B08_Attachment_5_Well_House_Rehab_SOW_5-10-24.docx
DOCX document 47 KB Posted
- Attached to
- YOSE- REHAB WELL HOUSES 2/6 AND 3/7
- Solicitation number
- 140P8524R0006
About this file
This document is a Statement of Work (SOW) for the rehabilitation of Well Houses 2/6 and 3/7 in the El Portal area of Yosemite National Park. The well houses provide potable water to a 500,000-gallon water tank that distributes water to the El Portal community.
The SOW outlines the scope of work for each well house, which includes replacing all piping, valves, meters, and fittings, adding eyewash stations, replacing heating units, and upgrading the roofing and exterior. The contractor will be responsible for providing the labor, materials, and coordination necessary to complete the work in accordance with applicable codes and regulations. The period of performance is from September 3, 2024, to October 19, 2024. This procurement is set-aside for Small Business concerns, with a NAICS code of 237110 and a size standard of $45.0 million. The construction magnitude is $500,000 to $1,000,000. Proposals are due by 12:00 P.M. Pacific Standard Time on July 15, 2024.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Rehabilitate Well Houses 2/6 and 3/7 El Portal, CA Mariposa County, CA Yosemite National Park 3/1/24
1. General Information Yosemite National Park is located in central California, in the Sierra Nevada Mountain range. The park was established by Congress on October 1, 1890. The Park’s mission is to protect, preserve, and interpret the natural, cultural, and historical resources for the benefit and inspiration of present and future generations. There are over 5 million visitors annually to the Park. El Portal is an administrative area to the West of the Arch Rock entrance, which provides facilities and utilities for throughout the Park.
2. Facility Background Yosemite National Park has a series of wells, well houses, and water storage tanks that provide potable water for the entire Park. Well houses 2/6 and 3/7 are two of the well houses in the El Portal area that provide water to Tank No. 3, which is a 500,000-gallon water tank. This water tank distributes water the El Portal community including the administrative site, residents, and businesses.
EXISTING WELL HOUSE NO. 2/6
The existing well house 2/6 includes a water well located inside the well house, as well as a well located outside of the well house. The raw water is pumped through the well house in above ground piping, which includes a series of valves, check valves, sampling ports, and meters. The raw water is treated with sodium hypochlorite for disinfection. There is also a SCADA system to monitor the status of the local pumps, and the off-site well pumps and water tanks throughout the system. The existing SCADA system does not provide the capability of remote controls in any part of the system. The piping within the well house includes a mixture of brass fittings, cast iron pipe and galvanized pipe. All the piping, as well as the various fittings are very old and in need of replacement. The chemical tanks and pumps have also exceeded their life span; and need replacement. In addition, an eye wash station needs to be installed in the well house to meet the code requirements relative to the chemical storage within the building. The existing well house structure and concrete flooring are in good shape for the most part. The exterior has weathered and needs to be painted, and the roof and soffits need replacement.
EXISTING WELL HOUSE NO. 3/7
The existing well house 3/7 does not have a well located inside the building, rather there are two wells located outside of the well house. The raw water is pumped through the well house in above ground piping, which includes a series of valves, check valves, sampling ports, and meters. The raw water is treated with sodium hypochlorite for disinfection and zinc orthophosphate to inhibit corrosion. The existing roof is a cedar shake roof which is in poor condition. There is also a SCADA system to monitor the status of the local pumps, and the off-site well pumps and water tanks throughout the system. The existing SCADA system does not provide the capability of remote controls in any part of the system. The piping within the well house includes a mixture of brass fittings, cast iron pipe and galvanized pipe. All the piping, as well as the various fittings are very old and in need of replacement. The chemical tanks and pumps have also exceeded their life span; and need replacement. In addition, an eye wash station needs to be installed in the well house to meet the code requirements relative to the chemical storage within the building. The existing well house structure and concrete flooring are in good shape for the most part. The exterior has weathered and needs to be painted, and the roof needs replacement and upgraded to metal soffits and roofing material.
