This document is a Statement of Structural Tests and Special Inspections for the project to rehabilitate the waterfront at Little Sand Bay and Devils Island and reconstruct the boathouse at Apostle Islands National Lakeshore. It details the required structural tests and inspections for the steel construction, concrete, masonry, and other elements of the project, including qualifications for inspectors and technicians. The key objectives are to verify compliance with the International Building Code and the approved project specifications, including inspections of welding, bolting, reinforcing steel, concrete placement, and other critical construction activities. This document supports the federal contract opportunity solicitation number 140P2024R0045 for the Apostle Islands National Park project.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PARK/PMIS page 1 of 23
Statement of Structural Tests and Special Inspections National Park Service (NPS) - Denver Service Center (DSC) | 6-29-21
Park: Apostle Islands National Lakeshore
Project Management Information System (PMIS) Number: 270691
Project Name: Little Sand Bay & Devils Island
Structural Engineering Firm: AMI Consulting Engineers, P.A.
This Statement of Structural Tests and Special Inspections is being submitted as required by Chapter 17 of the 2021 International Building Code (IBC-21). It includes the following:
1. Seismic requirements
2. Wind requirements
3. Qualification Requirements for Inspectors and Testing Technicians
4. Listing of Required Structural Tests and Special Inspections
The Construction Contractor’s Quality Control Supervisor will provide copies of all special inspection reports and associated documentation to the Contracting Officer (CO). The Construction Contractor will be required to correct all deficiencies discovered in the Special Inspection and Structural Testing program.
Prepared By: _________________Chad Scott___________________________________ (Type or print name)
Signature: ______see stamp_______________________________________ Date: 12/15/2023
Stamped by Professional Engineer (PE) or Structural Engineer (SE)
TS
PARK/PMIS page 2 of 23
Seismic and Wind Requirements
Seismic Requirements, IBC-21 Section 1704.3
Description of seismic-force-resisting system and designated seismic systems subject to special inspections:
Seismic forces were looked at but were determined to not control lateral forces.
Wind Requirements, IBC-21 Section 1704.3
Description of wind-force-resisting system and designated wind systems subject to special inspections:
Wind forces were looked at for the dock structures but did not control lateral forces. The boathouse has a moment frame and diagonal brace to resist wind loads.
PARK/PMIS page 3 of 23
Instructions:
1. Under Listing of Required Structural Tests and Special Inspections:
a. Required? - Place an X for all Special Inspections and Tests required for this project.
b. Required Qualifications - Provide qualifications for the special inspector, using the
Qualification Requirements for Inspector and Testing Technicians list below, for all required Structural Tests and Special Inspections.
c. Continuous - If marked with an X, continuous special inspection shall be as defined in Chapter
2, IBC-21.
d. Periodic - If marked with an X, provide the minimum number of tests, i.e. 20% of all field welds, or the amount of work to be inspected (e.g. 10% of all wall surfaces).
2. Attach completed Statement of Structural Tests and Special Inspections to the end of NPS DSC Division 1 Specifications Section 01 40 00 Quality Requirements.
Qualification Requirements for Inspectors and Testing Technicians
PE/SE Structural Engineer – licensed PE or SE specializing in the design of buildings and structures PE/GE Geotechnical Engineer – licensed PE specializing in soil mechanics and foundations EIT Engineer-In-Training – graduate engineer who has passed the Fundamentals of engineering examination
American Concrete Institute (ACI) Certification
ACI-CCSI Concrete Construction Special Inspector ACI-LTT Concrete Laboratory Testing Technician Level 1 or 2 ACI-STT Concrete Strength Testing Technician ACI-FTT Concrete Field Testing Technician – Grade I
American Society of Non-Destructive Testing (ASNT) Certification
Non-Destructive Testing Technician – Level II or III
American Welding Society (AWS) Certification
AWS-CWI Certified Welding Inspector
Exterior Design Institute (EDI) Certification
EDI-EIFS Certified EIFS inspector
International Code Council (ICC) Certification
ICC-PCSI Prestressed Concrete Special Inspector ICC-RCSI Reinforced Concrete Special Inspector ICC-SSI Soils Special Inspector ICC-SFSI Spray-applied Fireproofing Special Inspector ICC-SMSI Structural Masonry Special Inspector ICC-SSBSI Structural Steel and Bolting Special Inspector ICC-SWSI Structural Welding Special Inspector
