This document appears to be the technical specifications for the Folger Park Sidewalk Rehabilitation project, under PMIS No. 245149, being conducted by the Department of the Interior's National Park Service (NPS) National Capital Parks-East.

The key details are:

  • The work includes demolition and replacement of existing asphalt and stone pavers on concrete base walks, removal and refurbishing of existing site furnishings, and fine regrading and reseeding of adjacent planting and turf areas.
  • The project requires protection of existing trees during construction, compliance with OSHA guidelines, and adherence to the Archeological Resources Protection Act.
  • The contractor is responsible for obtaining all necessary permits, coordinating with utility companies, and providing temporary facilities and controls.
  • Administrative requirements include submittal procedures, construction schedules, quality control, accident prevention plans, and payroll reports.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL PARK SERVICE

U.S. DEPARTMENT OF THE INTERIOR

INTERIOR REGION 1 - NATIONAL CAPITAL AREA

DESIGN AND CONSTRUCTION BRANCH

WASHINGTON, D.C.

Folger Park Sidewalk Rehabilitation

SPECIFICATIONS

Folger Park (NACE) Washington, DC

FINAL CONSTRUCTION DOCUMENTS

March 24, 2023

Prepared by:

AECOM

Arlington, VA

NPS PMIS No. 245149 Image Credit: AECOM

NPS Revised on 4/16/24

TABLE OF CONTENTS

NATIONAL PARK SERVICE

NATIONAL CAPITAL REGION

2nd STREET S.E. AND 3rd STREET S.E.

WASHINGTON, DC

FOLGER PARK SIDEWALK REHABILITATION

Final Construction Documents

March 24, 2023

SPECIFICATIONS

Table of Contents

DIVISION 01 GENERAL REQUIREMENTS

01 10 00 01 10 00 01 33 00 01 33 00 01 50 00 01 50 00 01 56 39

Summary of Work Summary of Work Submittal Procedures Submittals Temporary Facilities and Controls Temporary Services, Facilities and Controls Temporary Tree and Plant Protection Product Requirements Execution and Closeout Requirements Closeout Procedures

DIVISION 02 EXISTING CONDITIONS

02 41 19 Selective Demolition

DIVISION 03 CONCRETE

03 30 00 Cast-In-Place Concrete

NPS Revised on 4/16/24

01 67 00

01 77 00 01 70 00

TABLE OF CONTENTS

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants

DIVISION 09 FINISHES

09 91 11 Exterior Cleaning and Painting

DIVISION 31 EARTHWORK

31 10 00 Site Clearing 31 20 00 Site Excavation and Grading

DIVISION 32 EXTERIOR IMPROVEMENTS

32 12 16 Asphalt Walks 32 14 00 Unit Paving 32 33 00 Site Furnishings 32 91 13 Soil Preparation 32 92 00 Turf and Grasses 32 93 00 Plants

FOLGER PARK SIDEWALK REHABILITATION

PMIS No. 245149

01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00

SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, and other Division 01 Specification Sections, apply to this Section.

1.2 DESCRIPTION: This section covers the following:

A. Location and Description of Work B. Coordination C. Project Meetings D. Construction Facilities and Temporary Controls E. Materials and Equipment F. Quality Requirements G. Accident Prevention H. Archeological Protection I. Permits, Fees and Responsibilities

1.3 LOCATION AND DESCRIPTION OF WORK

A. The work of this contract is located at Folger Park, located at D Street SE between 2nd Street and 3rd Street SE, Washington, DC.

B. The work of this contract includes, but not limited to the following work, as detailed in the specification sections and as shown on the attached drawings:

1. Protection of existing trees during construction/demolition activities

2. Demolition and disposal of existing asphalt on concrete base walks; replacement of asphalt on concrete base walks “in-kind”

3. Demolition and disposal of broken stone pavers on concrete base; install new stone pavers on concrete base “in-kind”

4. Removal, storage, refurbishing, and re-setting of existing site furnishings, including trash receptacles and park benches.

5. Fine regrading, topsoiling, and re-seeding impacted adjacent planting and turf areas

1.4 COORDINATION

A. Coordinate construction operations included in various sections of these specifications to assure efficient and orderly installation of each part of the work. Coordinate construction operations included under different sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in the sequence required to obtain the best results where installation of one part of the work depends on installation of other components, before or after its own installation.

01 11 00 - 2

SUMMARY OF WORK

2. Coordinate installation of different components to assure maximum accessibility for required maintenance, service, and repair.