3. Scope of Proposed Work The scope of work for each well house is as follows:
WELL HOUSE IMPROVEMENTS
1. Well House 2/6 It is proposed to replace all the piping within the well house with new piping. All the valves, meters, pressure gauges, spigots, and fittings are to be replaced as well. In addition, unions will be provided to aid in maintenance activities. The new piping and fittings will match the existing unless there are upgrades in materials. An eyewash station is to be added as well withing the well house. A new heating unit is to be provided for temperature control. Aluminum soffits are to be installed as noted on the plans, along with some minor structural repairs. The 2-inch galvanized steel supply line from the well, and the 4-inch distribution piping from inside the well house to the outside of the well house is to be replaced with new pipe and a new valve on the distribution pipe. The interior floor, interior and exterior walls, and interior electrical panels of the well house are to be painted with an epoxy paint; color approved by the Service. No SCADA or electrical improvements are proposed as part of this project. An option item to the contract is to replace the existing well pump for Well 2. The pump for Well 2 is a 7.5 HP pump.
2. Well House 3/7 It is proposed to replace all the piping within the well house with new piping. All the valves, meters, pressure gauges, spigots, and fittings are to be replaced as well. In addition, unions will be provided to aid in maintenance activities. The new piping and fittings will match the existing except for upgrades in materials. An eyewash station is to be added as well. The existing heating unit is to be replaced and provide thermostat control. The building roof is to be replaced with a standing seam metal roof, and aluminum soffits are to be installed as noted on the plans. The 3-inch galvanized steel supply line from the well, and the 6-inch distribution piping from inside of the well house to the outside of the well house is to be replaced with new pipe and a new valve on the distribution pipe The interior floor, interior and exterior walls, and interior electrical panels of the well house are to be painted with an epoxy paint, approved by the Service. No SCADA or electrical improvements are proposed as part of this project. Option items to the contract are to replace the existing well pumps for both Well 3 and Well 7. The pump for Well 3 is a 15.0 HP pump, and the pump for Well 7 is a 5.0 HP pump.
4. Contractor Responsibilities Contractor shall provide the labor, materials, and coordination necessary to complete the Scope of Work noted in the above section. (All materials and installations shall be in accordance with the California Waterworks Standards, the California Plumbing Code, and the California Department of Public Health as applicable).
The contractor must meet and provide the following:
· Utilities approved valving plan
· Lockout Tagout (water and electric)
· Flushing and disinfection plan AWWA C-651
· Disinfection of wells AWWA C-654
· NSF 60 & 61 for materials and additives
· Temporary water permit for construction water.
· AREA RESTORATION:
All areas disturbed by the contractor shall be restored to original condition. Areas outside of the immediate work area shall not be disturbed. All waste materials shall be disposed of off-site in an approved waste receiving facility or recycling facility by the contractor.
5. Government Furnished Property, Materials & Supplies Yosemite National Park will not be providing property, materials or supplies for the subject project other than the existing well houses, as is.
6. Business Hours The contractor shall typically complete on-site work or delivery, including unloading, during normal business hours of 8:00 am to 5:00 pm, Monday through Friday, excluding weekends and Federal holidays. The contractor shall coordinate an anticipated schedule at least 30 days prior to the performance start date in addition to a specific on-site work schedule with the Contracting Officer and COR 14 days prior to performance start date. While on site, the COR may be reached by mobile phone during normal business hours.
7. Management During Normal Working Hours The contractor shall manage the total work effort in accordance with effective and efficient management principles and safe working practices to ensure safety of the public and on-time completion of this contract.
8. Safety & Environmental Compliance
· The contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), and state, local, safety, laws.
