This is a Statement of Work (SOW) for a cultural resource inventory contract issued by the Bureau of Land Management (BLM) Rocky Mountain District on May 18, 2026, for work in Saguache County, Colorado. The contract covers a comprehensive Class III archaeological inventory of 699 acres across the Brewery Creek and Ward Gulch areas administered by the San Luis Valley Field Office, with a period of performance from July 1, 2026, to August 1, 2027 (13 months).

The contract consists of five sequential tasks with a 50-50 payment structure: Tasks I-III (File Search, Literature Review, and Inventory and Resource Identification) comprise 50% of the contract award, while Tasks IV-V (Draft Report and Final Report) comprise the remaining 50%. Task I requires conducting file searches and literature reviews of historic, ethnographic, and archaeological data within the project area and one mile beyond, synthesizing findings into tables, maps, and narrative format for a Historic Context overview. Task II involves a Class III pedestrian survey with crew spacing no greater than 20 meters apart following BLM State Protocol Agreement standards, Colorado SHPO guidelines, and BLM Colorado Digital Data Specifications. Task III requires recording all identified cultural resources using BLM Colorado Guidelines and appropriate OAHP site forms, with evaluation against National Register of Historic Places criteria under 36 CFR 60. Task IV requires completion of a draft inventory report with GIS data and attachments within 60 days of fieldwork completion, while Task V requires submission of the final report incorporating BLM comments within 30 days of receiving draft feedback. Deliverables include site and isolated find forms in PDF format, polygonal shapefiles in NAD 83 coordinate system, topographic maps with site locations, and comprehensive GIS databases conforming to BLM attribute table standards. The contractor must provide all personnel, equipment, and materials, with work conducted by or under direct supervision of an individual holding a Colorado BLM cultural resource use permit. Key compliance requirements include submitting fieldwork authorization five days prior to field operations, notifying the Contracting Officer Representative (COR) within 14 days of fieldwork completion with a progress report, and addressing any field inspection deficiencies at no cost to the government. The government furnishes access to SLVFO cultural records during regular office hours.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

BUREAU OF LAND MANAGEMENT

Rocky Mountain District

3028 East Main St.

Cañon City, CO 81212

05/18/2026

Section 1 Contract Terms & Conditions

1.1 Items Being Acquired

1.2 Deliverable of Services

Section 2 Project Description

2.0 Description of Project

2.1 Legal Locations

Section 3 Statement of Work

3.0 Task I File Search, Literature Review,

3.1 Task II Inventory and Resource Identification

3.2 Task III Record and Evaluation

3.3 Task IV Draft Report and attachments

3.4 Task V Final Report and final attachments

3.5 Government Furnished Material

3.6 Deliverables/Performance Schedule

3.7 Payment Schedule

List of Attachments:

Project Maps: Vicinity Map and Unit Maps Procedures and Reporting Standards Unit shape files

Section 1: Contract Terms & Conditions

1.1 ITEMS BEING ACQUIRED/TOTAL PRICE

The Contractor shall furnish all personnel, facilities, equipment, materials, supplies, and services (except otherwise expressed or set forth in this contract as furnished by the Government); and otherwise do all things necessary for, or incidents to the satisfactory performance of this contract. Under this contract, the Contractor shall provide the items of work required to fulfill the Statement of Work (SOW) as called for under Tasks I - V issued hereunder. The SOW for the Brewery Creek and Ward Gulch area covers a total of 699 acres of lands administered by the San Luis Valley Field Office (SLVFO) Bureau of Land Management (BLM) Colorado.

1.2 DELIVERABLE OF SERVICES

% of Contract Award

Tasks I-III Literature Review and Inventory 50% Task IV & V Draft and Final Report 50%

Section 2: Project Description

2.0 DESCRIPTION OF PROJECT

Complete an intensive Class III cultural inventory of public land administered by the BLM for a fuels reduction, timber salvage, and habitat enhancement project in Saguache County, Colorado. The contract will consist of Tasks I-V comprising a total of 699 acres to be inventoried. Work will be carried out by or under the direct supervision of an individual holding a Colorado BLM cultural resource use permit.

The intent of this archeological inventory is to identify, record, and evaluate cultural resources for their potential eligibility to the National Register of Historic Places to aid the BLM in resource management, compile cultural and paleontological data for future research, and to satisfy the BLM’s obligations to Section 106 of the National Historic Preservation Act. Following the completion of field work, the results will be prepared in draft and final report documents that include data synthesis of all cultural resources and analysis within the project area.