National Institute for Certification in Engineering Technologies (NICET) Certification
NICET-CT Concrete Technician – Levels I, II, III and IV NICET-GET Geotechnical Engineering Technician - Levels I, II, III and IV NICET-ST Soils Technician - Levels I, II, III and IV
PARK/PMIS page 4 of 23
Other
PARK/PMIS page 5 of 23
Listing of Required Structural Tests and Special Inspections R eq u ir ed
Structural Test or Special Inspection Required
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection
Steel Construction (IBC-21 Section 1705.2; American Institute of Steel Construction: AISC 360-16 Chapter N, AISC 341- 16 Chapter J)
Prior to Welding (AISC 360-16 Table N5.4-1)
X
1. Welder qualification records and continuity records
A.S.N.T. II OR
AWS-CWI
2. Welding procedure specifications (WPS) available
A.S.N.T. II OR
3. Manufacturer certifications for welding consumables available
A.S.N.T. II OR
X 4. Material identification (type/grade)
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X 5. Welder identification system
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X 6. Fit-up of groove welds (including joint geometry)
A.S.N.T. II OR
AWS-CWI
Twice a week during steel erection
a. Joint preparation X
b. Dimensions (alignment, root opening, root face, bevel)
c. Cleanliness (condition of steel surfaces) X
d. Tacking (tack weld quality and location) X
e. Backing type and fit (if applicable) X
X
7. Fit-up of CJP (complete joint penetration) groove welds of HSS (hollow structural sections) T-, Y- and K-joints without backing (including joint geometry)
Twice a week during steel
a. Joint preparation X
PARK/PMIS page 6 of 23
R eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
b. Dimensions (alignment, root opening, root face, bevel)
c. Cleanliness (condition of steel surfaces) X
d. Tacking (tack weld quality and location) X
X 8. Configuration and finish of access holes
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X 9. Fit-up of fillet welds
A.S.N.T. II OR
AWS-CWI
Twice a week during steel erection
a. Dimensions (alignment, gaps at root) X
b. Cleanliness (condition of steel surfaces) X
c. Tacking (tack weld quality and location) X
X 10. Check welding equipment
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
During Welding (AISC 360-16 Table N5.4-2)
X 1. Control and handling of welding consumables
A.S.N.T. II OR
AWS-CWI
Twice a week during steel erection
a. Packaging X
b. Exposure control X
X 2. No welding over cracked tack welds
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X 3. Environmental conditions
A.S.N.T. II OR
AWS-CWI
Twice a week during steel erection
a. Wind speed within limits X
b. Precipitation and temperature X
PARK/PMIS page 7 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection
X 4. WPS followed
A.S.N.T. II OR
AWS-CWI
Twice a week during steel erection
a. Settings on welding equipment X
b. Travel speed X
c. Selected welding materials X
d. Shielding gas type/flow rate X
e. Preheat applied X
f. Interpass temperature maintained
(minimum/maximum)
g. Proper position (F, V, H, OH) X
h. Intermix of filler metals avoided unless approved (reference: AISC 341-10 Table J6.2)
X 5. Use of qualified welders
X 6. Welding techniques
AWS-CWI
Twice a week during steel erection
a. Interpass and final cleaning X
b. Each pass within profile limitations X
c. Each pass meets quality requirements X
X
7. Placement and installation of headed stud anchors
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
After Welding (AISC 360-16 Table N5.4-3)
X 1. Welds cleaned
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X 2. Size, length, and location of welds
A.S.N.T. II OR
PARK/PMIS page 8 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection
X 3. Welds meet visual acceptance criteria
a. Crack prohibition X
b. Weld/base-metal fusion X
c. Crater cross section X
d. Weld profiles X
e. Weld size X
f. Undercut X
g. Porosity X
X 4. Arc strikes
A.S.N.T. II OR
X 5. k-area
6. Weld access holes in rolled heavy shapes and built-up heavy shapes
7. Backing removed and weld tabs removed (if required)
A.S.N.T. II OR
X 8. Repair activities
9. Document acceptance or rejection of welded joint or member
A.S.N.T. II OR
10. No prohibited welds have been added without the approval of the EOR (Engineer of Record)
A.S.N.T. II OR
11. Placement of reinforcing or contouring fillet welds (if required) (reference: AISC 341-16)
A.S.N.T. II OR
Nondestructive Testing (AISC 360-16 Section N5 and AISC 341-16 Section J6)
1. Risk Category II Structures - Perform Ultrasonic Testing on 10% of CJP groove welds in butt, T-and corner joints subject to transversely applied tension loading, in materials 5/16 inch thick or greater.