3. Make provisions to accommodate items scheduled for later installation.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and assure orderly progress of the work. Such administrative activities include, but are not limited to, the following:

1. Preparation of contractor’s construction schedule.

2. Installation and removal of temporary facilities.

3. Progress meetings.

4. Project closeout activities.

1.5 PROJECT MEETINGS

A. General: Contracting Officer (CO) /Contracting Officer’s Representative (CS/COR) will schedule and conduct meetings and conferences at project site, unless otherwise indicated.

1. Attendees: Authorized representatives of Acquisition Division and park staff;

Contractor and its superintendent; major subcontractors; manufacturers; suppliers;

and other concerned parties shall attend the conference, shall be familiar with project and shall be authorized to conclude matters relating to work.

B. Pre-Construction Conference: CO/CS/COR will schedule a Pre-Construction Conference before starting construction, at a time convenient to park staff and the contractor. The conference will be held at the project site or another convenient location.

1. Agenda: Subjects to be discussed will include the following:

a. Correspondence – General Procedure.

b. Contracting Officer’s Authorized Representatives.

c. Changes.

d. Submittals for Approval (General).

e. Submittals for Approval (Shop Drawings and Samples).

f. Subcontractors.

g. Labor Standards.

h. Payroll Reports.

i. Working Hours

j. Plans and Specifications.

k. Accident Prevention.

l. Park Rules and Regulations.

m. Contractor Parking and Personnel Passes

n. Payments to Contractor.

o. Liquidated Damages – Construction.

p. Tentative Construction Schedule.

C. Pre-Installation Conferences: If required, conduct a pre-installation conference at the project site before each construction activity that requires coordination with other construction.

01 11 00 - 3

SUMMARY OF WORK

D. Progress Meetings: If necessary, the CO/CS/COR will schedule and conduct progress meetings at designated intervals. Coordinate dates of meetings with preparation of payment requests.

1.6 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS (See Section 01 50 00)

A. For FAR Clauses see contract. .

1.8

MATERIALS AND EQUIPMENT

A. For FAR Clause see contract.

QUALITY REQUIREMENTS

A. Contractor shall be responsible for all work to comply with the latest edition of the International Building Code (IBC) and family of International Codes including but not limited to: International Plumbing Code, International Electrical Code and work shall conform to the Life Safety Code.

B. Testing and inspecting services may be required to verify compliance with requirements specified or indicated. These services do not relieve the Contractor of responsibility for compliance with the Contract requirements.

1. Specific quality-control requirements for individual construction activities as specified in the Sections may also cover production of standard products.

2. Requirements for Contractor to provide quality-control services as directed by the CO/ CS/COR or authorities having jurisdictions are not limited by provisions of this Section.

C. Submittals (See Section 013300 Submittals for detailed requirements)

1. Qualification Data: For testing agencies specified in “Quality Assurance” section to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

2. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, confirming that the products and systems are in compliance with performance and design criteria indicated. Include list cmadison Highlight

01 11 00 - 4

SUMMARY OF WORK

of codes, loads, and other factors used in performing these services.

D. Quality Assurance

1. Fabricator Qualification: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capability to produce required units.

2. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by the manufacturer to inspect installation of manufacturer’s products that are similar in material, design, and extent to those indicated for this Project.

3. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

4. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance.

5. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in the jurisdiction where the Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material design, and extent.

6. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities that are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

a. Requirement for specialists shall not supersede building codes and similar regulations governing the Work, nor interfere with local trade-union jurisdictional settlements and similar conventions.

7. Testing Agency Qualifications: An agency with the experience and capability to conduct testing and inspecting indicated, as documented by ASTM E 548, and that specializes in types of tests and inspections to be performed.

8. Pre-construction Testing: Testing agency shall perform pre-construction testing for compliance with specified requirements for performance and test methods.

a. Contractor responsibilities include the following:

1. Provide test specimens and assemblies representative of proposed materials and construction. Provide sizes and configurations of assemblies to adequately demonstrate capability of product to comply with performance requirements.

01 11 00 - 5

SUMMARY OF WORK

2. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying work.

b. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to CO/CS/COR, with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

E. Quality Control

1. Contractor Responsibilities: Unless otherwise indicated, provide quality-control services specified and required by these contract documents.

a. Contractor shall provide a qualified project manager or superintendent on site during active daily construction activities.

b. Contractor shall engage a qualified-independent testing agency to perform these quality-control services.

c. Contractor must maintain a set of contract plans and specifications on the job-site at all times during the contract period. Contractor shall provide copies of the contract plans and specifications to all sub-contractors.

