B08_ATTACHMENT_B_Price_Schedule.xlsx

XLSX spreadsheet 34 KB Posted

Attached to
Perform Park-wide Cross Connection Survey, Cross C
Solicitation number
140P8126Q0008
Issued by

About this file

This is a price schedule attachment containing cost estimates for two separate federal projects at Death Valley National Park, prepared by the National Park Service.

The first estimate addresses door replacement work totaling $440,844 in net construction costs. The base scope includes documents/project meetings/mobilization ($34,814), replacement of visitor center storefront double doors ($19,190), and replacement of visitor center storefront single doors ($32,995). Nine optional line items are available, including replacement of steel double doors ($25,025), steel single doors ($53,052), installation of ABAS automated door openers ($11,249), utility door replacement ($21,221), hacienda door hanging ($9,250), and installation of an ABAS door with automated opener in a gas tank house ($14,860). The estimate incorporates material costs ($131,868), labor costs with an 18.61% federal wage rate factor ($88,438), equipment costs ($1,350), location factor adjustment of 3.9%, remoteness factor of 6.9%, design contingency of 10%, general conditions at 7-5%, historic preservation factor of 10%, overhead and profit at 6.5% each, contracting method markup of 10%, and 8.25% sales tax on materials.

The second estimate covers cross connection survey, backflow prevention testing, and minor repairs services over a five-year period with a total net construction cost of $158,525. The base year (2026) includes cross connection survey and plans ($16,180), mobilization ($5,497), backflow testing for 67 units ($9,380), and minor repairs not-to-exceed $160 per unit ($10,720). Four option years (2027-2030) include annual backflow testing with escalating labor rates ranging from $145.60 to $163.78 per unit and minor repairs with NTE amounts increasing from $175 to $220. Labor costs total $102,160 across the period at a plumber wage rate of $86.09 per hour, material costs are $23,922, equipment costs are $10,050, with 5% overhead, 10% profit, and 8.25% material sales tax applied.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Total

PMIS:246800Estimate By:Brian Aillaud
Project:Replace DoorsDate:5/6/24
Park:Death Valley National Park
Reviewed By:
Unit Prices based on RSMeans, CESS, and Past ProjectsDate:
MaterialLaborEquipmentSubcontractorTotal
Item No.DescriptionQty.UnitCost/UnitMat'l CostCost/UnitLabor CostCost/UnitEquip. CostCostCost/UnitTOTAL
1Documents, Project Meetings, and Mobilization1LS$0.00$0$34,814.29$34,814$0.00$0$34,814.29$34,814
2Replace Visitor Center Storefront Double Doors1EA$13,047.00$13,047$6,118.00$6,118$25.00$25$19,190.00$19,190
3Replace Visitor Center Storefront Single Doors2EA$14,020.50$28,041$2,452.00$4,904$25.00$50$16,497.50$32,995
4OPTION: Replace Visitor Center and Headquarters Steel Double Doors3EA$6,476.52$19,430$1,840.00$5,520$25.00$75$8,341.52$25,025
5OPTION: Replace Visitor Center and Headquarters Steel Single Doors10EA$3,924.18$39,242$1,356.00$13,560$25.00$250$5,305.18$53,052
6OPTION: Install ABAS Automated Door Openers on steel doors4EA$1,458.25$5,833$1,329.10$5,316$25.00$100$2,812.35$11,249
7OPTION: Replace Utility Doors4EA$3,924.18$15,697$1,356.00$5,424$25.00$100$5,305.18$21,221
8OPTION: Hang Hacienda Doors10EA$0.00$0$900.00$9,000$25.00$250$925.00$9,250
9OPTION: Install ABAS Door in Gas Tank House w/ automated opener1EA$10,578.50$10,579$3,781.10$3,781$500.00$500$14,859.60$14,860
10$0.00$0$0.00$0$0.00$0$0.00$0
11$0.00$0$0.00$0$0.00$0$0.00$0

Totals $131,868 $88,438 $1,350 $221,655

SUBTOTAL - Bare Costs $131,868 $88,438 $1,350 $221,655

Subtotal
Location Factor (CCI = 3.9% or PLF = 1.25%)3.9%$8,645
Remoteness Factor (1% for each 10 miles)6.9%$15,294
Federal wage rate factor (Labor only, 18.61%)18.6%$16,458$16,458
Total Direct Construction Costs$262,052
Design Contingency (Class A: 0%-10%)10.0%$26,205
Standard General Conditions (5%-20%)7.0%$18,344
Government General Conditions (5%-20%)5.0%$13,103
Historic Preservation Factor (0%-10%)10.0%$26,205
Subtotal Net Construction Cost$345,909
Overhead (5%-10%)6.5%$22,484
Profit (5%-10%)6.5%$22,484
Estimate Net Construction$390,877
Contracting Method - (5%-15%)10.0%$39,088
Inflation Escalation (1.69% per year)0.0%$0
Sales Tax - Material Only (8.25%)8.3%$10,879$10,879
TOTAL Estimated NET Construction Cost$440,844