A.S.N.T. II OR
AWS-CWI
X
Twice a week during steel erection
2. Risk Category III or IV Structures - Perform Ultrasonic Testing on all CJP groove welds
PARK/PMIS page 9 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection subject to transversely applied tension loading in butt, T- and corner joints, in materials 5/16 inch thick or greater.
3. Access Holes – Perform Magnetic Particle Testing or Liquid Penetrant Testing when the flange thickness exceeds 2 inches for rolled shapes, or when the web thickness exceeds 2 inches for built-up shapes.
4. Welded Joints Subject to Fatigue
Nondestructive Testing (AISC 341-16 Section J6)
Column Splice and Column to Base Plate PJP Groove Weld (AISC 341-16 Section J6 2b)
1. Perform Ultrasonic Testing on 100% of PJP
(partial-joint-penetration) groove welds in column splices and column to base plate welds
AWS-CWI X
X 2. CJP Groove weld
X 3. Lamellar tearing
4. Beam cope and access hole
X 5. Reduced beam section repair
X 6. Weld tab removal
Prior to Bolting (AISC 360-16 Table N5.6-1)
These inspections are not required for snug-tight joints.
1. Manufacturer’s certifications available for fastener materials
A.S.N.T. II OR
2. Fasteners marked in accordance with ASTM requirements
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
3. Correct fasteners selected for the joint detail
(grade, type, bolt length if threads are to be excluded from shear plane)
A.S.N.T. II OR
AWS-CWI X
Twice a week
PARK/PMIS page 10 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection
X
4. Correct bolting procedure selected for joint detail
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
5. Connecting elements, including the appropriate faying surface condition and hole preparation, if specified, meet applicable requirements
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
6. Pre-installation verification testing by installation personnel observed and documented for fastener assemblies and methods used
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
7. Protected storage provided for bolts, nuts, washers and other fastener components
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel
During Bolting (AISC 360-16 Table N5.6-2)
These inspections are not required for snug-tight joints.
These inspections are not required for pretensioned joints and slip-critical joints, when the installer is using the turn-of-nut method with matchmarking techniques, the direct-tension-indicator method, or the twist-off-type tension control bolt method.
1. Fastener assemblies, of suitable condition, placed in all holes and washers (if required) are positioned as required
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
2. Joint brought to the snug-tight condition prior to the pretensioning operation
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
3. Fastener component not turned by the wrench prevented from rotating
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
4. Fasteners are pretensioned in accordance with the RCSC (Resource Council on Structural Connections) Specification, progressing systematically from the most rigid point toward the free edges
A.S.N.T. II OR
AWS-CWI
X
Twice a week during steel
After Bolting (AISC 360-16 Table N5.6-2)
PARK/PMIS page 11 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection
X Document acceptance or rejection of bolted connections.
A.S.N.T. II OR
AWS-CWI X
Twice a week
Other Inspection Tasks (AISC 360-16 Section N5.7)
1. Verify compliance of fabricated steel with the details shown on the approved shop drawings.
A.S.N.T. II OR
AWS-CWI
X
20% of members
10% of connections
X
2. Verify compliance of the erected steel frame with the details shown on the approved erection drawings, including braces, stiffeners, member locations and joint details.
A.S.N.T. II OR
AWS-CWI X
Twice a week
3. Anchor rods and other embedments support structural steel
a. Verify the diameter, grade, type and length of the anchor rod or embedded item.
b. Verify the extent or depth of embedment into the concrete.
4. RBS (reduce beam section) requirements, if applicable (AISC 341-16)
a. Contour and finish
b. Dimensional tolerances
X
5. Protected zone - no holes and unapproved attachments made by fabricator or erector, as applicable. (AISC 341-16)
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
X
6. H-piles - Protected zone - no holes and unapproved attachments made by the responsible contractor, as applicable. (AISC 341-16)
A.S.N.T. II OR
AWS-CWI X
Twice a week during steel erection
Cold-formed Steel Deck (IBC-21 1705.2.2)
X
1. Special inspections in accordance with QA/QC- 2017 Standard for Quality control (QC) and Quality assurance (QA) for Installation of Steel Deck
Open-Web steel Joists and Joist Girders (IBC- 21 Table 1705.2.3)
PARK/PMIS page 12 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
1. Installation of open-web steel joists and joist girders.
a. End connections - welding or bolted
b. Bridging - horizontal or diagonal
1. Standard bridging
2. Bridging that differs from the SJI (Steel
Joist Institute) specifications listed in Section 2207.1.