2. Manufacturer’s Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing.

3. Testing Agency Responsibilities: Cooperate with CO/CS/COR and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

a. Notify CO/CS/COR and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

b. Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

c. Submit a certified written report, in duplicate, of each test, inspections, and similar quality-control service through Contractor.

d. Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the work.

4. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and quality-control services with a minimum of delay and to avoid the necessity of removing and replacing construction of accommodate testing and inspecting.

1.9 ACCIDENT PREVENTION

A. For FAR Clause see contract.

01 11 00 - 6

SUMMARY OF WORK

B. Submit Accident Prevention Plan.

C. All work shall be in accordance with standard Occupational Safety and Health Administration (OSHA) guidelines and regulations.

1.10 ARCHEOLOGICAL PROTECTION

A. Archeological Resources Protection Act (ARPA) of 1979 (Public Law (P.L.) 96-95; 93 United States Statues at Large (Stat.) 712): defines archeological resources as any material remains of past human life or activities that are of archeological interest and at least 100 years old; Section 4 of the statute describes the requirements that must be met before Federal authorities can issue a permit to excavate or remove any archeological resource on Federal or Indian lands; the curatorial requirements of artifacts, and other materials excavated or removed.

1. Archeological Discovery: In the event that unanticipated archeological resources are uncovered during construction operations, the contractor will suspend operations at the discovery site, notify the Contracting Officer (CO), and Contracting Specialist (CS)/ Contracting Officer Representative (COR) who shall contact the Regional Archeologist or his representative, and continue operations in other areas, until such time as the National Park Service (NPS) has completed its compliance responsibilities under Section 106 of the 1966 National Historic Preservation Act, as amended.

2. Unanticipated Discovery of Human Remains (Anthropic Discovery): Should any human remains be encountered; excavations will stop and the CO/CS/COR will be notified immediately. DO NOT TOUCH, LEAVE THE REMAINS IN PLACE. The CO/CS/COR, in consultation with the Regional Archeologist or his representative, and the Park Superintendent shall determine the appropriate course of action, following the Department of the Interior’s guidelines on the treatment of human remains and appropriate Federal legislation.

3. WORK STOPPAGE: Contractor shall plan, schedule, and execute work to prevent stoppages at one area from stopping all work at construction site.

1.11 PERMITS, FEES AND RESPONSIBILITIES

A. In accordance with FAR 52.236-7: Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.

B. Permits, Licenses, and Certificates: It is the contractor’s responsibility to obtain and pay for all permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work. The Contractor shall be responsible for renewal of all required construction permits during the performance period of the contract. Submit all copies for the CO/COR’s records.

01 11 00 - 7

SUMMARY OF WORK

C. For the purpose of this contract, the Contractor will not be considered an agent of the Government. Therefore, the Contractor will comply with the appropriate Federal, State, and local laws.

D. Government Furnished Permits: During the development of the project’s design the permits listed below were negotiated and agreed to by the Government. The terms and provisions of these permits shall be adhered to for the duration specified in each permit.

1. A permit was acquired for DC BCIV Permit for DOEE Review of Erosion and Sediment Control with identification number BCIV 2300054 and ESC File No. 23-s20562. The Agencies with Jurisdiction for this permit is DC Department of Buildings (for routing to DOEE only) and DC Department of Energy and the Environment (DOEE).

E. Potential Permits: The permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist the contractor in determining which permits will be required for the contract’s chosen means and methods. The list shall not be considered complete, as it is the responsibility of the contractor to determine means and methods, and obtain the required permits. It is the responsibility of the Contractor to obtain and pay for all permits or utility fees required to legally conduct the work. It’s also the responsibility of the Contractor to renew all required construction permits from all agencies with jurisdiction for the duration of the project.

1. Street Closure – District Department of Transportation.

F. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.

G. Coordination with Utilities (Water, Sewer, Electric, Gas)

1. Coordination: Contact the Utility(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements. Coordinate utility service shutdown/startup with utility company in a timely manor to avoid delaying the work.

2. Contractor to pay all fees associated with shut down, start up, connections etc. to Utility to perform associated work.

H. Administrative Procedures:

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agencies or Utilities with Jurisdiction, Construction Manager, CO, CS/ COR, and Park to avoid conflicts and to ensure orderly execution of the Work.