&11Construction Cost Estimate

Page &P&11&A
Printed &D

IGE

PMIS:Estimate By:Jason Lieber
Project:Date:2/19/26
Park:Death Valley National Park
Reviewed By:
Unit Prices based on RSMeans, CESS, and Past ProjectsDate:
MaterialLaborEquipmentSubcontractorTotal
CLINDescriptionQty.UnitCost/UnitMat'l CostCost/UnitLabor CostCost/UnitEquip. CostCostCost/UnitTOTAL
10Cross Connection Survey and Plans1EA$0.00$0$16,180.00$16,180$0.00$0$16,180.00$16,180
10Mobilization1LS$5,497.00$5,497$0.00$0$0.00$0$5,497.00$5,497$21,677CLIN 10 Total
20Backflow Testing Base Year67EA$0.00$0$140.00$9,380$0.00$0$140.00$9,380
30Minor repairs NTE $16067EA$45.00$3,015$95.00$6,365$20.00$1,340$160.00$10,720$41,777Total Base Year
40Backflow Testing OY167EA$0.00$0$145.60$9,755$0.00$0$145.60$9,7552027
50Option Year 1: Minor repairs NTE $ 17567EA$50.00$3,350$100.00$6,700$25.00$1,675$175.00$11,725
60Backflow Testing OY267EA$0.00$0$151.42$10,145$0.00$0$151.42$10,1452028
70Option Year 2: Minor repairs NTE $19067EA$55.00$3,685$105.00$7,035$30.00$2,010$190.00$12,730
80Backflow Testing OY367EA$0.00$0$157.48$10,551$0.00$0$157.48$10,5512029
90Option Year 3: Minor repairs NTE $ 20567EA$60.00$4,020$110.00$7,370$35.00$2,345$205.00$13,735
100Backflow Testing OY467EA$0.00$0$163.78$10,973$0.00$0$163.78$10,9732030
110Option Year 4: Minor repairs NTE $22067EA$65.00$4,355$115.00$7,705$40.00$2,680$220.00$14,740
Totals$23,922$102,160$10,050$136,132

SUBTOTAL - Bare Costs $23,922 $102,160 $10,050 $136,132

Overhead (5%-10%)5.0%$6,807
Profit (5%-10%)10.0%$13,613
Sales Tax - Material Only (8.25%)8.3%$1,974$1,974
TOTAL Estimated NET Construction Cost$158,525
PLUMBER (Plumber, Pipefitter,
Steamfitter, Refrigeration)$86.09HR

&11Construction Cost Estimate

Page &P&11&A
Printed &D

Bid Schedule

MaterialLaborEquipmentPer Diem & MealsTravel (Mileage)
Item No.DescriptionQty.UnitCost/UnitMat'l CostCost/UnitLabor CostCost/UnitCostCost/Day/Person# PersonnelEquip. CostCost/MileMilesCostTOTAL
1Cross Connection Survey and Plans1EA$0$0$0$0$0$0
2Backflow Testing Base Year67EA$0$0$0$0$0$0
3Minor repairs NTE $ XX67EA$0$0$0$0$0$0
4Option Year 1: Backflow Testing67EA$0$0$0$0$0$0
5Option Year 1: Minor repairs NTE $ XX67EA$0$0$0$0$0$0
6Option Year 2: Backflow Testing67EA$0$0$0$0$0$0
7Option Year 2: Minor repairs NTE $ XX67EA$0$0$0$0$0$0
8Option Year 3: Backflow Testing67EA$0$0$0$0$0$0
9Option Year 3: Minor repairs NTE $ XX67EA$0$0$0$0$0$0
10Option Year 4: Backflow Testing67EA$0$0$0$0$0$0
11Option Year 4: Minor repairs NTE $ XX67EA$0$0$0$0$0$0
SUBTOTAL$0$0$0$0$0$0
Percentage
Overhead$0
Profit$0
Sales Tax - Material Only (8.25%)8.3%$0
TOTAL$0

&11Construction Cost Estimate

Page &P&11&A
Printed &D

File details come from the government source that posted it. Updated .