This document is Amendment 2 to Solicitation 140P2024R0045 for the Apostle Islands National Park, WI project to Rehabilitate Waterfront at Little Sand Bay and Devils Island, and Reconstruct Boathouse.

The amendment provides questions and answers, a site visit sign-in sheet, a corrected specification section, a presentation to bidders, and an extension to the solicitation due date to May 1, 2024. The National Park Service has secured permits from the Wisconsin Department of Natural Resources and the U.S. Army Corps of Engineers for the work. In-water work has seasonal restrictions, but exemptions have been granted for the 2024 construction season. The contract will be a firm-fixed price award to a small business, with a 335-day period of performance including a winter shutdown. Key evaluation factors include technical approach, experience, management approach, schedule, and key personnel.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2024R0045 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div

04/11/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/19/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this Amendment is to provide for the Questions and Answers as of 04/11/2024, Site-Visit sign in sheet from 4/4/2024, Corrected Section 01 31 00, Presentation to

Bidders, Delete pages 45-48 from solicitation and an extension to the Solicitation to May 1, 2024 . All other terms and conditions of the solicitation package remain unchanged and in full effect.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Edwin Berry

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Question: Answer:

Amendment

Number:

Could the performance period be extended to allow all of the 2025 season for construction?

In-water work is seasonally limited by the WIDNR permit. A WIDNR extension to the seasonal start was granted for the 2024 season and can be requested for the 2025 season as it nears. The NPS will consider extending the overall Period of performance based on feedback during this bid period. 1

Can project completion extend to, if not past, 12/1/25? Request due to unknown weather conditions and potentially shorter construction seasons than normal.

Please clarify your request. Are you requesting we extend to December

2025? Can you reasonably assume to execute work during these months? 1

Can we get a 2 week bid extension? Extending the bid period will have an impact on the 2024 construction season. With this in mind we are not going to extend the bid period. 1

4 consider an additional 6 months be added to the period of performance.

See response to #1 above. Please clarify your request. Are you requesting we extend to March 2026? Can you reasonably assume to execute work during these months? 1

Could you please provide a cut section of the demolition required at the

East Breakwater? On Sheet C1.2 there is a detail for Breakwater Extension

Demolition, are we to assume the East and West Breakwater Extension demolition are similar?

No demolition is to occur on east breakwater. CLIN 7 (Bid Option #3)is for sheetpile installation only. For informational purposes, 4/C1.2 illustrates how the east breakwater is constructed. Photo 5/C1.1 provides additional information. 2

Is it acceptable to construct a temporary causeway on the Lake Superior side of the Marina to facilitate construction during the duration of the project?

This is acceptable within the marina as long as it does not conflict with the Town of Russel boat launch or dock. Means and methods of this would be the responsibility of the contractor. 2

Solicitation Number - 140P2024R0045 APIS - 270691 Apostle Island National Park, WI -

Rehabilitate Waterfront at Little Sand Bay and Devils Island, Reconstruct Boathouse

WDNR Permit Appendix E for Devils Island states “To minimize adverse impacts on fish movement, fish spawning, and egg incubation periods, work may not take place during September 15th through April 15th. The second WDNR letter item 6 states: “Fish spawning. No discharges of dredged or fill material below the ordinary high-water mark of a navigable stream as defined by s. 310.03(5), Wis. Adm. Code, may take place during fish spawning periods or times when nursery areas would be adversely impacted. These periods are: September

15th through July 1st for Lake Superior fish spawning refuge”

Specifications section 01 31 00 1.9 C. States no in water work for Devils

Island from Sept 15th to July 15th.

Which is correct?

Previous Projects in this area utilized the April 15th end date for the no in water work period. A longer construction period of April 15th – September

15th is preferred due to the amount of work required on Devils Island.

Add updated 01 31 00 section now as amendment

Time of Year Restrictions: According to the Water Quality Certificates

(WQC) obtained from the WI DNR, in water work can not occur at the project locations with out a fish window exemption from the WI DNR during the following times.

