B08_Attachment_1_140P8423R0004_Specifications.pdf
PDF 4 MB Posted
- Attached to
- Replace Water Storage Tanks, NPS-LAVO Federal contract opportunity
- Solicitation number
- 140P8423R0004
About this file
This federal solicitation requests proposals to replace water storage tanks at two locations within Lassen Volcanic National Park in California. Offerors are invited to inspect the project sites in advance of submitting proposals. Proposals are due by June 2, 2023. The work includes removing and replacing two damaged steel water storage tanks and associated piping, telemetry, and equipment. One site will also involve replacing an existing water treatment building and treatment systems. The solicitation package, which includes standard forms, specifications, and instructions for submitting proposals, is available for download. Any questions must be submitted in writing by the deadline specified. The National Park Service Pacific West Region is the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Attachment_6_140P8423R0004_Site_Visit-Amendment_Notes_0001.pdf | ||
| B08_Attachment_5_140P8423R0004_Site_Visit_Sign_In_Sheet_0001.pdf | ||
| Sol_140P8423R0004_Amd_0001.pdf | ||
| B08_Attachment_7_140P8423R0004_Archived_KYVC_Tank_Plan_Sheet_0001.pdf | ||
| B08_Attachment_3_140P8423R0004_Wage_Determination_28Apr2023_0001.pdf | ||
| B08_Attachment_8_140P8423R0004_KYVC_Tank_Paint_Test_0001.pdf | ||
| B08_Attachment_2_140P8423R0004_Drawings.pdf | ||
| Sol_140P8423R0004.pdf | ||
| B08_Attachment_3_140P8423R0004_Wage_Determination.pdf | ||
| B08_Attachment_4_Proposal_Submission_Package.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LASSEN VOLCANIC
NATIONALPARK
REPLACE WATER STORAGE TANKS
AT
DRAKESBAD AND KYVC
PMIS No. 315519/324970
CONSTRUCTION SPECIFICATIONS
NATIONAL PARK SERVICE
PACIFIC WEST REGION
LAVO – 315519/324970 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 31 00a RFI Form 01 32 16 Construction Schedule 01 32 33 Photo Documentation 01 33 23 Submittal Procedures 01 33 23a CM16 - Transmittal 01 35 13 Archeological Protection 01 35 25 Safety Requirements 01 40 00 Quality Requirements 01 40 00a Daily Inspection Form 01 42 00 Reference Standards 01 50 00 Temporary Facilities & Controls 01 57 23 Under-an-Acre Pollution Prevention Plan 01 57 23a Under-an-Acre Pollution Prevention Plan Template 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management 01 77 00 Closeout Procedures 01 78 23 Operation & Maintenance Data
DIVISION 02 – EXISTING CONDITIONS
02 05 00 General Site Conditions 02 41 00 Demolition & Removals
DIVISION 03 – CONCRETE
03 30 00 CIP Concrete
DIVISION 04 – MASONRY
04 20 00 Unit Masonry
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITIES
06 10 00 Rough Carpentry 06 16 00 Sheathing
DIVISION 07 – ROOFING WATERPROOFING AND INSULATION
07 21 00 Thermal Insulation 07 25 00 Weather Barrier 07 61 14 Steel Standing Seam Roof 07 62 00 Sheet Metal Flashing & Trim
LAVO – 315519/324970 TOC-2
DIVISION 8 – WINDOWS AND DOORS
08 31 13 Access Doors and Frames 08 70 00 Finish Hardware
DIVISION 09 – FINISHES
09 90 00 Painting
DIVISION 22 – PLUMBING
22 05 29 Pipe Support Systems 22 11 3 Facility Water Piping and Accessories 22 11 15 Polyethylene Pressure Pipe
DIVISION 26 – ELECTRICAL
26 05 00 Basic Electrical 26 08 00 Testing 26 27 00 Basic Electrical Materials & Methods 26 31 01 PV Systems
DIVISION 31 – EARTHWORK
31 05 16 31 05 25 31 10 10 31 12 33 31 22 13 31 22 19
Aggregates for Earthwork Utility Line Marking Site Clearing Utility Trenching and Backfill Rough Grading Topsoiling & Finished Grade
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 16 00 Restoration of Surfaces
DIVISION 33 – UTILITIES
33 11 00 Water Utility Distribution Piping 33 12 16 Valves Hydrants & Appurtenances
33 13 00 Disinfecting Water Utility Distribution 33 16 13 Glass Fused Steel Water Tank
DIVISION 43 – PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE
43 32 76 Chlorination Equipment
LAVO – 315519/324970 01 11 00 - 1
012721 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Under Other Contracts
3. Government-Furnished Materials
4. Contractor Use of Site
5. Public Use of Site
6. Conduct of Operations
7. Work Restrictions
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: This project is located at two locations. The first location is at Drakesbad Guest Ranch in Lassen Volcanic National Park. The second location is at the KYVC (SW Visitor’s Center) in Lassen National Park.