· Contractor shall comply with FAR 23 “Environment, Conservation, Occupational, Safety, and Drug Free Workplace”. The Contractor shall immediately report any accident, incident, or potentially hazardous situation to the CO and the COR. The Contractor shall adhere to all YNP work-place safety rules and policies. The Contractor shall cooperate and provide full assistance to any investigation. Failure to do so shall be deemed as grounds for termination for default of the contract. Contractor personnel and property are subject to safety inspections in the performance of this contract.
· The contractor shall comply with pertinent Environmental Protection Agency laws and regulations.
· Contractor must be licensed in the State of California to install Public Water Systems.
· Installed waterlines must pass both a pressure test and/or disinfection test per the project specifications, as applicable.
· The Park safety officer has the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten Government and contractor employees or damage to Government property.
· The contractor shall immediately report to the Contracting Officer, COR and YOSE safety officer all accidents resulting in employee injury or death or damage to property while performing this contract.
· Environmental compliance will be the responsibility of the NPS.
9. Insurance The Contractor shall be insured in accordance with the Solicitation documents. The Government is not responsible for damage to Contractor’s equipment, vehicles, tools or materials or their employees and the personal property brought on-site. The Government will not accept any liability due to contractor employee negligence.
10. Motor Vehicle & Traffic Regulations Contractor employees operating motor vehicles shall possess an appropriate, valid, driver's license. Driver and vehicle permits, licenses, registrations and proof of insurance shall be maintained in the vehicle at all times and made available upon request. Contractor employees shall comply with federal vehicle motor law requiring seat belts be worn at all times. Contractor employees shall adhere to the posted speed limits.
11. Replacement of Contractor Employee for Security Reasons The Government retains the right to request removal of the contractor’s employee(s), regardless of prior clearances.
12. Non-Payment for Additional Work Any additional contractor performed services not specified in contract, either at its own volition or at the request of an individual other than an appointed Contracting Officer, except as may be explicitly authorized in the contract, shall be performed at the financial risk of the contractor. Only an appointed Contracting Officer is authorized to bind the Government to a change in specifications, contract terms, or conditions.
13. Conflict of Interest The contractor shall not employ off-duty COR’s or other Government employees if such employment would create a conflict of interest or be contrary to the policies contained in conflict-of-interest directives.
14. Contractor Safety Plan: The contractor shall provide a Safety Plan with the proposal. The COR shall review all Safety Plans prior to the start of work or staging of supplies, equipment, or personnel on United States Government property. The contractor is solely responsible for ensuring adequate lead-time is provided to review and provide concurrence of the safety plan. The Contractor shall complete the Safety Plan in accordance with OSHA and NPS requirements. If revisions are required, the Contractor shall include them in the Safety Plan with appropriate configuration control notations (i.e. change bars and revision numbers).
15. Contractor Safety Violation Notification: Under NO circumstances are unsafe working conditions permitted. Upon notification, the contractor shall take immediate steps to correct the condition. The contractor shall immediately contact the Contracting Officer or the Contracting Officer’s Representative upon receipt of a Safety Violation Notice. Failure to correct unsafe conditions shall be cause for termination of the contract for default. In addition, costs to the Government to correct contractor safety violations shall be charged against the contractor. In accordance with Yosemite Safety Standard Operating Procedures, a copy of the Safety Concern Notice shall be placed in the permanent project and contract file and routed to the appropriate agencies for action.
16. Identification and Change of Critical Contractor Personnel: The Contractor shall submit an organizational chart displaying key personnel involved in the effort and their respective positions and disciplines. The Contractor shall immediately and expressly notify the CO of any changes in critical Contractor personnel. Critical Contractor personnel consist of all on-site supervisory personnel (i.e. superintendent, QC, or safety) and any others in a management role. The Contractor shall obtain CO approval of any proposed changes in contract personnel along with the steps taken/proposed to ensure there are no impacts to the schedule or ability to maintain performance level associated with individual responsibilities. The Contractor shall identify to the CO all subcontractors to be used, prior to signing any contract or initiating any work. The Contractor shall provide subcontractor qualifications to the CO prior to subcontractor utilization.