The project is located in the northwestern portion of the San Luis Valley Field Office in the Brewery Creek and Ward Gulch drainages. Brewery Creek is located approximately is 1.3 miles southwest of Bonanza, Colorado and Ward Gulch is located approximately 16 miles northwest of Saguache, Colorado. The following legal descriptions are utilizing the New Mexico Principal Meridian.

2.1 Entire Project Area: 699.0 acres

Legal description: T. 47N, R. 7E, sec 35 & T. 46N, R. 5E, sec 23, 26

USGS 7.5’ Topo Map Reference: Trickle Mountain and Bonanza

The project area consists of open meadows, closed conifer stands, and some open ponderosa pine.

Mature aspen stands with some fir encroachment. Intermixed pinyon/juniper woodland may be present in the lower elevations.

Brewery Creek: One previous survey has been completed within the APE, and one previously recorded site (5SH.1470) is located within the APE. Based on previous surveys in the area, proximity to Bonzana, and the presence of 5SH.1470, there is a moderate likelihood of finding both historic and precontact cultural resources.

Ward Gulch: No previous surveys or cultural resources have been recorded within the APE, and only limited survey coverage exists in the surrounding area. However, it is anticipated there is a moderate likelihood of finding both historic and precontact cultural resources.

Section 3: Statement of Work

3.0 TASK I: FILE SEARCH, LITERATURE REVIEW

Task I consists of two parts that can be completed simultaneously with each other. The first part consists of completing a file search overview with synthesis of data for known historic, ethnographic and archeological data that encompass the project area, and the area within one mile of the project boundary.

This research is necessary to identify and compile all available known cultural data previously recorded and inventoried areas that includes recorded resources, isolates, and potential unrecorded resources to develop an interpretive narrative overview for understanding and writing the Historic Context of the project area.

Available existing cultural resource data shall include, but not limited to, BLM San Luis Valley Field Office cultural resource inventory records, Colorado State Institutional Archives, Repositories; listed properties in the State Historic Sites Inventory, National American Engineering Records, and Historic American Buildings Survey records, and the Colorado Office of Archaeology and Historic Preservation COMPASS cultural resource database. Other available sources of information may be obtained from, and not limited to, State and National Registers, published and unpublished manuscripts, aerial photographs, General Land Office maps, Mining Ledgers, historical photographs, regional historical contexts, and Museums and library reference material. Data gathered will then be used to develop a Historic Context overview of the project area for precontact, historic and potential traditional cultural properties (TCP’s).

At the time of submitting this contract no TCP’s have been identified by local tribes during consultation.

After completion of the file search and review, the results will need to disseminate the gathered data within summarized tables, maps, photographs, narrative, or other informative format. Historic Context will consider explicit types of resources that might be encountered, and evolve potential research questions based on prehistory, history, and ethnology of the San Luis Valley, and surrounding region. All discussions will need to be accurately identified and referenced in the bibliography.

3.0.a A file search shall gather known/documented historic and archeological data that is pertinent to the project area, and from the results develop an informative draft overview in table, and narrative format.

This part of the draft will be sent to the Contracting Officer Representative (COR). After review, the COR may suggest additional comments or directives to ensure a comprehensive overview and developed Historic Context.

3.0.b Previously recorded resources within one mile shall be presented in a table format. All sites shall be listed with their state trinomial number, site type, date recorded and the previous evaluation status of eligible, not eligible, or unevaluated/needs data to the National Register, and the report reference. Isolated finds and non-eligible resource data may remain in table format. National Register eligible resources, and unevaluated resources, within and immediately adjacent to the APE shall be further described in brief narrative detail as discussion points in support of the historic context and anticipated inventory expectations.

3.1 TASK II: INVENTORY AND RESOURCE IDENTIFICATION

Task II consists of completing a Class III inventory spaced no more than 20 meters apart in accordance with the most current versions of the following documents:

The BLM State Protocol Agreement (Protocol) with the Colorado State Historic Preservation Office (SHPO) dated October 29, 2014, Inventory standards and guidelines are specified in the most current BLM Colorado Guidelines and Procedures for Inventory, Evaluation, and Treatment of Cultural Resource Sites, BLM-Colorado Digital Data Specifications Guide 2026, Office of Archaeology and Historic Preservation’s “Colorado Cultural Resource

Survey Manual: Guidelines for Identification: History and Archaeology,” BLM Linear Forms, Rocky Mountain District Standards and Procedures, and Other supplemental guidance.

