This document provides data on the time required by the Department of the Interior to definitize equitable adjustments for change orders under construction contracts. The Department does not have any supplemental policies or procedures regarding definitization beyond the requirements of FAR 36.211(b). Data presented indicates the number of change order proposals the Department definitized within various time periods after receipt of an adequate definitization proposal. The related federal contract opportunity is solicitation number 140P3023R0011 for rehabilitation of the geothermal piping system at Thomas House at Monocacy National Battlefield for the National Park Service, National Capital Area.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Contract Administration

Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts.

The Department of the Interior does not have any supplemental policies and procedures in regard to definitizing equitable adjustments for change orders under construction contracts.

The table below contains data, as it is made available, regarding the definitization of equitable adjustments for change orders under construction contracts.

Time to definitize after receipt of an adequate change order definitization proposal under construction contracts

Number of change order proposals definitized under construction contracts

30 days or less

31 to 60 days

61 to 90 days

91 to 180 days

181 to 365 days

366 or more days

After completion of contact performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance

Data only includes contracts over the Simplified Acquisition Threshold (SAT).