17. Quality Control The contractor shall establish and maintain a Quality Control Plan (QCP) to ensure the work performed conforms to the contract requirements. Paragraph 4. Contractor Responsibilities outlines the responsibilities of the contractor. The contractor’s QCP shall address methods for complying with the noted requirements and remedying any non-compliant work. The Contractor shall develop QCP and submit with proposal package. The Contractor’s QCP includes:
· Required services identified in the “Statement of Work – “Contractor Requirements”
· Contractor’s surveillance methodology
· Method and timeframe for responding to COR or customer complaints
· Progress meetings with Government stakeholders
18. Contractor’s Proposal Package The following deliverables are to be submitted with offer in response to RFQ.
· Technical approach to perform required services.
· Identification of key personnel to be responsible for the on-site work and their qualifications.
· Contractor safety plan.
· Contractor’s QCP
· Proof of Insurance–Business Liability & Workers Compensation.
19. Post Award Meeting: After the issuance of the Contract, the Contractor shall attend a post award meeting at the location specified by the CO. The purpose of the meeting shall be to review all contract requirements, information, and/or site-specific data addressed under the Contract. As directed by the CO, all on-site supervisory Contractor staff shall attend the meeting.
20. Photo Documentation: The Contractor shall prepare photo documentation as a routine component of the project’s construction. Photos shall be taken of all areas impacted by construction prior to beginning work, during work to document progress, and post-construction. Photos shall be turned in the COR within three days of being taken.
21. Changes: All changes to the contract or order must be expressly made by an authorized representative of the Contractor and a duly warranted CO of the United States. No work is authorized to begin in advanced of a properly executed contract modification.
22. Preservation of natural, cultural, and archaeological resources: No contractor shall violate any Park regulations regarding preservation of natural, cultural, and archaeological resources. Within the Park and the El Portal Administrative Site the following is prohibited: (1) Possessing, destroying, injuring, defacing, removing, digging, or disturbing from its natural state, any fish or wildlife; plants or parts or products thereof; non-fossilized and fossilized paleontological specimens, cultural or archaeological resources, or the parts thereof; and any mineral resource or cave formation or the parts thereof. (2) Walking on, climbing, entering, ascending, descending, or traversing an archaeological or cultural resource, except in designated areas and under conditions established by the superintendent. (3) Possessing, destroying, injuring, defacing, removing, digging, or disturbing a structure or its furnishing or fixtures, or other cultural or archaeological resources. These regulations are enforceable under 36 CFR Part 2.
23. Discharge into Water Resources is Prohibited: The Clean Water Act, 33 U.S.C. 1251 et. seq., prohibits any discharge of pollutants by any person into water of the U.S. without a permit. "Pollutant" refers to soil sediments, solid waste, chemical or biological materials or even water that is at a different temperature than the receiving body of water. "Person" is broadly defined to include individuals, corporations, partnerships, associations, states, municipalities, etc.
Reporting of any Spill of Oil or Hazardous Substance is Required and the failure to do so is criminally enforceable under 33 U.S.C 1321.
Contractor shall provide an Oil and Hazardous Materials Spill Prevention, Control, and Countermeasures Plan to address spill prevention and response measures for hazardous substances used on site, including fuels. A copy of this Plan shall be maintained on site during construction and contractor and subcontractor employees should be trained on spill prevention and response measures.
Prior to the start of work, the Contractor shall submit a plan that complies with YNP, Federal and State requirements and allows contractors to properly notify officials in the event of an emergency occurring during construction activities. YNP requirements include at a minimum:
During non-work operations, stationary equipment shall be parked over specially prepared containment pads designed to trap any leaking oil, fuel, or hydraulic fluids.