A fieldwork authorization must be submitted to the Field Office Archaeologist at least 5 days prior to the start of fieldwork. Emphasis shall be placed on complete and timely coverage of the area to identify all cultural resources within the area of potential effect (APE) for the project.

3.1.a If there are areas identified that are too steep, vegetation or brush that is extensively thick, or other occurrences that prevent regular pedestrian intensive inventory transects feasible without risk to safety, or poor visibility, the COR/PI will be notified and consulted for further instructions. Such areas may need to be removed or alternative inventory methods to adequately cover the project area. The Contracting Officer will make the determination if areas are to be removed and any needed adjustments to the contract.

3.1.b Each field crew must be supervised in the field by a qualified crew chief listed on the Cultural Resource Use Permit (CRUP). Crew chiefs must be on-site at all times.

3.1.c The Contractor must notify the COR/PI by telephone and with written confirmation immediately upon the discovery of human remains, funerary objects, sacred objects, or objects of cultural patrimony (as defined in 43 CFR 10.2) and must immediately stop any activities connected with such discovery and make a reasonable effort to protect the discovered remains or objects.

3.1.d Upon completion of the inventory and identification of cultural resources, the COR/PI may review the results and may provide comments or recommendations to insure comprehensive coverage of identified resources.

3.1 e If a significant paleontological resource, including but not limited to fossilized flora or faunal remains (older than 100 years) is located during this inventory, the COR/PI will be notified by an email that includes specific location data and photograph(s). Unless it is associated with cultural materials, this does not need to be included in the report deliverables. This contract does not require specialized paleontological personnel. This clause is for inadvertent discoveries of paleontological resources.

3.1 f A fieldwork authorization form shall be carried with the field crews on the project area. This can be either carried by a crewmember or displayed in the window of the field truck.

3.2 TASK III: RECORD AND EVALUATE IDENTIFIED

HISTORIC/ARCHEOLOGICAL RESOURCES.

Task III consists of two parts. Part 1 involves recording identified cultural sites and Part 2 is the evaluation of those sites for their eligibility for inclusion to the National Register of Historic Places. All identified cultural resources shall be recorded in detail utilizing BLM Colorado Guidelines and Procedures for Inventory, Rock Mountain District Standards and Procedures and appropriate OAHP site forms. Following BLM Guidelines, site and isolate forms will include relevant diagnostics, features, or other notable characteristics on each site, and forms shall be accompanied with a detailed site sketch map, feature sketch, and the site location identified on a USGS 1:24000 quadrangle map. In addition, all site forms shall have appropriate listed bibliographies of associated utilized/known references associated with site form.

Incomplete site forms will be regarded as unfinished product. Inconsistencies will be corrected prior to acceptance and given state trinomial numbers.

3.2.a There must be sufficient description on the forms for the COR/PI to derive an accurate eligibility assessment. The site description must include number and types of objects present, site dimensions, types of features, topographic location, etc. If any significant disturbances or impacts have occurred, these must be described and photographed. Each form must be legible and must include a formal site map and a USGS 7.5', 1:24,000 scale GIS produced topographic map showing the exact location of the site. Site boundaries must be depicted as accurately on both the site and topographic maps. The topographic map must be clearly labeled with the map name, site number, map scale, north arrow and land status. Site maps must include spatial relationships of features and artifacts to each other and other pertinent non-cultural data or topography (i.e., roads, trees, drainages, etc.). If tools or diagnostic artifacts are present, scaled artifact sketches or photographs must accompany the site form.

3.2.b Collection policy: The SLVFO has a no collection policy.

3.2.c The evaluations will be completed for all previously recorded sites. Care will be taken in coordinating the site numbers when previously recorded sites are re-located to assure that the correct site numbers are used since they may have associated curated collections. Original site numbers for these sites will be retained as much as possible even though expanded recording may reveal a much larger site area than originally documented.

3.2.d When re-mapping previously recorded sites, new maps should be built off of earlier site maps.

Feature and structure numbers from earlier maps should be carried forward to the new map.

New features or structures will be numbered to follow the last number.

