B08 Attachment 2 General Design Submission Requirements.docx

DOCX document 14 KB Posted

Attached to
Building 7, Bays 1 and 2 Renovations at Tobyhanna Army Depot
Solicitation number
W25G1V-21-R-0033
Issued by

About this file

This document outlines general design submission requirements for a federal construction project. It requires five design submissions - concept, 35%, 65%, 95%, and 100% - to be delivered within specified timeframes. Electronic CADD drawings and PDFs are required at each stage. A Document of Record noting changes between submissions must also be provided. The construction completion date is estimated at 548 calendar days following the final 182-day design period, totaling 730 calendar days for the project. The Army Contracting Command within the Department of the Army Materiel Command is the contracting agency.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL DESIGN SUBMISSION REQUIREMENTS

Note: A DOR (Document of Record) notating (listing) the changes made between each submission shall be required by the contractor.

1. CONCEPT DESIGN SUBMISSION

1. 35% DESIGN SUBMISSION

1. 65% DESIGN SUBMISSION

1. 95% DESIGN SUBMISSION

1. 100% DESIGN SUBMISSION

1. Electronic copy (CADD drawing and PDF) and paper copies are required at each submission

SUBMISSION SCHEDULE

The timeframes below are subject to change by the Contracting Officer.

Event
Duration
Govt. Review
Cumulative
Concept
14 calendar days
14 calendar days
28 calendar days
35% Design
21 calendar days
21 calendar days
70 calendar days
65% Design
21 calendar days
21 calendar days
112 calendar days
95% Design
21 calendar days
21 calendar days
154 calendar days
100% Design
14 calendar days
14 calendar days
182 calendar days
Complete Construction (548 calendar days) + Design (182 calendar days)
Total Project: 730 calendar days

The Government may extend its review time when reasonable and necessary without penalty or claim. The Government review will be primarily for determining if the design is in conformance with the scope.

It is not the intent of the Government to check the Architect-Engineer’s (A-E’s) work in detail. The A-E shall be responsible for incorporating each review comment or providing written rationale for exclusion at each submission.