B. The Work consists of:
1. Removing and replacing two damaged steel water storage tanks and associated piping, telemetry, and apparatuses. The KYVC site will include demolition of the existing steel water storage tank, but the demolition for the Drakesbad site will primarily be done under a separate contract. The Drakesbad site will also consist of replacing the existing water treatment building and treatment/disinfection equipment.
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. Removal and replacement of the water and propane distribution lines within the guest ranch area. This project may be completed by time the water tank project starts.
2. Demolition of the Drakesbad Water Tank and Treatment building.
LAVO – 315519/324970 01 11 00 - 2
3. Various fire related mitigation projects.
1.4 GOVERNMENT-FURNISHED MATERIALS
A. In case of Government -furnished materials:
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. Contractor is responsible for initial inspection, receiving, unloading, and handling Government-furnished items at Project site.
3. Government will inspect delivered items for damage after delivery. Contractor shall be present for and assist in Government's inspection.
4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into Work.
B. Government-Furnished Materials:
1. Float switch for KYVC tank.
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Confine storage of materials to area shown on plans.
C. Stockpiling: Confine stockpiling to areas shown in the plans.
D. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
E. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
LAVO – 315519/324970 01 11 00 - 3
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
F. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
G. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
1.6 PUBLIC USE OF SITE
A. The park or area will be closed to the public during construction.
B. Contractor shall conduct operations to ensure the least inconvenience to public. Road closures may be permitted, when required, upon specific approval of Contracting Officer.
1.7 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
LAVO – 315519/324970 01 11 00 - 4
C. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
LAVO – 315519/324970 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
C. Plan Quantities (P). Items listed as Plan Quantity and denoted as (P) are items where unit quantities have been determined and provide for reference only. Plan Quantity Items shall not be measured in the field and are essentially lump sum items where unit rates are established should any modification of increased or decreased quantities be required.
D. Where unit quantity items are listed, payment shall be up to the contract price amount. Should quantities exceed the contract amount a contract modification shall be required.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
SCHEDULE 1: KYVC SITE
A. Contract Line Item Number 0001: Mobilization and Demobilization
1. This item consists of all preparatory work and operations for all items under the contract, including, but not limited to those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site and all other work or operations which shall be performed or costs incurred prior to beginning work on the various items on the project site. This item also includes bonding, permits (if any), and demobilization cost.
2. This item may not exceed 20% of the total bid.
3. Measurement for payment: Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price. No more than 75% of this bid item shall be made until the contractor has demobilized from the site.
B. Contract Line Item Number 0002: Demolition and Removals
1. This item consists of disconnecting demolishing the existing steel water tank and all associated piping, valves and apparatuses as shown in the plans.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
LAVO – 315519/324970 01 27 00 - 2
C. Contract Line Item Number 0003: Site Preparation & Grading
1. This item consists of all preparatory site work and grading as required to prepare the site as required to construct the water tank per the requirements of the tank manufacturer.
