This Contract Data Requirements List (CDRL) outlines quarterly reporting requirements for a contractor providing services to the Missouri River Recovery Implementation Committee (MRRIC). The contractor must submit draft quarterly chair updates within 5 days of the end of each quarterly reporting period, with final reports due to MRRIC members not later than 5 additional days after government approval of the draft. Reports are to be in Microsoft Word and must include highlights from MRRIC work groups, teams, participating agencies, and ISAP activities. The contractor will provide the reports to the National Center for Environmental Conflict Resolution Program Manager and Contracting Officer's Representative.
The related Request for Proposal solicits bids for non-personal professional services in coordination with MRRIC, the Udall Foundation's National Center, lead agencies, a facilitation team, and Third-Party Science Neutral. The base period of performance is from January 10, 2022 to January 9, 2023 at the contractor's facility with potential travel. The solicitation is issued by the Morris K. Udall Foundation and includes 4 option periods extending performance through January 9, 2027.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST (CDRL)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to the Morris K. Udall and Steward L. Udall Foundation, 130 S. Scott Avenue, Tucson, AZ 85701. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER_X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A002
Contractor’s Quarterly Chair Updates
Quarterly Updates
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
NA TOTAL PRICE
7. NOT USED 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
REQUIRED See Block 16
1st reporting period after start date
a. ADDRESSEE
b. COPIES
8. NOT USED 11. AS OF DATE 13. DATE IF SUBSEQUENT SUBM. final See Block 16 draft reg repr
16. REMARKS NCECR PM 1 1
The Contractor’s Quarterly Chair Updates Report provides the MRRIC team members the status of the program and summaries/highlights the work performed by the Committee throughout the quarter. This quarterly update will contain highlights from the various Work Groups, Teams, and ISAP activities, as well as highlights from participating agencies, as necessary. A draft report is due to the NCECR Program Manager and COR within 5 working days following the end of each quarter of the performance period. Upon review and approval of the Government, the final report shall be sent to MRRIC members not later than (NLT) 5 working days from receipt of DRAFT approval. E-Mail addresses for distribution will be provided with the contract.
COR 1 1
1. Format: Each report will be developed in Microsoft Word and submitted in softcopy to the NCECR PM and COR. The document will not be locked or protected in any fashion that would prevent text to be copied or edited by the government after delivery.
(a) Report shall be written for printing on 8 1/2" X 11" standard letter size paper (Portrait orientation) although necessary attachments, figures, and sketches may be submitted on in a size/orientation that best displays the information being presented.
(b) Font shall be Times New Roman, size 12.
(c) Each page beyond the first page shall have a header identifying the site name or report title and date of report
(d) Report shall be grammatically correct.
(e) All attachments shall be identified and referenced in the text of the report.
15. TOTAL --------------- > 2 2
G. PREPARED BY H. DATE I. APPROVED BY J. DAT
Mitch Chrismer 4/19/2021
UDALL Form 1423-1, FEB 2021 Previous editions are obsolete Page 1 of 1 Page