Little Sand Bay- September 15th through June 15th

Devils Island- September 15th through July 1st

Fish Window Exemptions have been secured from the WI DNR for the

2024 construction season. In-water work can occur at the project sites during the following times:

Little Sand Bay- May 26th through September 15

Devils Island- June 3rd through September 15

In-water work outside of the dates listed above shall require approved by the WI DNR Fisheries Biologist prior to in-water work commencing.

Since we are now shifting the Period of Performance to 2025 and 2026 we NPS will request an exemption for 2025, WIDNR will only grant one year at a time. 2

Sheet CT 2.5 shows an anchoring detail for the toe stone and a toe trench detail. Is it the contractor’s option to either anchor the toe stone or create a trench? Either option is acceptable. 2

Sheet CT0.1 States that vibro compaction is required for all material placed in water depths greater than 1 foot. Where is vibro compaction required? Inside the sheetpile. 2

One document says completion date by 4/1/2025, another says 9/15/2025, and recent amendment says performance period 5/01/2024 to 4/01/2025.

Which is the correct completion date and performance period?

The NPS plans to award the construction contract in June of 2024.

However, due to long lead items and contractor completion of Division

1s we now anticipate issuance of the Notice to Proceed on May 1, 2025.

The Period of Performance is 335 days, with a winter shutdown (winter shutdown days not counted against 335). Offerors shall plan for a winter shutdown anticipated 10/31/25 through 4/30/26. The WIDNR permit in water work restrictions are outside of the control of the NPS but additional days under the permit will be sought for 2025 season (to mirror the unused 2024 season). An extension to the WIDNR Little Sand

Bay Permit (which expires in September 2026) will also be sought. 2

Specification section 05 12 00 2.4 A states fabrication according to AISC

Code of Standard Practice for Steel Buildings and Bridges and AISC 360.

Does this require the fabrication to be completed by an AISC certified fabricator? Yes, AISC certified fabrication is required. 2

Specification section 05 12 00 2.6 GALVANIZING. What steel is required to be galvanized? Note on sheet CT0.0 also mentions painting of structural steel shapes. What steel is to be painted? Items which require galvanization and painting are shown on drawings. Only items specifically identified as requiring galvanization/painting are to be treated. 2

Plan notes state that contractor is responsible for clearing drive line 5-ft below existing mudline. Can the government provide the bottom elevation of the existing cribs at Sand Bay? Suggest NPS provide as-builts. 2

Underwater welding is noted in the plans and specifications. Where is underwater welding required on this project? Please refer to 3/CT1.11 2

Sheet CT1.4 detail 1 and 2 Is a toe trench required for placement of the scour stone? Or is that dip in the mudline just depicting a varying mudline?

Yes, a 1-foot-deep toe trench is required for placement of the scour stone. 2

Sheet CT1.4 detail 4. Can you please provide a non-truncated cross section that accurately depicts layer thicknesses of the armor and filter stone? Also, is the “toe stone” note in this detail referring to the larger 5.3-8.8 ton toe stone? Or is this all armor stone 2.2-4.4 ton? Refer to section 31 35 19 2.2.A 2

Sheet CT1.4 detail 2 and sheet CT 1.6 Detail 2. Does the 3/4 “ crushed stone fill come all the way up to the top of the horizontal HP14 Strut? Yes, CT1.6 shows the 3/4" crushed coming all the way to the top. 2

Please confirm that the viewing platform is to be removed, stored, and reinstalled with no additional materials required of the contractor. The contractor is required to furnish and install a new ramp and stairs only.

Incorrect, a new viewing platform is to be provided and installed. NPS to receive salvaged wood for use elsewhere. 2

19 Will a CMR be involved in the construction phase?

Yes, a Construction Management Representative will be part of the team. 2

20 Will the A/E team be involved in vetting the submittals?

Yes, we will have the A/E team on contract to assist with submittals and

RFIs. 2

21 Can the prime contractor utilize the subcontractor's past performance? Yes. 2

It appears that the intent is to issue a notice to proceed in 2025, however can a partial notice to proceed be issued to allow for movement of materials and staging in the 2024 season?

Yes, this is possible provided the permit requirements are met and some key submittals are accepted. 2

April 4, 2024 1000 am

APIS 270691 01 31 00 - 1

042123 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. NPS/DSC Project Website

7. Project Meetings

8. Environmental Coordination

9. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make provisions to accommodate items scheduled for later installation.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

APIS 270691 01 31 00 - 2

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Contractor's Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

9. Commissioning activities

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and controls.

e. Indicate required installation sequences.

2. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.

APIS 270691 01 31 00 - 3

3. Follow NPS DSC Electronic Drawing Standards. See CAD/BIM (Computer Aided Design/Building Information Modeling) & Drafting Standards page > DSC Requirements section.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, and electrical elements. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

3. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

4. Electrical Work:

a. Runs of vertical and horizontal conduit 1-1/4 inches (32 millimeters) in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

C. Coordination Digital Data Files: Prepare coordination digital data files according to:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.

3. Contracting Officer will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 1 documents:

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Temporary Storm Water Pollution Prevention Plan (SWPP) https://www.nps.gov/dscw/ds-cad-bim-drafting.htm https://www.nps.gov/dscw/ds-cad-bim-drafting.htm

APIS 270691 01 31 00 - 4

11. Historic Preservation Treatment Plan (HPTP)

12. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

13. Site Logistics and Access Plan indicating the staging/material storage areas, fencing and proposed access path, construction phasing & impacts to visitor use and NPS operations.

Site Logistics and Access Plan shall be reviewed and approved by NPS prior to beginning of construction.

E. Provide items listed to Contracting Officer at least one week prior to Pre-Construction Conference, or as directed by Contracting Officer.

1. Failure to submit items may result in:

a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.

b. Work shall not commence until written Notice to Proceed has been issued and Certificates of Insurance and SF1413 documents are received for Contractor and all Subcontractors.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract

Time or Contract Sum, Contractor shall state impact in RFI.

8. Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

APIS 270691 01 31 00 - 5

C. RFI Form: Complete RFI Form on NPS/DSC Project Website as follows:

1. Enter general information at the top of the form.

2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.

3. Enter details of question and attach related documents.

4. Select "Submit Form" at bottom of page.

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.

1.6 PROJECT WEB SITE

A. Use NPS/DSC management software website for communication throughout contract period on:

1. Project directory

2. Project correspondence

3. Meeting agendas and minutes

4. Contract modifications forms and logs

5. RFI form and processing

6. Task and issue management

7. Photo documentation

8. Baseline schedule, schedule updates and calendar management

9. Submittal form and processing

10. Payment coordination documentation

11. Drawing and specification document hosting, viewing, and updating

12. Online document collaboration

13. Reminder and tracking functions

14. Archiving functions

15. Notification of submittal and RFI statuses and current responsible party

16. Permits and addendums

APIS 270691 01 31 00 - 6

B. Some documents are not suitable to be shared using the NPS/DSC management software website.

Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using NPS/DSC management software website and shall be coordinated with Project team as appropriate.

C. Submit to Contracting Officer a list of employees who will need access to the website. Users will receive an invitation to register from Department of Interior (DOI). Once registered on DOI website, user will be given access to NPS/DSC management software website.

D. All users will be required to have the following software packages:

1. Internet Explorer version 7 or later.

2. Adobe Acrobat Professional (Pro) version 9 or later.

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

5. Coordination of Subcontractors

6. Labor law application

7. Modifications

8. Payments to Contractor

9. Payroll reports

10. Contract time

11. Liquidated damages

12. Contractor Performance Evaluation

13. Display of Hotline posters

14. Notice to proceed

15. Correspondence procedures

16. NPS/DSC Project website

17. Acceptance/rejection of work

18. Progress meetings

19. Submittal procedures

20. NPS Final Accessibility Inspection

21. Environmental requirements

22. Permit requirements

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials

26. Value engineering

27. Schedule of Values

APIS 270691 01 31 00 - 7

B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings

b. Submittal status

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)

h. Construction Schedule update (provide updated Critical Path Method (CPM)).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements

C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:

a. Contract Documents

b. Options

c. Related RFIs

d. Related Change Orders

e. Purchases

f. Deliveries

g. Submittals

h. Review of mockups

i. Possible conflicts

j. Compatibility requirements

k. Time schedules

l. Weather limitations

m. Manufacturer's written instructions

n. Warranty requirements

o. Compatibility of materials

p. Acceptability of substrates

q. Temporary facilities and controls

APIS 270691 01 31 00 - 8

r. Space and access limitations

s. Regulations of agency(ies) with jurisdiction

t. Testing and inspecting requirements

u. Installation procedures

v. Coordination with other work

w. Required performance results

x. Protection of adjacent work

y. Protection of construction and personnel

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.

