DAYS PRIOR TO FIRST ARTICLE TEST OR PRODUCTION IF FIRST

ARTICLE IS NOT APPLICABLE. ALLOW 28 DAYS FOR APPROVAL/DISAPPROVAL THROUGH THE

CONTRACTING OFFICER. SUBMIT ELECTRONICALLY TO mark.a.godlewski.civ@army.mil. CONTRACTOR SHALL RESUBMIT WITH GOVERNMENT REVISIONS WITHIN 10 DAYS. FCDD-ACE-QP SHALL PROVIDE PROCEDURE REVIEW RESPONSE BACK TO CONTRACTING OFFICER. COATED PANELS PER PARA 3.2.2 SHALL INCLUDE THREE WITH PHOSPHATE ONLY, THREE WITH PHOSPHATE AND PRIMER, AND THREE

WITH PHOSPHATE, PRIMER AND TOP COAT. A DD FORM 250 IS NOT REQUIRED FOR PHOSPHATE

COATING PROCEDURAL APPROVAL. CONTRACTOR FORMAT ACCEPTABLE. WRITTEN PROCEDURES

SHALL BE SUBMITTED USING A PC COMPATIBLE FORMAT (I.E. PDF, RICH TEXT FORMAT (RTF), OR WORD

FILE).

THE PANELS SHALL BE MAILED TO THE

FOLLOWING ADDRESS:

Combat Capabilities Development Command Armaments Center Attn: FCDD-ACE-QP/Mark Godlewski 1 Rock Island Arsenal Bldg. 62 2nd Floor, NW Wing Rock Island, IL 61299-7300

FCDD-ACE-QP 0 1 0

15. TOTAL

G. PREPARED BY

Steven Carpenter for SDMO

FCDD-ACE-SP

H. DATE

09/14/2022

I. APPROVED BY

Drew Smith, FCDD-ACE-SC

J. DATE

DD Form 1423-1, FEB 2001 Previous editions may be used. Page: 5 of 7

12 May 2021 mailto:team@mail.mil

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

E. CONTRACT / PR NO.

MULTIPLE

F. CONTRACTORD. SYSTEM/ITEM

VARIOUS SIGNALS, ILLUM

1. DATA ITEM

NO. A022

2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE

GROUP

GOVERNMENT FURNISHED MATERIEL (GFM) CONSUMPTION REPORT CONSUMPTION REPORT

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE

FAR PART 45

6. REQUIRING OFFICE

JMC MLRC

18. ESTIMATED

TOTAL PRICE

DI-MGMT-80438B

7. DD 250 REQ

9. DIST

STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

NO MTHLY ASREQ b. COPIES

8. APP CODE N/A 11. AS OF DATE

13. DATE OF SUBSEQUENT SUBMISSION a. ADDRESSEE

Draft

Final

Reg Repro N/A N/A

ASREQ

16. REMARKS PRODUCTION MANAGER 0 1 0

PCO 0 1 0

DUE TO BEGIN 30 DAYS AFTER PRODUCTION COMMENCES

FREQUENCY: 3 WORKING DAYS FOLLOWING REPORTING MONTH

SHALL BE SUBMITTED IN ELECTRONIC FORMAT AND INCLUDE AT A MINIMUM:

DESCRIPTION/NSN OF GFM

TOTAL OF GFM REQUIRED VS. TOTAL DELIVERED AS OF THE CURRENT MONTH

RECEIPTS: CUMULATIVE VS. CURRENT MONTH

CONSUMED: CUMULATIVE VS. CURRENT MONTH

REJECTED/DAMAGED MATERIAL: LOT NUMBERS AND SERIAL NUMBERS OF GFM

LAP CLINS: CONTRACT QUANTITY VS. DELIVERED QUANTITY

THIS INFORMATION SHOULD BE PROVIDED FOR EACH DELIVERY ORDER

SUBMIT ELECTRONICALLY TO THE PCO, OTHER DISTRIBUTION WILL BE DISCUSSED AFTER AWARD OF

REQUIREMENT.

FORMAT AND CONTENT WILL BE APPROVED THROUGH PCO

15. TOTAL 0 2 0

H. DATE I. APPROVED BY J. DATE G. PREPARED BY

Steven Carpenter for SDMO, FCDD-ACE-SP

09/14/2022

DD Form 1423-1, FEB 2001 Previous editions may be used. Page: 6 of 7

DD FORM 1423-1, FEB 2001

(1 Data Item)

PREVIOUS EDITION MAY BE USED.

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP ________ TM _______ OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15. TOTAL

16. REMARKS

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

Page of Pages

PRODUCTION/SHIPPING PROGRESS REPORT PRODUCTION/SHIPPING STATUS REPORT

DI-MGMT-81255 TBD AMJM-SPG

NO

N/A N/A

MONTHLY

N/A

ASREQ*

MONTHLY**

***POC's

0 0 0

*30 Days prior to production commencement to include CLINs that are contractually scheduled to be produced with a rolling 12 Month period.

**10th working day of each month. Submit Production/Shipping Progress Report on the provided spreadsheet. Production Progress data will include CLIN level information, such as: DODIC, Model/Nomenclature, Delivery Order, CLIN, MILSTRIP, Ship To Address (DODAAC), MILSTRIP QTY, and Actual Schedule for a rolling 12 Month period.

Shipping progress data will include DODIC, Model/Nomenclature, Delivery Order, CLIN, DD250/Shipment Number, Lot Number, MILSTRIP, Ship To Address (DODAAC), Shipment QTY, DD250 Date, Shipment Request/SIR Submit and Sign Date. Submit electronically to the POC's identified in block 14a.

***Distribution list will be provided after each delivery order award.

Adobe Professional 8.0

A023

QA CDRL Distribution block - IPT members list Distribution with specific contact information will be provided at Post Award

PQM – Product Quality Manager

PCO – Procuring Contracting Officer

CS – Contract Specialist

QAR – Quality Assurance Representative

PO or PM – Project Officer or Project Manager

AQE – Army Quality Engineer

APO - Army Lead Engineer (Project Officer)

DA – Design Agent (NAVSEA)

PL – Project Lead (NAVAIR)

NQA – Navy Quality Assurance

ME – Material Engineer (NAVAIR)

PE – Program Engineer (Air Force)

AEA – Acquisition Engineering Agent (NAVSEA) GE – Gage Engineer

Production Manager, JMC - Production Manager, Joint Munitions Command

MCEA – Marine Corp Engineering Activity

CDM – Configuration/Data Management (NAVAIR)

WARP - Worldwide Ammunition-Data Repository Program

SAFE - Safe Access File Exchange

FOR GOVERNMENT PERSONNEL FOR THE CONTRACTOR

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM -

Technical Manual; Other - other category of data, such as

"Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award). Item F. Self-explanatory (to be filled in after contract award). Item G. Signature of preparer of

CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the

Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items

12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data. These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required.

The estimated data prices shall not include any amount for rights in data. The

Government's right to use the data shall be governed by the pertinent provisions of the contract.

DD FORM 1423 (BACK)

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the

Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

a. Group I. Definition - Data…