Inspect construction site daily for proper storage of hazardous materials, proper parking of equipment on containment pads, and for hydraulic and oil leaks of equipment, tighten hoses, and ensure they are in good condition. If equipment is leaking, it shall be immediately repaired or removed from the Park at Contractor’s expense.
Routine oiling, lubrication, and refueling shall be conducted with secondary containment using Best Management Practices (BMPs) at all times. Refueling of equipment in wetlands or stream channel areas is not allowed at any time. Signs prohibiting refueling will be posted in environmentally sensitive areas as directed by the natural resource monitor.
Contractor shall maintain secondary containment for all equipment operating with fluids (such as drilling) or when direct discharge of leakage, spills, or other source of construction or equipment fluids can flow directly to any streambed, whether flowing with water or dry. Containment shall be designed and installed to prevent accidental spills into streambeds in the event of mechanical failure or hose breakage.
Contractor shall maintain spill response materials on the project site when using heavy equipment to ensure rapid response to spills. These materials shall include absorbent pads, booms, or other materials as appropriate to contain oil, hydraulic fluid, solvents, and hazardous material spills. The contractor shall maintain adequate equipment to effectively respond to potential spillage at the site as determined by review of the COR.
Contractor shall provide names and phone numbers of appropriate contractor’s personnel to be contacted at any time (24 hours per day) regarding accidental release of hazardous substances to air, soil, or water. This list shall be submitted to the CO and a copy visibly displayed in work areas on site.
Contractor shall adhere to appropriate YNP staff notification procedures and shall rely on YNP to accomplish external notification. Contractor’s responsibility shall include immediate notification of all spills to the COR (or to park dispatch if the COR is not available). This notification will include specific details regarding spilled materials, amounts, and other relevant details as required by the park SPCC plan or as defined in advance in consultation with the COR.
Contractor shall digitally photograph or videotape the spill release at its source and photographically document the initial spill extent within 30 minutes of initial release.
24. Any Damage to Park Resources Must be Reported: A report should be relayed immediately to the COR. As additional information becomes available, the initial report shall be amended.
25. Working in Bear Country: Proper food storage is important to the welfare of the Yosemite bear population; and it is required by law.
- If staying in a campsite, store all food and related items in metal food lockers provided in campgrounds, not in vehicles.
- Bears have a strong sense of smell and may break into vehicles with the slightest hint of food. Dispose of your trash, food scraps, and recycling in a bear-proof receptacle.
- Be sure to check your vehicle daily and remove any item that may attract a bear. This includes canned food, drinks, soap, cosmetics, toiletries, trash, recycling, ice chests, grocery bags, and unwashed items used for preparing or eating meals.
- Close and latch any windows and doors in your hard-sided unit while you are away.
- Check job site at the end of each workday for trash or food
- Large open top bins/dumpsters used on the job site shall be covered and marked, “No Food /Trash.”
NPS Contracting Office shall provide “The bears are not to blame” brochure as courtesy for field personnel. Use the Save-a-Bear hotline (209) 372-0322 to report overflowing trash containers, improperly stored food, bear sightings, or other information about bears.
26. Inspection.
The Government will conduct inspections during and upon completion of required services. Final payment will be processed upon confirming that all noted contractor performance deficiencies have been satisfactorily corrected.
27. Schedule The period of performance for the subject project is from September 3, 2024, to October 19, 2024. The contractor shall provide a realistic schedule for the completion of the proposed work; and notify the Park if there is not sufficient time in the schedule prior to accepting the contract.
28. Liquidated Damages (NA)
29. Referenced Documents The Service will provide Design Plans and Specifications.
30. Base Price Schedule See attachment.
31. Location Map See attachment
ACRONYMS
| CAP | Contractor Acquired Property |
| CFR | Code of Federal Regulations |
| CO | Contracting Officer |
| COR | Contracting Officer Representative |
| FAR | Federal Acquisition Regulation |
| SOW | Statement of Work |
| YNP | Yosemite National Park |