3.2.e Evaluation results shall specify the National Register of Historic Places (NRHP) criteria set forth in 36CFR60 that applied to determining a significance value and formulating a determination of eligibility. This eligibility recommendation shall be well reasoned for or against nomination to the NRHP. If the site is recommended eligible under Criterion D, the specific research question(s) shall be noted. The NRHP criteria shall be applied to each component of a site. Results shall be summarized in a narrative format formulating the methods applied during the evaluation process. Discussion should include sufficiency of the data recovered and detail reasons for the evaluation methods prescribed, and the potential for the need to conduct additional data recovery to support eligibility determinations. Minimal scrapings, probing, or subsurface testing will be allowed to support evaluations. For any properties recommended as eligible, additional recommendations shall be made for treatment, mitigation, fire sensitivity and discussion on notable adverse effects (erosion, cattle, looting, off road vehicles, etc.) to these properties for elevating their protection and management. If a site is identified as a landscape size scale, the COR/PI shall be notified immediately for follow-up recommendations on how to proceed.

3.2.f All historic sites with identifiable features and structures shall include additional supportive

OAHP architectural documentation with photographs, and sketch plan view maps. This documentation shall collaborate with the site sketch map.

3.2.g All precontact sites with significant identifiable features shall include additional supportive documentation including descriptions with photographs, and a plan view sketch diagram. This documented data shall collaborate with the site sketch map.

3.2.h If a site is located within the project boundary and extends beyond the inventory area, it will be recorded to a reasonable extent following the BLM Guidelines. The COR/PI should be notified immediately about the site and discuss options to appropriately address the issue. The primary objective is to properly record the site to allow adequate assessment and evaluation of that portion of the site within the area of potential direct and indirect effects based on evaluation criteria.

3.2.i Within fourteen working days of completion of the fieldwork the Contractor will contact the

COR/PI with a progress report. It can be in a brief narrative or table format and will include:

(1) a description of each site and IF including site type, temporal or cultural affiliation, and the NRHP eligibility recommendation; (2) a copy of a 7.5’ topographic map showing the project survey boundary and site and IF locations. The BLM will have two weeks to perform quality control field inspections if warranted. Should the field inspections result in the discovery of inventory or site recording deficiencies, the contractor must address these deficiencies at no cost to the government. This includes, but is not limited to, additional field mobilizations.

3.2.j After the completion of Tasks I - III an invoice may be sent for 50% of the contract award.

3.3 TASK IV: DRAFT INVENTORY REPORT

Task IV consists of writing the draft report, GIS data and draft attachments. This task consists of data synthesis of the results from previous Tasks to develop the Final Report. The report will reflect all fieldwork results accomplished during this contract and should require minimal editing to produce the Final Report. OAHP site forms, figures and maps are referred to as attachments and should also be in a draft state that requires minimal editing before the final attachments are delivered. The draft report, site, and isolated find forms must include the BLM and SHPO report numbers. The BLM will provide the BLM project number. OAHP project and site numbers must be obtained directly from OAHP using the new templates.

https://sites.google.com/state.co.us/oahp-resource-center/forms-guidance/requesting-numbers

3.3.a The draft final report and all required survey information and site and IF forms will meet the guidelines established by the Secretary of Interior’s Standards and Guidelines for Archaeology and Historic Preservation, the most current BLM Colorado Handbook of Guidelines and Procedures for Inventory, Evaluation, and Mitigation of Cultural Resources and associated Digital Data Specifications Guide, Colorado SHPO standards, District and field office standards and procedures and other supplemental guidance.

3.3.b The draft final report will include evaluations of all sites, recommendations on National

Register eligibility, and a discussion of site impacts. The evaluations should be made in the context of previous investigations and findings in the general area, and research questions for the region. All sites brought forward as “Need Data” will include a detailed discussion of how field testing was conducted and why field testing was inconclusive and specific recommendations for additional evaluative testing to determine eligibility. The recommendations for site management must take into account the current site condition based on disturbances observed while conducting the field work.

3.3.c The shapefiles must be polygonal (no points or lines) of both the actual area inventoried, and the site and IF boundaries. All shapefiles will be in NAD 83 for submission. The Contractor shall provide all draft data as electronic (.pdf) and Word document files on thumb- drive, or by Secure File Transfer Protocol with software compatible with Bureau of Land Management software.

3.3.d GIS data tables shall conform to BLM guideline standards for attribute table database fields (see Digital Data Specifications Guide).