2. Supply all needed information to Agency(ies) with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.

01 11 00 - 8

SUMMARY OF WORK

3. Submit copies of all obtained permits and paid fees to the CO/CS/COR.

PART 2 – PRODUCTS (Not Applicable)

PART 3 – EXECUTION (Not Applicable)

END OF SECTION 01 11 00

01 33 00 - 1

SUBMITTALS

SECTION 01 33 00

SUBMITTALS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, and other Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for submittals required for performance of the Work, including the following:

1. Submittal Procedures

2. Staff Names, Subcontractors and Qualifications

3. Contractor's Construction Schedule

4. Quality Control Reports and Daily Quality Control Construction Reports

5. Shop Drawings

6. Product Data

7. Samples

8. Contracting Officer’s Action

9. Requests for Information (RFIs)

10. Schedule of Values

11. Payroll Reports

12. Permits: See Section 011100

13. Accident Prevention Plan: See Section 011100

14. Performance Bonds, Liability Insurance Certificate, List of Sub-Contractors and SF1413's

15. Traffic Control Plan (see Section 01 50 00)

B. Related Sections: The following Sections contain requirements that relate to this Section:

1. Division 01 Section 01 11 00 "Summary of Work " specifies requirements for submittal of inspection and test reports.

2. Division 01 Section 01 70 00 "Execution and Closeout Requirements" specifies requirements for submittal of Project Record Documents, Operations & Maintenance Manuals and warranties at project closeout.

1.3 SUBMITTAL PROCEDURES

A. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.

1. Coordinate transmittal of different types of submittals for related elements of the Work so processing will not be delayed by the need to review submittals concurrently for coordination.

01 33 00 - 2

SUBMITTALS

a. The Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until all related submittals are received.

2. Processing: To avoid the need to delay installation as a result of the time required to process submittals, allow sufficient time for submittal review, including time for re-submittals.

a. Allow 2 weeks for initial review. Allow additional time if the Contracting Officer (CO) & Contracting Officer’s Representative (CS/COR) must delay processing to permit coordination with subsequent submittals.

b. If rejected, allow 2 weeks for reprocessing each submittal.

c. No extension of Contract Time will be authorized because of failure to transmit submittals to the Contracting Officer and CS/COR sufficiently in advance of the Work to permit processing or disapproved submittals by the CO/CS/COR for failure of meeting the contract requirements.

C. Submittal Transmittal: Package each submittal appropriately for transmittal and handling. Submit separate submittal form packages for each CSI Specification Division. Transmit each submittal from the Contractor to the Contracting Officer’s Representative using the NPS SUBMITTAL Form 01 33 10 sample form (Separate file) (CM-16 Transmittal Form). Fill out submittal form completely, providing required information on each line of the form. The Contracting Officer and Contracting Officer’s Representative will not accept submittals received from sources other than the Contractor.

1. On the transmittal, record relevant information and requests for data. On the form, or separate sheet, record deviations from Contract Document requirements, including variations and limitations. Include Contractor's certification that information complies with Contract Document requirements.

2. Re-submittals: Note date and content of previous submittal. Note date and content of revision in label or title block and clearly indicate extent of revision. Re-submit submittals until they are marked “Approved” or “Approved with notations”.

3. Subcontractor Submittals: The prime contractor is responsible of reviewing and certifying in writing that the subcontractor data and information in the submittals are in complaince with the contract requirements before submitting to the Contracting Officer (CO) and Contracting Officer’s Representative (CS/COR). The prime contractor shall not submit to the CO/CS/COR any subcontractor submittals with data and information that are not in compliance with the contractor requirements.

4. Submittals, regardless of sources, shall be reviewed and certified by the prime conractor that they are in compliance with the contract requrements when submitting to the CO/CS/COR.

CI. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations.

1.4 STAFF NAMES, SUBCONTRACTORS AND QUALIFICATIONS

A. Contractor’s Principal Staff: No less than (14) fourteen days prior to of commencement of construction operations, submit a list of the contractor’s principal staff assignments, including the job site superintendent, project manager, and other personnel in attendance at the project site. Identify individuals; their qualifications, construction experience, duties and responsibilities. List shall include names, cell number and email address.

B. Job Site Superintendent: A minimum of three years of experience in the construction field and has the ability to effectively manage the construction work performed by the prime contractor and/or the subcontractors. The Superintendent must have adequate and in-depth knowledge of the contract

01 33 00 - 3

SUBMITTALS

requirements as detailed in the contract specifications and plans.

C. List of Subcontractors: No less than (14) fourteen days prior to of commencement of construction operations, submit a list of the subcontractor assignments, including the job site superintendent, project manager, and other personnel in attendance at the project site. Identify individuals; their qualifications, construction experience related to this specific project, duties and responsibilities.