1.8 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection. Environmental Manager can also perform other duties on the project.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiarity with Environmental Management Systems (EMSs) such as International Organization for Standardization (ISO) 14001; familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of Waste Management Plan (WMP).

c. Implementation of Indoor Air Quality (IAQ) Management Plan.

d. Implementation of Storm Water Pollution Prevention Plan (SWPPP).

e. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.

f. Training for Contractor personnel in accordance with position requirements.

g. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements

2. Regulatory Requirements

3. Indoor Air Quality (IAQ) Management

4. Noise and Acoustics Management

5. Temporary Storm Water Pollution Prevention Environmental Management

6. Construction Waste Management

APIS 270691 01 31 00 - 9

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:

1. Overview of environmental issues related to building industry.

2. Overview of environmental issues related to Project.

3. Review of site-specific procedures and management plans:

a. Construction Waste Management

b. Indoor Air Quality (IAQ) Management

c. Noise and Acoustics Management

d. Temporary Storm Water Pollution Prevention

4. Pollution Prevention (P2) practices: Submit evidence of P2 training.

5. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.

1.9 PERMITS

A. General:

1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract, Contractor will not be considered an agent of the Government. Contractor shall comply with appropriate Federal, State and local laws.

B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.

1. The following Individual Permits (IP) and certificates were acquired from WIDNR. The Agency(ies) with Jurisdiction for this permit is Wisconsin DNR.

a. Little Sand Bay (LSB)

1) Dredge Permit (IP-NO-2023-4-03112)

2) Piers, Wharf and Marina Permit (IP-NO-2023-03113)

3) Shore Erosion Control (IP-NO-2023-4-03114)

4) Water Quality Certification (WQC) for discharges associated with construction

APIS 270691 01 31 00 - 10

b. Devils Island (DI)

1) Piers, Wharf and Marina permit (IP-NO-2023-2-03108)

2) Boat Shelter Permanent permit (IP-NO-2023-03109)

3) Shore Erosion Control permit (IP-NO-2023-03110)

4) Water Quality Certification (WQC) for discharges associated with construction

2. A standard permit was acquired for Little Sand Bay and Devils Island The Agency(ies) with Jurisdiction for this permit is United States Army Corps of Engineers (USACE).

a. Little Sand Bay Permit No. MVP-2023-01226-CCK

b. Devil Island Permit No. MVP-2023-00950-CCK

C. Time of Year Restrictions: According to the Water Quality Certificates (WQC) obtained from the WI DNR, in water work cannot occur at the project locations without a fish window exemption from the WI DNR during the following times.

1. Little Sand Bay- September 15th through June 15th

2. Devils Island- September 15th through July 1st

3. Fish Window Exemptions have been secured from the WI DNR for the 2024 construction season. In-water work can occur at the project sites during the following times:

a. Little Sand Bay- May 26th through September 15

b. Devils Island- June 3rd through September 15

4. In-water work outside of the dates listed above shall require approval by the WI DNR Fisheries Biologist prior to in-water work commencing.

D. Permit Expiration Dates

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.

a. Devils Island WIDNR Permit Expires January 3rd, 2027

b. Devils Island USACE Permit Expires December 31st, 2027

c. Little Sand Bay WINDR Permit Expires September 1st, 2026

d. Litte Sand Bay USACE Permit Expires December 31st, 2027

2. If construction will continue past the expiration dates listed above, extension may be granted by each respective agency prior to the expiration date of the approved permits.

E. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.

1. Electrical Utility Hookup - Bayfield Electric Cooperative

2. Gas Utility Hookup – NOT INCLUDED

3. Sewer Hookup - NOT INCLUDED

4. New Water Meter - NOT INCLUDED

5. Construction trailer, Utilities hookup permit – Bayfield County Planning and Zoning

APIS 270691 01 31 00 - 11

6. New Stationary Air Pollution Source - NOT INCLUDED

7. Street Closure – Wisconsin Department of Transportation Northwest Region, Bayfield

County Highway Department

8. Stormwater Pollution Prevention Permit – Wisconsin DNR

9. MS4 Stormwater Permit – NOT INCLUDED

10. Dewatering Permit – Wisconsin DNR

F. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.

