B08 - Attachment 3 - Proposed LOE.docx

DOCX document 20 KB Posted

Attached to
RADIO FREQUENCY IDENTIFICATION (RFID)_Amendment 004 Federal contract opportunity
Solicitation number
HT942524R0130
Issued by
Defense Health Agency

About this file

This document is an Attachment titled "Proposed Level of Effort" related to a federal contract opportunity for "Enhancing Inventory Management and Biosecurity Surveillance Using Radio Frequency Identification (RFID)". It provides the government's estimated level of effort for this 6-month project, including labor categories and hours for a Project Manager, Field Engineers for deployment/integration and testing/validation, and a Project Manager for training and operational handover. The total estimated level of effort is 320 hours. The associated federal contract opportunity is a Solicitation (HT942524R0130) from the Defense Health Agency to develop customized RFID technology to improve inventory management and biosecurity within the U.S. Army Medical Research Institute of Infectious Diseases (USAMRIID) high containment laboratories. The SOO encourages innovative RFID solutions that meet USAMRIID's technical and cost-effectiveness objectives without prescribing specific methodologies.

View the file

Other files for this federal contract opportunity

Other files attached to RADIO FREQUENCY IDENTIFICATION (RFID)_Amendment 004, newest first.
File Type Posted
HT942524R0130 Amendment 003.docx DOCX document
HT942524R130 Amendment 002.docx DOCX document
B08 - Attachment 6 - Price Proposal_Amendment 001.xls XLS spreadsheet
Solicitation HT9425-24-R-0130_Amendment 001.docx DOCX document
B08 - Attachment 8 - Statement of Objectives_Amendment 001.docx DOCX document
B08 - Attachment 9 - Deliverables.docx DOCX document
B08 - Attachment 8 - Statement of Objectives.docx DOCX document
B08 - Attachment 6 - Price Proposal.xls XLS spreadsheet
B08 - Attachment 5 - IMP-IMS-Guide-2023.pdf PDF
B08 - Attachment 10 - Statement of Work Template.docx DOCX document
B08 - Attachment 4 - MIL-STD-881F.pdf PDF
B08 - Attachment 1 - Organizational and Consultant Conflicts of Interest_Deliverable 10.docx DOCX document
B08 - Attachment 7 - Non-Disclosure Agreement_Deliverable 5.doc DOC document
B08 - Attachment 2 - QAP Template_Deliverable 4.docx DOCX document
Solicitation HT942524R0130 26 July 2024.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3 –Proposed LOE

ATTACHMENT 3 – ESTIMATED LEVEL OF EFFORT

Title: ENHANCING INVENTORY MANAGEMENT AND BIOSECURITY SURVEILLANCE USING RADIO FREQUENCY IDENTIFICATION (RFID).

Estimated Level of Effort:

The Government estimates that this order will require an approximate level of effort, as outlined below, to accomplish the tasks identified in the SOO. Please note that the Government estimate is only put in place for Offerors to ascertain the approximate or estimated level of effort for this task. However, this is not to be construed as either mandatory or necessarily the best technical approach. It is only in place as a reference to allow Offerors to better understand the general scope of this effort from the Government’s perspective. The Government is seeking the best level of effort and labor mix that the Offeror has determined is right to accomplish the mission contained in this task statement. The Offeror is not bound to propose these labor categories or quantities below; rather, it is expected to provide its best solution citing the labor mix and quantity required to accomplish the tasks. If the Offeror has determined either the following labor categories or overall level of effort provided are not the best technical solution, it is strongly encouraged and expected to submit a level of effort consistent with all of the cost/price and non-cost/price aspects of the Offeror’s approach.

6 Month Period of Performance

Labor Category
Estimated Hours

Project Manager (planning & design, technology selection)

Field Engineer (deployment & integration)

Field Engineer (testing & validation)

Project Manager (training & operational handover)

Total Estimated Hours
320