1.5 CONTRACTOR'S CONSTRUCTION SCHEDULE

B. Bar-Chart Schedule: Prepare a fully developed, horizontal bar-chart-type, contractor's construction schedule. Submit no less than (14) fourteen calendar days prior to commencement of work as mutually agreed and stated in the Notice To Proceed.

2. Provide a separate time bar for each significant construction activity. Schedule shall graphically indicate a period for contractor submittals (noting long lead items), Notice to Proceed, all critical components of work, and projected dates for Final Acceptance and Final Inspection.

2. Provide a continuous vertical line to identify the first working day of each week.

3. Schedule Updating: Revise the Schedule immediately after each meeting or other activity where revisions have been recognized or made.

4. The schedule shall be prepared using MS Project or compatible scheduling program.

5. Electronically submit in both .mpp and .pdf formats. Transmit via email attachment to the CO/

CS/COR.

1.6 QUALITY CONTROL REPORTS AND DAILY CONSTRUCTION REPORTS

C. Submit quality-control submittals, including design data, certifications, manufacturer's instructions, manufacturer's field reports, and other quality-control submittals as required under other sections of the Specifications.

D. Certifications: Where other sections of the Specifications require certification that a product, material, or installation complies with specified requirements, submit a notarized certification from the manufacturer certifying compliance with specified requirements.

3. Signature: Certification shall be signed by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.

E. Inspection and Test Reports: Prepare and submit certified written reports of inspection and testing from independent testing agencies that include the following.

1. Date of issue.

2. Project title and number. Contract number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests or inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

10. Ambient conditions at time of sample taking and testing and inspecting.

11. Comments or professional opinion on whether tested or inspected Work complies with the

Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on testing reinspecting.

01 33 00 - 4

SUBMITTALS

D. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site, including photos as needed. Submit at weekly intervals.

1. List of subcontractors at Project site.

2. List of separate contractors at Project site.

3. Approximate count of personnel at Project site.

4. Equipment at Project site.

5. Material deliveries.

6. High and low temperatures and general weather conditions, including presence of rain or snow.

7. Accidents.

8. Meetings and significant decisions.

9. Unusual events (see special reports).

10. Stoppages, delays, shortages, and losses.

11. Meter readings and similar recordings.

12. Emergency procedures.

13. Orders and requests of authorities having jurisdiction.

14. Change Orders received and implemented.

15. Construction Change Directives received and implemented.

16. Services connected and disconnected.

17. Equipment or system tests and startups.

18. Partial completions and occupancies.

19. Substantial Completions authorized.

DI. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information.

Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

1.7 SHOP DRAWINGS

A. Prepare and submit project specific information, drawn accurately to scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Standard information prepared without specific details or reference to the Project is not a Shop Drawing.

B. Shop Drawings include fabrication and installation Drawings, setting diagrams, schedules, patterns, templates and similar Drawings. Include the following information:

1. Dimensions.

2. Identification of products and materials included by sheet and detail number.

3. Fabrication and installation drawings.

4. Compliance with specified standards.

5. Notation of coordination requirements and Relationship to adjoining construction clearly indicated.

6. Notation of dimensions established by field measurement.

7. Format PDF Sheet Size: Except for templates, patterns and similar full-size Drawings, submit

Shop Drawings on sheets at least 11 by 17 inches but no larger than 24 by 36 inches. Submit (3) three paper copies as directed by CO/CS/COR.

8. Submit shop drawings electronically as a single file in Adobe Acrobat (.PDF) and autocad (.dwg) formats as required by CO/CS/COR. Electronic submission shall be transmitted to the CO/CS/ COR via email attachment or Contractor’s FTP website posting if available. Each file max size is 10MB, which

01 33 00 - 5

SUBMITTALS

may require dividing the PDF file in manageable sections.

9. The CO/CS/COR will email a signed PDF electronic file marked with action taken and corrections or modifications required.

10. The contractor shall certify on the shop drawings that they are in compliance with the contract requirements. Also the Contractor shall require their subcontractors to certify that their shop drawings are in compliance with the contract requirements. Seal and signature of professional engineer if specified.

11. Do not use Shop Drawings without an appropriate final stamp indicating action taken by the Contracting Officer (CO) and Contracting Officer’s Representative (CS/COR).

1.8 PRODUCT DATA

A. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.

B. Collect Product Data into a single submittal for each element of construction, type of product, equipment, or system. Product Data includes information, such as manufacturer's installation instructions, catalog cuts, standard color charts, roughing-in diagrams and templates, standard wiring diagrams, and performance curves.