G. Administrative Procedures:

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.

2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.

3. Upload permits to NPS/DSC management software website when permits are obtained.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

Click to edit Master title style

• Click to edit Master text styles

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Pre-Proposal Presentation Solicitation: 140P2024R0045

APIS 270691

Rehabilitate Waterfront at Little Sand Bay and Devils Island, Reconstruct Boathouse

National Park Service MWR Region

Apostle Islands National Lakeshore

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Park Introduction

• Apostle Islands National Seashore

• Located in Northern Wisconsin, near Bayfield, WI

• On Lake Superior

• 2 project sites - Devils Island and

Little Sand Bay

• Annual Visitation around 250,000

Lake Superior

Wisconsin

Minnesota

Michigan

Devils Island

Little Sand Bay

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Project Purpose ▪2017 storms impacted the structural integrity of both marinas and highlighted the need to improve resiliency.

▪Little Sand Bay Marina will be rehabilitated to improve resiliency, extend design life, reduce operations and maintenance costs, and provide accessibility.

▪Historic Devils Island Marina and Boathouse will be replaced and access will be restored to the island.

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Little Sand Bay Orientation

• Adjacent developed area includes NPS visitor center, kayak launch, historic

Hokenson fishery; Town of Russell dock, playground, picnic area, public beach, and campground.

• Little Sand Bay is an inholding within the Red Cliff Reservation, providing tribal boat access for fishing, hunting & gathering to park islands & surrounding waters.

• Only mainland NPS and public access to half of the park and safe harbor; fastest response for search & rescue and law enforcement.

• Fueling station for park boats operations. Public Beach and Kayak Launch

Boat Slips and FuelingCamping and Visitor Center

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Little Sand Bay Orientation – Marina Overview

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Little Sand Bay Orientation – North Dock and Breakwater

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Little Sand Bay Orientation – North and West Dock

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Little Sand Bay Orientation – West and South Docks

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Little Sand Bay Orientation – East Dock and Ramp

**Town of Russell Ramp, beach, and Dock

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Scope of Work – Little Sand Bay

• Demolition of west breakwater and crib structure per plans, deck removal, removal of finger piers, removal of timber framing, salvage sheet pile, and removal of pier decking with disposal of items.

• Removal and storage of existing viewing platform.

• Installation of viewing platform on new dock with stair structure.

• Dredging and placement of soil at Hokenson Dock Location,

• Installation of riprap, grading, concrete placement, pile placement and tie-ins, crib extension, wave return, sheet pile, H-

Pile and wale at obstruction, deck surface (west and north dock), water quality conduits, handrail and stone revetment.

• Installation of land side accessible ramp and kayak launch route;

• Electrical Improvements.

Bid Options:

• Construct Breakwater Extension (CLIN 06 Bid Option 1)

• Rehabilitate East Dock (CLIN 07 Bid Option 2)

• Roll On/Roll Off Ramp (CLIN 08 Bid Option 3)

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Devils Island Orientation

• Historic Devil's Island dock – only safe harbor, access to island & historic light station

• Harbor is the start of the historic 1-mile trail to the light station

• 19 miles from Little Sand Bay

• Extreme weather exposure

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Devils Island Orientation – East

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Devils Island Orientation - West

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Devils Island Orientation – Boathouse Location

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Devils Island Orientation – Retaining Wall

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Scope of Work – Devils Island

• Reconstruct boathouse

(removed and partially salvaged)

• Demo, removal, and construction of west and east docks

• Demo and construction of retaining wall

• Construction of stone breakwater, landing craft unloading area stone, grading, and gravel path

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

• Maintain the following:

• Harbor passage

• NPS boat slips (2)

• NPS access to fueling

• Public use of dock and beach

• Public use of kayak launch

• Road access

Operations and Visitor Access During Construction

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Staging

Roys Point Little Sand Bay

• Roys Point – Contractor Parking, staging area, and barge staging

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Limits of Construction and Staging