3.3.e The Draft Report shall be completed within 60 days of the completion or fieldwork. Extensions may be allowed in coordination with BLM. Any extension will be in writing will clearly defined dates for drafts and final report reviews.

3.3.f Within 30 days of submission of the initial Draft Report, the BLM shall provide comments on suggested revisions or modifications of the draft and electronic data. Conversations and corrections will continue until the edits are made and the COR/PI are satisfied the work has met the above guidelines and standards for cultural resource inventory in the RGFO.

3.3.g The contractor will submit the Draft Report after internal review and technical editing.

Documents that are submitted without either technical editing or content review may be returned for corrections prior to BLM’s review of the draft. It is advised that the contractor communicate with the BLM if they are having difficulties meeting this requirement and a solution can be worked out and agreed upon by both parties.

3.4.a Task V: FINAL INVENTORY REPORT

3.4.a The COR/PI will inform the contractor when the report is ready to go final.

3.4.b The final report containing all changes and corrections identified from the draft report review shall be submitted within 30 days of receiving the BLM draft report comments. The final report shall be submitted by Secure File Transfer or Rocky Mountain District Archaeological Contractor Microsoft Teams Site and include following:

1. Final Report in PDF format

2. Individual site and isolated find forms in PDF format

3. Shapefiles of survey areas, sites, and isolated finds

A request, in writing, for an extension due to unforeseen circumstances may be granted, but the request must be submitted to the COR/PI three (3) working days before the due date of the final report, and it must clearly state why the extension is needed.

3.4.c Final Report will include one complete copy of a final inventory report presenting results, including appropriate maps, tables, photographs, sketches, attachments (Site and IF forms) and a final copy of electronic GIS site data.

3.4.d After receipt of BLM comments the contractor shall correct any revisions or modifications responsive to comments. The contractor shall submit the final deliverables electronically. This can be done through an FTP site, or via the RGFO Archaeological Contractors Office 365 Team.

3.4.e After delivery of the final report, and acceptance is approved, along with submission of electronic files, and any appropriate Government Furnished Material. The final invoice may be submitted for the remaining 50% of contract.

3.5 Definitions

3.5.a Cultural Resource or Cultural Property: Any definite location of past human activity, occupation, or use, identifiable through field inventory (survey), historical documentation, or oral evidence. This term may be applied to archaeological, historic, or architectural sites, structures or places, or places of traditional cultural or religious importance to specified social and/or cultural groups, whether or not represented by physical remains.

3.5.b Class III inventories: They are professionally conducted, continuous, intensive pedestrian surveys of an entire target area (100%). The goal is locating and recording all cultural resource properties that have surface and exposed-profile indications, through systematic inspection carried out by a crew of trained observers walking a series of parallel transects until the area has been thoroughly examined. Crew spacing should not be wider than 15-20 meters apart.

Intensive inventory describes the distribution of properties in an area; determines the number, location and condition of properties; determines the types of properties actually present within the area; permits classification of individual properties; and records the physical extent of specific properties.

3.5.c Evaluation: The evaluation of cultural resources requires a determination of site eligibility for the NRHP using National Register eligibility criteria (36 CFR 60).

3.5.d Historic Property: Any precontact or historic district, site, building, structure, or object included in, or eligible for inclusion in the NRHP. The term includes, but is not limited to, artifacts, records, and remains that are related to and located within such properties. The phrase “eligible for inclusion in the NRHP” includes both properties formally determined as such by the Secretary of the Interior and all other properties that meet National Register listing criteria and those sites already identified as eligible during consultation between the BLM and the Colorado

SHPO.

3.5.e Undertakings: Actions assisted, licensed, permitted, approved, funded, or authorized by BLM, as defined in the Code of Federal Regulations [36 CFR 800.2(o)]. Undertakings for which BLM is considered the lead agent, whether or not they involve federal lands, are federal actions.

3.6 Government Furnished Material

The government will make available or provide Contractor with the following:

Access to SLVFO cultural records, or other available associated documentation during regular office hours.

3.7 Deliverables/Performance Schedule

Prework meeting: 0-14 days from award.

A draft Literature Review will be submitted prior to field work.

BLM review of Draft Report and Attachments 30 days from receipt.

Comments/Corrections and Final Report prior to end of Period of Performance

Period of Performance: July 01, 2026 to August 01, 2027 (13 months)

3.8 Payment Schedule

% of Contract Award

Tasks I-III Literature Review and Inventory 50% Task IV & V Draft and Final Report 50%