Inspection of Composite Structures Prior to Concrete Placement (AISC 341-16 Table J9.1)
1. Material identification of reinforcing steel
(Type/Grade) during bar placement
2. Determination of carbon equivalent for reinforcing steel other than ASTM A706
3. Proper reinforcing steel size, spacing and orientation
4. Reinforcing steel has not been rebent in the field
5. Reinforcing steel has been tied and supported as required
6. Required reinforcing steel clearances have been provided during bar
X 7. Composite member has required size
Inspection of Composite Structures During Concrete Placement (AISC 341-16 Table J9.2)
1. Concrete: Material identification (mix design, compressive strength, maximum large aggregate size, maximum slump)
2. Limits on water added at the truck or pump X
PARK/PMIS page 13 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
3. Proper placement techniques to limit segregation
Inspection of Composite Structures During Concrete Placement (AISC 341-16 Table J9.2)
1. Achievement of minimum specified concrete compressive
Break cylinders from the beginning of every pour
Cold-formed Steel Trusses Spanning 60-feet or Greater (IBC-21 Section 1705.2.4)
1. Verify temporary installation restraint/bracing installed in accordance with the approved shop drawings.
2. Verify permanent individual truss member restraint/bracing installed in accordance with the approved shop drawings.
Concrete Construction (IBC-21 Section 1705.3)
1. Inspect reinforcing steel, including prestressing tendons, and placement.
Structural EIT or greater approved by
EOR X
Prior to every concrete pour unless approved by EOR
2. Inspection of reinforcing steel welding
a. Verify weldability of reinforcing bars other than ASTM A706.
b. Inspect single pass fillet welds, maximum
5/16 inch.
c. Inspect all other welds.
3. Inspection of anchors cast in concrete.
4. Inspection of anchors post-installed in hardened concrete members.
a. Adhesive anchors installed in horizontally or upwardly inclined orientations to resist sustained tension load
b. Mechanical anchors and adhesive anchors not defined in 4 a
PARK/PMIS page 14 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection
X 5. Verify use of approved design mix. ACI-FTT X At each pour
X
6. Prior to placement fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete.
ACI-FTT
7. Inspect concrete and shotcrete placement for proper application techniques.
Structural EIT or greater approved by
EOR
8. Inspect for maintenance of specified curing temperature and techniques.
ACI-FTT
X
Pull temps once per week for highs and lows while curing for first 28 days or until it reaches specified strength.
9. Inspection of prestressed concrete:
a. Application of prestressing forces
b. Grouting of bonded prestressing tendons in the seismic-force-resisting system.
10. Erection of precast structural members
11. For precast concrete diaphragm connections or reinforcement at joints classified as moderate or high deformability elements (MDE or HDE) in structures assigned to Seismic Design Category C, D, E, or F, inspect such connections and reinforcement in the field for:
a. Installation of the embedded parts
b. Completion of the continuity of reinforcement across joints
c. Completion of connections in the field
12. Inspect installation tolerances of precast concrete diaphragm connections for compliance with ACI 550.5 (American Concrete Institute).
13. Verification of in-situ concrete strength, prior to stressing of tendons in post-tensioned concrete
PARK/PMIS page 15 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection and prior to removal of shores and forms from beams and structural slabs.
X
14. Inspection formwork for shape, location and dimensions of the concrete member being formed.
Structural EIT or greater approved by
EOR X
Prior to every concrete pour unless approved by EOR
Masonry Construction (IBC-21 Section 1705.4)
1. Inspect masonry construction in accordance with IBC-21 Section 1705.4 and TMS 602-13 (The Masonry Society)/ACI 530.1-13 Article 1.6.
Level A Quality Assurance
Tests: None.
Inspection: Verify compliance with the approved submittal and project specifications.
Level B Quality Assurance
Tests:
1. Verify slump flow and Visual Stability Index (VSI) as delivered to the project site in accordance with TMS 602-13/ACI 530.1-13 Specification Article 1.5B.1.b.3 for self-consolidating grout.