1. Product Data shall be marked to show applicable choices and options. Where Product Data includes information on several products that is not required, mark to indicate the applicable information. Include the following information:

a. Manufacturer's printed recommendations, specifications and installation instructions.

b. Compliance with trade association standards.

c. Compliance with recognized testing agency standards.

d. Application of testing agency labels and seals.

e. Notation of dimensions verified by field measurement.

f. Notation of coordination requirements.

2. Do not submit Product Data until compliance with requirements of the Contract Documents has been confirmed.

3. Submittals: Submission shall be electronically transmitted to the CO/CS/COR via email attachment, Contractor’s FTP website posting, or NPS Microsoft Teams/Sharepoint as directed by the CO/CS/COR. Submit in .PDF file format. Each file max size is 10MB, which may require dividing the PDF file in manageable sections. Also submit paper copies for required shop drawings when requested by the CO/CS/COR. Submit using the NPS SUBMITTAL Form CM

16. The CS/COR will email a signed PDF electronic file marked with action taken and corrections or modifications required.

a. Do not proceed with installation until a copy of Product Data is in the Installer's possession.

b. Do not permit use of unmarked copies of Product Data in connection with construction.

4. The contractor shall certify on the product data submittals that they are in compliance with the contract requirements. Also the Contractor shall require their subcontractors to certify that their product data submittals are in compliance with the contract requirements.

1.9 SAMPLES

01 33 00 - 6

SUBMITTALS

A. Submit full-size, fully fabricated Samples cured and finished, as specified, and physically identical with the material or product proposed. Samples include partial sections of manufactured or fabricated components, cuts or containers of materials, color range sets, and swatches showing color, texture, and pattern.

1. Mount or display Samples in the manner to facilitate review of qualities indicated. Prepare Samples to match the Government’s sample. Include the following:

a. Specification Section numbers and reference.

b. Generic description of the Sample.

c. Sample source.

d. Product name or name of the manufacturer.

e. Compliance with recognized standards.

f. Availability and delivery time.

2. Submit Samples for review of size, kind, color, pattern, and texture. Submit samples for a final check of these characteristics with other elements and a comparison of these characteristics between the final submittal and the actual component as delivered and installed.

a. Where variation in color, pattern, texture, or other characteristic is inherent in the material or product represented, submit at least 3 multiple units that show approximate limits of the variations.

b. Samples shall illustrate workmanship, fabrication techniques, and details of assembly, connections, operation, and similar construction characteristics.

c. On the transmittal, indicate special requests regarding disposition of Sample submittals.

Samples not incorporated into the Work, or otherwise designated as the Owner's property, are the property of the Contractor and shall be removed from the site prior to Final Acceptance.

3. Submittals: Except for Samples illustrating assembly details, workmanship, fabrication techniques, connections, operation, and similar characteristics, submit three (3) sets. The Contracting Officer’s Representative will return one (1) set marked with the action taken.

Submit with NPS SUBMITTAL Form CM 16.

4. Maintain sets of Samples, as returned, at the Project Site, for quality comparisons throughout the course of construction.

1.10 CONTRACTING OFFICER’S ACTION

A. Except for submittal's for the record or information, where action and return is required, the Contracting Officer (CO, Contracting Specialist (CS) and Contracting Officer’s Representative (COR) will review each submittal, mark to indicate action taken, submit to the CO/CS/COR for final signature and return promptly.

1. Compliance with specified characteristics is the Contractor's responsibility.

B. Action Stamp: Each submittal will receive a uniform, action stamp. The Contracting Officer’s Representative will mark the stamp appropriately to indicate the action taken, as follows:

1. Approved: When the Contracting Officer’s Representative marks a submittal "Approved," the Work covered by the submittal may proceed provided it complies with requirements of the

01 33 00 - 7

SUBMITTALS

Contract Documents. Final payment depends on that compliance.

2. Approved As Noted: When the Contracting Officer (CO) / Contracting Officer’s Representative marks a submittal "Approved as Noted," the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Documents.

Final payment depends on that compliance.

3. Disapproved, Resubmit: When the Contracting Officer (CO) / Contracting Officer’s Representative (CS/COR) marks a submittal "Disapproved Resubmit," do not proceed with Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal according to the notations; resubmit without delay. Repeat if necessary to obtain different action mark.

a. Do not use, or allow others to use, submittals marked "Disapproved Resubmit" at the Project Site or elsewhere where Work is in progress.