Little Sand Bay

• Little Sand Bay – Staging area in parking lot and small area by water

• Devils Island Marina – No staging

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Government Furnished Permits Wisconsin Department of Natural Resources Little Sand Bay

• Dredge Permit (IP-NO-2023-4-03112)

• Piers, Wharf and Marina Permit (IP-NO-2023-03113)

• Shore Erosion Control (IP-NO-2023-4-03114)

• Water Quality Certification (WQC) for discharges associated with Construction

Devils Island

• Piers, Wharf and Marina permit (IP-NO-2023-2-03108)

• Boat Shelter Permanent permit (IP-NO-2023-03109)

• Shore Erosion Control permit (IP-NO-2023-03110)

• Water Quality Certification (WQC) for discharges associated with construction

U.S. Army Corps of Engineers

• Little Sand Bay Permit No. MVP-2023-01226-CCK

• Devil Island Permit No. MVP-2023-00950-CCK

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023

• SOLICITATION NO. 140P2024R0045

SUMMARY OF SOLICITATION INFORMATION

• PRE PROPOSAL MEETING – April 4, 2024 10am

• PRE PROPOSAL QUESTION CUTOFF DAY– 4/24/2024

• OFFERS DUE –May 1, 2024 1:00 pm MDT

• SECTION L – 52.216-1 – Type of Contract – Firm Fixed Price

• NAICS Code: 237990

• THIS IS A COMPETIVE PROCUREMENT WITH SET-ASIDE FOR SMALL BUSINESS

• Notice of award (estimated) to be around June 2024

SOLICITATION INFORMATION & CRITERIA

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

▪ Key Points for Bid content and submission:

▪ Submission is by electronic mail. The email address for receiving proposals is noted in Section L as: Edwin_Berry@nps.gov and Stormy_Gallagher@nps.gov

• Include all information required by Section L when you email your proposal

• Please submit proposals in two separate volumes (Price & Technical)

• Please follow the page number limitations as specified in Section L

• See the file size limitations in Section L

• Offerors are encouraged to make their own arrangements to visit the site

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Solicitation – Important Clauses

▪ Section F – 52.211-10 – Commencement, Prosecution,

▪ and Completion of Work (335 Calendar Days after Receipt of the NTP to include winter shutdown)

▪ Section F – 52.211-12 – Liquidated Damages—Construction ($1,167.69 per calendar day)

▪ Section H – Special Clause 2: Key Personnel (Project Manager, Superintendent, QC Manager (can be combined with other roles), Safety Manager (can be combined with other roles)– No substitutions for 120 days)

▪ Section H – Special Clauses for Key Trades

▪ 52.228-15 – Performance and Payment Bonds—Construction (Note: Requires resubmittal as contract amount increases)

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

Solicitation – Important Clauses (continued)

▪ 52.232-27 – Prompt Payment for Construction Contracts (14 days)

▪ 52.236-5 – Material and Workmanship

▪ 52.236-6 -- Superintendence by the Contractor

▪ 52.236-9 - Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

VOLUME I , TECHNICAL PROPOSAL– FORMAT, ORGANIZATION, CONTENTS

▪ 1. FORMAT: Submit (1) one electronic copy. No hard copies shall be submitted.

▪ 2. ORGANIZATION: Include a Table of Contents with tabs for hard copy formats and folders and files for electronic formats named as follows:

− FACTOR 1 – TECHNICAL APPROACH & SCHEDULE

− FACTOR 2 – EXPERIENCE

− FACTOR 3 –MANAGEMENT APPROACH

− FACTOR 4 – SCHEDULE

− FACTOR 5 – KEY PERSONNEL EXPEREINCE

− PAST PERFORMANCE QUESTIONNAIRES

− OTHER SUBMITTALS

− PROPOSED EQUALS

− HAZARDOUS MATERIALS

SOLICITATION INFORMATION & CRITERIA (Refer to the Solicitation for complete information)

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

VOLUME II, BUSINESS AND PRICE PROPOSAL – FORMAT, ORGANIZATION, CONTENTS

▪ 1. FORMAT: Submit one Submit one (1) original signed electronic copy. No hard copies shall be submitted.