2. Verify f’m and f’aac in accordance with TMS 602-13/ACI 530.1-13 Specification Article 1.4B prior to construction, except where specifically exempted.
Inspection:
1. Verify compliance with the approved submittals and project specifications.
2. At the start of masonry construction, verify:
a. Proportions of site-prepared mortar.
b. Construction of mortar joints.
c. Grade and size of prestressing tendons and anchorages.
PARK/PMIS page 16 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
d. Location of reinforcement, connectors, prestressing tendons and anchorages.
e. Prestressing technique.
f. Properties of thin-bed mortar for AAC (autoclaved aerated concrete) masonry.
(Continuous inspection is required for the first 5000 square feet of AAC masonry.
Periodic inspection is required after the first 5000 square feet of AAC masonry.)
3. Prior to grouting, verify:
a. Grout space is clean.
b. Grade, type and size of reinforcement and anchor bolts, and prestressing tendons and
c. Placement of reinforcing and connectors, and prestressing tendons and anchorages.
d. Proportions of site-prepared grout and prestressing grout for bonded tendons.
e. Construction of mortar joints.
4. During masonry construction, verify:
a. Size and location of structural members.
b. Type, size and location of anchors, including other details of anchorage of masonry to structural members, frames, or other construction.
c. Welding of reinforcement.
d. Preparation, construction and protection of masonry during cold weather (temperature below 40 degrees Fahrenheit) or hot weather (temperature above 90 degrees Fahrenheit).
e. Application and measurement of prestressing force.
f. Placement of grout and prestressing grout for bonded tendons is in compliance.
PARK/PMIS page 17 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
g. Placement of AAC masonry units and construction of thin-bed mortar joints.
(Continuous inspection is required for the first 5000 square feet of AAC masonry.
Periodic inspection is required after the first 5000 square feet of AAC masonry.)
5. Observe preparation of grout specimens, mortar specimens and/or prisms.
Level C Quality Assurance
Tests:
1. Verify f’m and f’aac in accordance with TMS 602-13/ACI 530.1-13/ASCE 6-13 Specification Article 1.4B prior to construction, and for every 5000 square feet during construction.
2. Verify proportions of materials in premixed or pre-blended mortar, prestressing grout, and grout other than self-consolidating grout as delivered to the project site.
3. Verify slump flow and Visual Stability Index (VSI) as delivered to the project site in accordance with TMS 602-13/ACI 530.1- 13/ASCE 6-13 Specification Article 1.5B.1.b.3 for self-consolidating grout.
Inspection:
1. Verify compliance with the approved submittals and project specifications.
2. Verify:
a. Proportions of site-prepared mortar, grout and prestressing grout for bonded tendons.
b. Grade, type and size of reinforcement and anchor bolts, and prestressing tendons and
c. Placement of masonry units and construction of mortar joints.
d. Placement of reinforcement, connectors and prestressing tendons and anchorages.
e. Grout space prior to grouting.
PARK/PMIS page 18 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
f. Placement of grout and prestressing grout for bonded tendons.
g. Size and location of structural elements.
h. Type, size and location of anchors, including other details of anchorage of masonry to structural members, frames or other construction.
i. Welding of reinforcement.
j. Preparation, construction and protection of masonry during cold weather (temperature below 40 degrees Fahrenheit) or hot weather (temperature above 90 degrees Fahrenheit).
k. Application and measurement of prestressing force.
l. Placement of AAC masonry units and construction of thin-bed mortar joints.
m. Properties of thin-bed mortar for AAC masonry.
3. Observe preparation of grout specimens, mortar specimens and/or prisms.
Wood Construction (IBC-21 Section 1705.5)
1. Inspect prefabricated wood structural elements in accordance with Section 1704.2.5.
2. High load diaphragms:
a. Verify sheathing grade and thickness.
b. Verify nominal size of framing members at adjoining panel edges.
c. Verify nail or staple diameter and length.
d. Verify number of fastener lines.
e. Verify spacing between fasteners in each line and at panel edges.
3. Shearwalls:
PARK/PMIS page 19 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test
a. Verify sheathing grade and thickness.
b. Verify nominal size of framing members at adjoining panel edges.
c. Verify nail or staple diameter and length.
d. Verify number of fastener lines.
e. Verify spacing between fasteners in each line and at panel edges.
f. Location and size of holdowns.