C. The Contracting Officer (CO)/(CS/COR) action of "approved" or "approved as noted" on the submittals does not override or substitute for, the contract requirements in the specifications and the drawings. The CO/CS/COR is not responsible to design or generate calculations when reviewing a submittal. The approval of a submittal is subject to the provisions of the contract drawings and specifications. The approval action is for general concurrence only and the contractor is responsible for any errors or omissions in the approved submittals.

1.11 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI.

1. Coordinate and submit RFIs in a prompt manner to avoid delays in the work. Email RFI to the CO/CS/COR.

2. CO/CS/COR will not respond to RFIs submitted by other entities controlled by Contractor.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

ContractTime or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

01 33 00 - 8

SUBMITTALS

C. Contracting Officer’s Action: CO/CS/COR will review each RFI, determine action required, and respond. CO/CS/COR will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO/CS/COR's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO/CS/COR's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.12 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with Continuation Sheets.

b. Submittals Schedule.

c. Contractor's Construction Schedule.

2. Submit the preliminary Schedule of Values to CO/CS/COR within fifteen (15) days after award of the contract.

3. Submit finalized Schedule of values within ten (10) days from the approval date of the Overall Construction Schedule. Submit the finalized Schedule of Values within ten (10) days after the issuance of the Notice to Proceed.

B. Format and Content: Use the Construction Specification table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Contract number.

b. PMIS number.

c. Park unit.

d. Project name and location.

e. Contractor's name and address.

f. Date of submittal.

2. Submit Schedule of Values using AIA Forms G702 and G703 or approved equivalent.

3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of

01 33 00 - 9

SUBMITTALS

Applications for Payment and progress reports. Coordinate with the Project Specification table of contents. Provide line items for principal subcontract amounts, where appropriate. Include separate line items for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training.

4. When the Contracting Officer requires substantiating information, submit data justifying line item amounts in question.

5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

6. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site. If specified, include evidence of insurance or bonded warehousing.

7. Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

8. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

9. The equitable value of work deleted from a lump sum contract shall be determined from the approved Schedule of Values.

1.13 PAYROLL REPORTS

A. The Contractor shall promptly furnish to the Contracting Officer and cause all subcontractors through the Contractor to furnish in like manner, one copy of all payrolls covering payments to laborers and mechanics for on-site work. These payrolls shall be furnished within seven days after the regular payroll date. Payrolls are to be accompanied by a signed statement that Federal Labor Standards requirements have been complied with and a completed weekly statement of compliance similar to that on the reverse side of US Department of Labor Forms WH-347. Only one copy of each payroll and completed forms is required. Failure to furnish payrolls on time may result in progress payments being withheld. Payrolls should be prepared as follows:

1. Number payrolls consecutively.

2. Date each payroll (for final payroll insert "Final" after date).

3. Show contract number; give brief description of work and name and location of project.

4. A Prime Contractor's payrolls need show only the name of the Prime Contractor.

A subcontractor's payroll should show the sub and Prime Contractor's name. A

01 33 00 - 10

SUBMITTALS

sub-subcontractor payroll show all three names, etc.

5. Show correct name of employee (show last four digits of social security number).

6. Insert employee's labor classification exactly as shown in specifications. If an apprentice is employed, show apprentice, evidence of registration must be furnished.

7. In cases where an employee works in more than one classification, each classification, together with hours worked and rate paid for each classification, is to be shown. However, at the option of the Contractor, he may pay the higher of the scales for a period during which different classifications of work were performed by an individual, thus eliminating the need for a breakdown.

8. The exact number of straight time hours worked and exact number of overtime hours worked must be properly broken down.

9. Show fringe benefits paid (to employee or fund). Fringe benefits are paid on straight time basis only for each hour worked.

10. Compute total earnings on the basis of straight time rate for straight time hours worked, and on the basis of the overtime rate for overtime hours worked. Include fringe benefits at straight time rate for each hour worked.

11. Show total earnings.

12. Show exact amount of F.I.C.A. and Withholding Tax.

13. If other deductions are made, they must be authorized and carefully itemized.

14. If deductions are made which require approval of the Secretary of Labor, a letter of approval from that Secretary must accompany initial payroll on which such deductions are shown.

15. A statement that Federal Labor Standards Requirements have been complied with must accompany each payroll submission.

