B08_Attachment 3 - CDRL A001 Contractors Progress Status and Management Report.pdf
PDF 187 KB Posted
- Solicitation number
- 95900621R0005
- Issued by
-
Morris K. Udall Foundation
About this file
This document contains a Contract Data Requirements List (CDRL) for a contract to provide monthly progress reports on work performed. The contractor must submit a Microsoft Word document no later than the 10th day of each month detailing the progress made on tasks, costs incurred and expended funds, problems encountered and recommendations, plans for the upcoming period, and key metrics. The reports should include a title page with contract and reporting period details, as well as content on task status, results, organizational changes, problem areas, expenditures, trips, calls, and appendices as needed. Distribution is to the NCECR PM and COR. This is Attachment 3 to CDRL A001 for an unspecified contract or procurement number.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST (CDRL)
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to the Morris K. Udall and Steward L. Udall Foundation, 130 S. Scott Avenue, Tucson, AZ 85701. Please DO NOT RETURN your form to either of these addresses. Send completed form to the government Issuing Contracting Officer for the Contract/PR No. in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER_X
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A001
Contractor’s Progress, Status and Management Report
Monthly Progress Report
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
NA TOTAL PRICE
7. NOT USED 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
REQUIRED See Block 16
1st reporting period after start date
a. ADDRESSEE
b. COPIES
8. NOT USED 11. AS OF DATE 13. DATE IF SUBSEQUENT SUBM. final See Block 16 draft reg repr
16. REMARKS NCECR PM 0 1
The Contractor’s Progress, Status, and Management Report indicates the progress of work and the status of the program and of the assigned tasks, reports costs, and informs of existing or potential problem areas for the contract.
The progress report for this contract is due not later than (NLT) 10 working days following the end of each reporting period. The reporting period shall coincide with the contractor’s normal ‘monthly’ accounting and billing cycle. E-Mail addresses for distribution will be provided with the contract.
COR 1
1. Format: All reports will be developed in Microsoft Word and submitted in softcopy to the NCECR PM and COR. The document will not be locked or protected in any fashion that would prevent text to be copied or edited by the government after delivery.
(a) Report shall be written for printing on 8 1/2" X 11" standard letter size paper (Portrait orientation) although necessary attachments, figures, and sketches may be submitted on in a size/orientation that best displays the information being presented.
(b) Font shall be Times New Roman, size 12.
(c) Each page beyond the first page shall have a header identifying the site name or report title and date of report
(d) Report shall be grammatically correct.
(e) All attachments shall be identified and referenced in the text of the report.
2. Title page:
A. Title. The title shall identify the subject of the report, program name, or task.
B. Name of contractor. The name of the contractor preparing the report.
C. Contract number. The procurement instrument identification number.
D. Key person. The individual assigned to the task or who produced the report.
E. Reporting period. The dates the reporting period begins and ends.
3. Content.
(a) Description of the progress made during the reporting period;
(b) Results, positive or negative, obtained related to previously-identified problem areas, with conclusions and recommendations;
(c) Any significant changes to the contractor’s organization or method of operation or to the project management network;
(d) Problem areas affecting technical or scheduling elements, with background and any recommendations for solutions beyond the scope of the contract;
(e) Problem areas affecting cost elements, with background and any recommendations for solutions beyond the scope of the contract;
(f) log of WG / Team / Planning calls attended;
(g) Contract hours expended on this contract by task and by contractor personnel;
(h) Roll up of TDY/travel funds expended and remaining;
(i) Any other costs (ODCs, etc.) incurred for the reporting period and total contractual expenditures and remaining funds as of reporting date;
(j) Any trips and significant results;
(k) Record of all significant telephone calls and any commitments made by telephone;
(l) Plans for activities during the following reporting period;
(m) Name and telephone number of preparer of the report;
(n) Appendices for any necessary tables, references, photographs, illustrations, and charts.
15. TOTAL --------------- > 0 2
G. PREPARED BY H. DATE I. APPROVED BY J. DAT
Mitch Chrismer 4/19/2021
UDALL Form 1423-1, FEB 2021 Previous editions are obsolete Page 1 of 5 Pages
Project Status Report Project Name:
Week To
Manager Report Date
Status Summary
Percent Complete 5% Budget Status Y
1. Key Project Performance Metrics
Budget to Actual Performance
Current Month Budget Cumulative Budget Current Month Actual Cumulative Actual
Current Month Budget less Actual Cumulative Budget less Actual Percent Deviation this Month
Percent Deviation Cumulative
Forecasts EAC (Estimate at Completion) BAC (Budget at Completion)
2.2 Project Manager’s Outlook Summary
2. Project Manager’s Report
2.1 Project Manager’s Status Summary
3. Activities/Accomplishments/Decisions This Week
3.1 Planned Activities Brought Forward - DD/MM/YY to DD/MM/YY
WBS Activity Description
1.3.2
1.3.3
1.3.4
3.4 Planned Activities For The Next Week - DD/MM/YY to DD/MM/YY
WBS Activity Description Expected Target Delivery Date
1.3.2 DD/MM/YY
1.3.3 DD/MM/YY
1.3.4 DD/MM/YY
5. Risk and Issue Logs
5.1 Issue Log
L og
N o
Description
T yp e
Resolution Strategy
Im pa ct
O w ne r
Identified
Target Resolution
Days
Overdue
Issue Type Key
B – Business P – Project D – Development
5.2 Risk Log
L og
N o
Description
T yp e
Mitigation Strategy
Se ve ri ty
Pr ob ab ili ty
O w ne r
Identified
Target
Resolution
Days Overdue
6.0 Outstanding Decisions and Sign-Offs
Decision/Sign-Off Responsibility Due
Probability Key Impact Key
High (H) – 90% Probability of risk being realized. High (H) - Critical Path Risk. If realized, the resulting issue would immediately impact cost / project delivery dates.
Medium (M) – 75% Probability of risk being realized.
Medium (M) – If realized, the resulting issue would cause slippages in deliverable release dates but would have an immediate effect on overall cost /project delivery dates.
Low (L) – 50% Probability of risk being realized. Low (L) – If realized, the resulting issue would not impact delivery dates but could impact the quality of deliverables.
File details come from the government source that posted it. Updated .