4. Verify nailing, bolting, anchoring and fastening of:
a. Drag struts and collectors.
b. Braces.
c. Hold-downs.
5. Metal-plate-connected wood trusses spanning
60 feet or greater:
a. Verify temporary installation
b. Verify permanent individual truss member
Soils (IBC-21 Section 1705.6)
1. Verify materials below shallow foundations are adequate to achieve the required bearing capacity.
PE/GE
X
One visual inspection prior to formwork.
2. Verify excavations are extended to proper depth and have reached proper material.
3. Perform classification and testing of compacted fill materials.
4. During fill placement, verify use of proper materials and procedure in accordance with the provisions of the approved geotechnical report.
One visual inspection per 50 linear feet
PARK/PMIS page 20 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of Periodic Test or Inspection
Verify densities and lift thicknesses during placement and compaction of compacted fill.
5. Prior to placement of compacted fill, inspect subgrade and verify that site has been prepared properly.
Driven Deep Foundation Elements (IBC-21 Section 1705.7)
X 1. Verify element materials, sizes and lengths.
during erection
X
2. Determine capacities of test elements and conduct additional load tests when required.
Refer to project specifications.
3. Inspect driving operations and maintain complete and accurate records for each element.
X 4. Verify element locations and plumbness.
a. Verify type and size of hammer. X
b. Record number of blows per foot of penetration.
c. Determine required penetration to achieve specified capacity.
d. Record pile tip and butt elevations. X
e. Document any damage to any foundation
5. For steel piling, perform additional inspection in accordance with Section 1705.2 and AISC 341- 16, Table J10.1.
during erection
6. For concrete elements and concrete-filled elements, perform additional inspections in accordance with Section 1705.3.
7. For specialty elements, perform additional inspections as required in the project specifications.
Cast-in-Place Deep Foundation (IBC-21 Section 1705.8)
PARK/PMIS page 21 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
1. Inspect drilling operations and maintain complete and accurate records for each
2. Verify element locations and plumbness.
a. Verify element diameter.
b. Verify bell diameter (if applicable).
c. Verify element lengths.
d. Verify embedment depth into bedrock (if applicable).
e. Verify adequate end-bearing strata capacity.
f. Record concrete or grout volumes.
3. For concrete elements, perform additional inspections in accordance with Section 1705.3.
Helical Piles (IBC-21 Section 1705.10)
1. Verify pile locations.
a. Verify installation equipment used.
b. Verify pile dimensions.
c. Verify tip elevations.
d. Verify final depth.
e. Verify final installation torque.
f. Other data as required by the project specifications.
Fabricated Items (IBC-21 Section 1705.11)
1. Inspect fabricated items in accordance with
Section 1704.2.5.
Wind Resistance (IBC-21 Section 1705.12)
PARK/PMIS page 22 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
1. Provide inspections when required by Section
1705.12.
Seismic Resistance (IBC-21 Section 1705.13)
1. Provide inspections when required by Section
1705.13.
Testing and Qualification for Seismic Resistance (IBC-21 Section 1705.14)
1. Test and qualify seismic resistance in accordance with IBC-21 Section 1705.14 and the project specifications.
Sprayed Fire-Resistant Materials (IBC-21 Section 1705.15)
1. Inspect sprayed fire-resistant materials in accordance with IBC-21 Section 1705.15 and the project specifications.
Mastic and Intumescent Fire- Resistant Coatings (IBC-21 Section 1705.16)
1. Perform inspections in accordance with AWCI
12-B (Association of the Wall and Ceiling Industry) and IBC-21 Section 1705.16.
Exterior Insulation and Finish Systems (EIFS) (IBC-21 Section 1705.17)
1. Perform inspections in accordance with project specifications and IBC-21 Section 1705.17.
Fire-Resistant Penetrations and Joints (IBC-21 Section 1705.18)
1. Perform inspections in accordance with project specifications and IBC-21 Section 1705.18.
Smoke Control (IBC-21 Section 1705.19)
PARK/PMIS page 23 of 23 eq u ir
Qualifications
C o n ti n u o u s
P e ri o d ic
Frequency of
1. Perform testing in accordance with project specifications and IBC-21 Section 1705.19.
Sealing of Mass Timber (IBC-21 Section 1705.20)
1. Perform testing in accordance with project specifications and IBC-21 Section 1705.20.