▪ 2. ORGANIZATION: Include a Table of Contents with tabs for hard copy formats and folders and files for electronic formats named as follows:

• SF1442

• AMENDMENTS

• SECTION B PRICE SCHEDULE

• SF 24 BID BOND

• SECTION K REPRESENTATIONS AND CERTIFICATIONS

• GENERAL REFERENCES

SOLICITATION INFORMATION & CRITERIA (Refer to the Solicitation for complete information)

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

SECTION M – EVALUATION FACTORS FOR AWARD

BASIS FOR AWARD:

1. The Government will conduct a source selection using the Best Value Continuum Tradeoff Process defined at FAR Part 15.1. The Contracting Officer (CO) will obligate and award a contract to the offeror who submits a proposal the Source Selection Authority (SSA) determines conforms to solicitation requirements; is fair and reasonable; and provides the best value to the government considering all evaluation factors combined as detailed below.

For this acquisition, the CO is the SSA.

2. The Government may accept other than the lowest priced proposal when the perceived benefits of a higher priced proposal merit the price differential.

3. Additionally, the Government may award a contract without entering into discussions.

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

EVALUATION FACTORS (Listed in Descending Order of Importance)

▪ FACTOR 1 – TECHNICAL APPROACH & SCHEDULE

▪ FACTOR 2 – EXPERIENCE

▪ FACTOR 3 –MANAGEMENT APPROACH

▪ FACTOR 4 – SCHEDULE

▪ FACTOR 5 – KEY PERSONNEL EXPEREINCE

▪ PAST PERFORMANCE QUESTIONNAIRES

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

CONTRACT PRICE LIST (Refer to the Solicitation for complete information).

Section B – Supplies or Services and Prices Contract Price Schedule

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023PPFL ● 2023

QUESTIONS DURING THE SOLICITATION PHASE

• All questions must be submitted in writing via email to both the CO,and the CS as follows:

Edwin_Berry@nps.gov

Stormy_Gallagher@nps.gov

• Changes to the Solicitation document shall only be made by written amendment posted as an amendment to the solicitation document. Offerors are required to fill out and sign the acknowledgment of amendments received (SF1442 Section 19) and include this when submitting our offer on the Form 1442.

PRE-PROPOSAL CONFERENCE QUESTIONS

• Second level

• Third level

• Fourth level

• Fifth level

PPFL ● 2023

PPFL ● 2023

Thank you

Re

APIS 270691

APIS270691 Presentation for Bidders.pdf
Slide 1: APIS 270691 Rehabilitate Waterfront at Little Sand Bay and Devils Island, Reconstruct Boathouse
Slide 2: Park Introduction
Slide 3: Project Purpose
Slide 4: Little Sand Bay Orientation
Slide 5
Slide 6
Slide 7
Slide 8
Slide 9
Slide 10: Scope of Work – Little Sand Bay
Slide 11: Devils Island Orientation
Slide 12: Devils Island Orientation – East
Slide 13: Devils Island Orientation - West
Slide 14: Devils Island Orientation – Boathouse Location
Slide 15: Devils Island Orientation – Retaining Wall
Slide 16: Scope of Work – Devils Island
Slide 17
Slide 18
Slide 19
Slide 20: Government Furnished Permits
Slide 21
Slide 22
Slide 23: Solicitation – Important Clauses
Slide 24: Solicitation – Important Clauses (continued)
Slide 25: SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS VOLUME I , TECHNICAL PROPOSAL– FORMAT, ORGANIZATION, CONTENTS
Slide 26: SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS VOLUME II, BUSINESS AND PRICE PROPOSAL – FORMAT, ORGANIZATION, CONTENTS
Slide 27: SECTION M – EVALUATION FACTORS FOR AWARD
Slide 28: EVALUATION FACTORS (Listed in Descending Order of Importance)
Slide 29: Section B – Supplies or Services and Prices Contract Price Schedule
Slide 30: QUESTIONS DURING THE SOLICITATION PHASE
Slide 31
Section 01 31 00 - Project Management And Coordination - REV. 1 Amendment 2.pdf
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits – Contractor Provided
C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depe...
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.