These items include, but are not limited to, grading and excavation to prepare the tank foundation, adjacent temporary site grading, clearing and grubbing, and improvements to the access road as required to facilitate ingress and egress of construction equipment and components.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item Number 0004: Ancillary Piping & Components
1. This item consists of all constructing all ancillary water mains, fittings, and components as shown in the plans to create a fully operational system. The intent of this line item is to cover all water main piping and associated components that are not directly supplied as part of the water tank. These components include but are not limited to, connection piping between the existing valve vault and new tank, and overflow and drain piping and components. This work shall be coordinated with the tank foundation construction.
2. This item also includes constructing the sample tap located near the proposed water tank.
3. This item also includes connecting to the existing system.
4. Measurement for payment: Measurement shall be on a lump sum basis.
5. Payment will be made at the contract lump sum price.
E. Contract Line Item Number 0005: Construct Water Tank Foundation
1. This item consists of constructing the proposed water tank foundation.
2. Under typical construction work-flow, the tank foundation is constructed by a contractor that differs from the tank supplier.
3. Measurement for payment: Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
F. Contract Line Item Number 0006: Construct New Water Tank
1. This item consists of furnishing and installing the new glass lined steel water tank and all associated valving, piping, and components, as show in the plans and as specified.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
G. Contract Line Item Number 0007: System Disinfection & Start-Up
1. This item consists of disinfecting the new water tank and new watermain piping as specified. This item also includes system start-up, which involves coordinating with the park to switch over from the temporary water system to the new system once it is operational.
2. Measurement for payment: Measurement shall be on a lump sum basis.
H. Contract Line Item Number 0008: Stormwater & Sediment Control
LAVO – 315519/324970 01 27 00 - 3
1. This item consists of implementing limited stormwater and sediment control practices as shown in the plans and as identified by the contractor in the UPPP.
2. This item also consists of removing BMPs.
3. Measurement for payment: Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
I. Contract Line Item Number 0009: Site Restoration & Cleanup
1. This item consists of all miscellaneous activities required to fully restore the site to preconstruction conditions upon project completion. Items include but are not limited to, final surface grading, removal of trash and rubbish, removal of installed BMPs, and restoring damages to the existing access road.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
SCHEDULE 2: DRAKESBAD SITE
A. Contract Line Item Number 0001: Mobilization and Demobilization
1. This item consists of all preparatory work and operations for all items under the contract, including, but not limited to those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site and all other work or operations which shall be performed or costs incurred prior to beginning work on the various items on the project site. This item also includes bonding, permits (if any), and demobilization cost.
2. This item may not exceed 20% of the total bid.
3. Measurement for payment: Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price. No more than 75% of this bid item shall be made until the contractor has demobilized from the site.
B. Contract Line Item Number 0002: Demolition and Removals
1. This item consists of miscellaneous demolition and removals at the site.
2. The majority of demolition work for this site will be completed under a separate contract associated with fire recovery efforts. Prior inspection revealed elevated levels of lead in the ashes of treatment building (likely from lead paint). The separate demolition project will remove and properly dispose of on-site hazardous materials.
3. The work under the other contract will remove what remains of the existing treatment building (including foundation), the existing steel water tank, tank foundation and most ancillary piping.
4. This pay item will include minor demolition that will primary be limited to a small amount of underground piping, and minor demolition required to reconnect the raw water line.
5. Measurement for payment: Measurement shall be on a lump sum basis.
6. Payment will be made at the contract lump sum price.
C. Contract Line Item Number 0003: Site Preparation & Grading
1. This item consists of all preparatory site work and grading as required to prepare the site as required to construct the water tank per the requirements of the tank manufacturer.
These items include, but are not limited to, grading and excavation to prepare the tank foundation, adjacent temporary site grading, clearing and grubbing, and improvements to
LAVO – 315519/324970 01 27 00 - 4
the access road as required to facilitate ingress and egress of construction equipment and components.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item Number 0004: Ancillary Piping & Components
1. This item consists of all constructing all ancillary water mains, fittings, and components as shown in the plans to create a fully operational system. The intent of this line item is to cover all water main piping and associate components that are not directly supplied as part of the water tank. These components include but are not limited to, piping, valves, and fittings from the existing raw water main connection to the treatment building, piping from the treatment building to the tank connection, overflow and drain piping and components, and the tank float valve. This work shall be coordinated with the tank foundation construction.