16. If fringe benefits must be paid, a statement as to their distribution must accompany each payroll submission.

1.14 PERMITS

A. Permits: See Section 01 11 00

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

01 33 00 - 11

SUBMITTALS

END OF SECTION 01 33 00

Transmittal Form (CM-16) National Park Service (NPS) - Denver Service Center (DSC) | 10-7-20 ACRONYMS: A/E: Architect/Engineer; CMR: Construction Management Representative; FAR: Federal Acquisition Regulation; LEED: Leadership in Energy & Environmental Design; N/A: Not Applicable; PMIS: Project Management Information System

Submittal Number: PARK Acronym: PMIS Number: Project: Contract Number: Date: Sheet: 1 of 2 Transmittal Number:

Construction Contractor: Subcontractor / Supplier:

Ac tio n

Su bm itt al

In fo rm at io na l S ub m itt al

Ite m

N um be r

Sp ec ifi ca tio n

Se ct io n

N um be r

Pa ra gr ap h N um be r

Description of Item (Size, Type, Name, Manufacturer, Use, etc.) Al te rn at e M at er ia ls

Pr op os ed

A/E ACTION

Action Submittal

Ap pr ov ed

Ap pr ov ed w ith

N ot at io ns

D is ap pr ov ed

R es ub m it

NPS ACTION

Action Submittal

Ap pr ov ed

Ap pr ov ed w ith N ot at io ns

D is ap pr ov ed

R es ub m it

Informational Submittal

Ac ce pt

R ej ec t

Construction Contractor - Name, Title, & Signature: Date:

I hereby certify this submittal has been reviewed for accuracy, completeness, and compliance with contract requirements. FAR 52-236-21

CMR - Name, Title, & Signature: Date:

A/E - Name, Title, & Signature: Date:

Review Comments - Name: Comment(s):

Recommended By - NPS CS/COR or Alternate CS/COR - Name, Title, & Signature: Date:

Action By - NPS Name, Title, & Signature: Date:

Approval of this submittal is subject to the provisions of the contract drawings and specifications.

This action is for general concurrence only and the Government is not responsible for errors or omissions.

Date Received: Date to Construction Contractor:

Distribute 1 copy each: CMR Interim, A/E, DSC, & Construction Contractor.

NPS Review Comments - Name: Comment(s):

Transmittal Form (CM-16) - Continuation National Park Service (NPS) - Denver Service Center (DSC) | 10-7-20 ACRONYMS: A/E: Architect/Engineer; CMR: Construction Management Representative; FAR: Federal Acquisition Regulation; LEED: Leadership in Energy & Environmental Design; N/A: Not Applicable; PMIS: Project Management Information System

Submittal Number: PARK Acronym: PMIS Number: Project: Contract Number: Date: Sheet: 2 of 2 Transmittal Number:

Construction Contractor: Subcontractor / Supplier:

Ac tio n

Su bm itt al

In fo rm at io na l S ub m itt al

Ite m

N um be r

Sp ec ifi ca tio n

Se ct io n

N um be r

Pa ra gr ap h N um be r

Description of Item (Size, Type, Name, Manufacturer, Use, etc.) Al te rn at e M at er ia ls

Pr op os ed

A/E ACTION

Action Submittal

Ap pr ov ed w ith N ot at io ns

D is ap pr ov ed

R es ub m it

NPS ACTION

Action Submittal

Ap pr ov ed w ith N ot at io ns

D is ap pr ov ed

R es ub m it

Informational Submittal

Ac ce pt

R ej ec t

Review Comments - Name: Comment(s):

01 50 00 - 1

TEMPORARY SERVICES, FACILITIES AND CONTROLS

SECTION 01 50 00

TEMPORARY SERVICES, FACILITIES AND CONTROLS

PART 1- GENERAL

1 .1 DESCRIPTION

A. The work of this section consists of providing temporary services, facilities and controls.

B. Work also consists of furnishing, installing, and maintaining barriers to protect existing facilities from construction operations.

1 .2 SUBMITTALS

A. As specified in Section 01 33 00.

PART 2- PRODUCTS

2 .1 GENERAL

A. Material may be new or used but shall be suitable for intended purpose. Fences and barriers shall be structurally adequate and neat in appearance.

2 .2 BARRIER TAPE

A. Banner Guard, imprinted with "CAUTION: CONSTRUCTION AREA", manufactured by Reef Industries, Inc., Houston, Texas, or approved equal

PART 3- EXECUTION

3 .1 BARRIERS

A. Protection of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. A temporary security fence (on footers) shall be installed to prevent access to excavated areas and other areas of investigation.

B. Barrier Tape: Install where directed by Contracting Officer (CO) / Contracting Specialist (CS)/ Contracting Officer’s Representative (COR). Keep a minimum of two rolls on site at all times.

C. Removal: Completely…