2. This item also includes connecting to the existing system (raw water and distribution).
3. This item also includes constructing the sample tap located near the proposed water tank.
4. This item does not include process piping and components located within the treatment building. The limits of this pay item within the treatment building are the 4”x2” reducers.
5. Measurement for payment: Measurement shall be on a lump sum basis.
6. Payment will be made at the contract lump sum price.
E. Contract Line Item Number 0005: Construct Water Tank Foundation
1. This item consists of constructing the proposed water tank foundation.
2. Under typical construction work-flow, the tank foundation is constructed by a contractor that differs from the tank supplier.
3. Measurement for payment: Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
F. Contract Line Item Number 0006: Construct New Water Tank
1. This item consists of furnishing and installing the new glass lined steel water tank and all associated valving, piping, and components, as show in the plans and as specified.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
G. Contract Line Item Number 0007: Construct Treatment Building
1. This item consists of furnishing and installing the new treatment building and components, as show in the plans and as specified.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
H. Contract Line Item Number 0008: Process Piping & Equipment
1. This item consists of furnishing and installing all new process piping, fittings, and components as shown in the plans and as specified. Items included under this pay item included, but are not limited to, process piping, fittings, ball valves, flow control valves, check valves, air valves, hoses bibs, pressure gages, basket strainer, unions, sample taps, flow meters, days tanks, chlorinator, and all other process equipment as shown in the plans.
LAVO – 315519/324970 01 27 00 - 5
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
I. Contract Line Item Number 0009: System Disinfection & Start-Up
1. This item consists of disinfecting the new water tank and new watermain piping as specified. This item also includes system start-up, which involves coordinating with the park to switch over from the temporary water system to the new system once it is operational.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
J. Contract Line Item Number 0010: Stormwater & Sediment Control
1. This item consists of implementing limited stormwater and sediment control practices as shown in the plans and as identified by the contractor in the UPPP.
2. This item also consists of removing BMPs.
3. Measurement for payment: Measurement shall be on a lump sum basis.
4. Payment will be made at the contract lump sum price.
K. Contract Line Item Number 0011: PV System
1. This item consists of furnishing and installing the PV system as shown in the plans and as specified. This item includes, but is not limited to, solar panels, inverters, controllers, cables, wiring, batteries, and miscellaneous system components.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
L. Contract Line Item Number 0012: Interior Electric and Lighting
1. This item consists of furnishing and installing all interior electrical and lighting components as shown in the plans and as specified.
2. Measurement for payment: Measurement shall be on a lump sum basis.
3. Payment will be made at the contract lump sum price.
M. Contract Line Item Number 0013: Site Restoration & Cleanup
1. This item consists of all miscellaneous activities required to fully restore the site to preconstruction conditions upon project completion. Items include but are not limited to, final surface grading, removal of trash and rubbish, and restoring damages to the existing access road.
2. Measurement for payment: Measurement shall be on a lump sum basis.
END OF SECTION 01 27 00
LAVO – 315519/324970 01 31 00 - 1
012721 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Project Meetings
7. Environmental Coordination
8. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
LAVO – 315519/324970 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
b. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
c. Indicate required installation sequences.
2. Refer to individual Sections for Coordination Drawing requirements for Work in those Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Contractor's responsibility. If Contracting Officer
LAVO – 315519/324970 01 31 00 - 3
determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Contractor, who shall make changes and resubmit.
2. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
D. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPPP or UPPP)
E. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
LAVO – 315519/324970 01 31 00 - 4
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete RFI Form as follows:
1. Enter general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.
3. Enter details of question and attach related documents.
4. Select "Submit Form" at bottom of page.
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
LAVO – 315519/324970 01 31 00 - 5
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Notice to proceed
14. Correspondence procedures
15. Acceptance/rejection of work
16. Progress meetings
17. Submittal procedures
18. Environmental requirements
19. Permit requirements
20. As-constructed drawings/operation and maintenance (O&M) manuals.
21. Saturday, Sunday, holiday and night work.
22. Reference materials
23. Value engineering
24. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
LAVO – 315519/324970 01 31 00 - 6
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Responsibilities: Responsibilities shall include:
LAVO – 315519/324970 01 31 00 - 7
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
e. Training for Contractor personnel in accordance with position requirements.
f. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Temporary Storm Water Pollution Prevention Environnemental Management
4. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Temporary Storm Water Pollution Prevention
4. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the Government. Contractor shall comply with appropriate Federal, State and local laws.
LAVO – 315519/324970 01 31 00 - 8
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. None
C. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.
D. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
E. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
Request for Information (RFI) Form, 2-18-20 page 1 of 1
Request for Information (RFI) Form National Park Service (NPS) - Denver Service Center (DSC) | 2-18-20
RFI Number:
Project: Replace Water Storage Tanks at Drakesbad and KYVC
Contract Number:
Date:
To:
Carbon Copy (CC):
From:
Subject:
Please provide the following information or clarification:
Response Required By:
Date:
To:
From:
Subject: Response to RFI Number:
Response:
LAVO – 315519/324970 01 32 18 - 1
012721 CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
C. Anticipated Schedule
It is anticipated that this project will be awarded in the summer of 2023. Demolition work for the Drakesbad site will likely occur in the fall of 2023. Depending on several factors, it may be possible for the contractor to begin sitework and some demolition (primarily at KYVC) in the fall of 2023. Given the anticipated lead times for ordering steel-lined tanks, it is understood that construction for this project may not begin until spring of 2024. It is anticipated that most construction work will occur in the summer of 2024. Construction season at Lassen typically begins in June and goes through November. Upon project award, the successful contractor should present a schedule based on anticipated tank delivery dates. The NPS understands that there are several factors that may impact construction schedule, including tank lead times, and a short construction season. It is the intent of the NPS to work with the contractor to establish a reasonable schedule based on these factors. Adjustments to project completion dates will be made based on tank delivery timelines.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
LAVO – 315519/324970 01 32 18 - 2
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
1.3 SUBMITTALS
A. Electronic Copies: Schedules and reports submitted shall be posted on the NPS/DSC management software website in native electronic file formats. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit baseline schedule, large enough to show entire schedule for entire construction period.
Utilize Schedule of Values in preparation of Construction Baseline Schedule.
D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit paper copies of the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of activities sorted in ascending order of total float.
E. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent completion of each schedule activity and necessary supporting data.
Provide two paper copies.
LAVO – 315519/324970 01 32 18 - 3
F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision, submit a Time Impact Analysis.
1.4 QUALITY ASSURANCE
A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints.
4. Review delivery dates for Government-furnished products.
5. Review schedule for work of separate Government contracts.
6. Review time required for review of submittals and re-submittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review time required for obtaining and activating permits.
10. Review and finalize list of construction activities to be included in schedule.
11. Review baseline schedule comments, resolve issues and progress on incorporating them
12. Review procedures for updating schedule.
13. Discuss reporting requirements and establish protocol for naming and transmitting electronic schedules.
B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction Schedule. Submit resume outlining qualifications of Scheduler to Contracting Officer for acceptance. Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency of using scheduling software. Authorized representative will be responsible for preparing the Baseline Schedule, required updates, revisions, Time Impact Analyses, and reports.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of work from parties involved.
3. Coordinate each construction activity in network with other activities and schedule in proper sequence.
LAVO – 315519/324970 01 32 18 - 4
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested. Work activities broken out within schedule of values shall be integrated into and made a logical part of the construction baseline schedule. Total costs for the component work activities shall equal contract price for that lump-sum item. Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. Total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments and the Construction Schedule.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-based, time-scaled Critical Path Method network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing work within applicable completion dates, regardless of Governments acceptance of schedule.
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using preliminary Critical Path Method network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates.