B08_Attachment_02_SOW_Technical_Specifications.pdf

PDF 387 KB Posted

Attached to
REPLACE METER BASES & PANELS AT CAPEHART Federal contract opportunity
Solicitation number
140P8624R0007
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document is a technical specification for the General Painting and Coating Requirements for a construction project to replace meter bases and panels at Capehart in the Golden Gate National Recreation Area. The key details are:

The project involves replacing the meter bases and panels at Capehart in the Golden Gate National Recreation Area. The work includes providing painting and coating materials, surface preparation, and application requirements. Specific requirements include using polyamide surface tolerant epoxy coatings, approved manufacturers, submittals, quality control, and delivery/storage/handling procedures. The painting and coating work is part of a larger electrical project encompassing general electrical requirements, conductors and cables, grounding and bonding, and raceways and boxes. The overall federal contract opportunity is for the National Park Service Pacific West Region to Replace Meter Bases and Panels at Capehart.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOLDEN GATE NATIONAL RECREATION AREA

SAUSALITO, CALIFORNIA

Replace Meter Bases and Panels at Capehart

GOGA

PMIS# 332727, 332740, 332735

CONSTRUCTION DOCUMENTS

TECHNICAL SPECIFICATIONS

National Park Service

Pacific West Region

March 5, 2023

GOGA 33272, 332740, 332735 General Painting and Coating Requirements

SECTION 09 90 00

GENERAL PAINTING & COATING REQUIREMENTS

PART 1 - GENERAL

1.1 GENERAL

A. General procedures and requirements for field-applied painting and coating.

1.2 REFERENCES

A. Master Painters Institute (MPI)

1. MPI(a), Mar 2001, ‘Architectural Painting Specification Manual’

1.3 SUBMITTALS

A. Product Data

1. Include following information for each painting system, arranged in same order as in Project

Manual.

a. Manufacturer's cut sheets for each component of system indicating ingredients and percentages by weight and by volume, environmental restrictions for application, and film thicknesses and spread rates.

1) If using a manufacturer based on MPI approval, also include copies of appropriate entries from MPI Approved Product List. Listing in MPI

Approved Product List is mandatory for Sections 09912, 0-9923 and 09924.

If proposed manufacturer has products listed for these three Sections, but not for other Sections, Contracting Officer may approve products submitted by proposed manufacturer for other Sections.

b. Manufacturer’s substrate preparation instructions and application instruction for each painting system used on Project.

c. Confirmation of colors selected and that each area to be painted or coated has color selected for it.

2. Provide two (2) copies of Product Data submission.

B. Samples - Provide two (2) twelve inch by twelve inch (12”x12”) minimum brush out cards for each paint or coating color to be selected by the Contracting Officer for approval.

1.4 QUALITY ASSURANCE

A. Regulatory Requirements - Paint and painting materials shall be free of lead and mercury, and have VOC levels acceptable to local jurisdiction.

B. Field Samples

1. Before application of any paint system, if required by Contracting Officer, meet on Project site with Contracting Officer, and Manufacturer's representative. Contracting Officer may select one surface for application of each paint system specified. This process will include establishing acceptable substrate conditions required for Project before application of paints and coatings.

2. Apply paint systems to surfaces indicated by Contracting Officer following procedures outlined in Contract Documents and Product Data submission specified above.

3. After approval of samples, proceed with application of paint system throughout Project.

Approved samples will serve as standard of acceptability.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Deliver specified products in sealed, original containers with Manufacturer’s original labels intact on each container. Deliver amount of materials necessary to meet Project requirements in single shipment. Notify Contracting Officer two working days before delivery of paint. B. Store materials in single place.

C. Keep storage area clean and rectify any damage to area at completion of work of this Section.

Maintain storage area at fifty-five (55) degree F minimum.

1.6 PROJECT CONDITIONS

A. Project Environmental Conditions

1. Perform painting operations at temperature and humidity conditions recommended by

Manufacturer for each operation and for each product.

2. Apply painting systems at lighting level of 540 Lux (fifty (50) foot candles) minimum on surfaces to be painted. Inspection of painting work shall take place under same lighting conditions as application. If painting and coating work is applied under temporary lighting, deficiencies discovered upon installation of permanent lighting will be considered latent damage as defined in MPI Manual, PDCA P1-92

1.7 SCHEDULING

A. Coordinate with other trades for materials and systems that require painting prior to installation.

B. Schedule painting and coating work to begin when work upon which painting and coating work is dependent has been completed. Schedule installation of pre-finished and non-painted items, which are to be installed on painted surfaces, after application of final finishes.

C. Schedule pre-finishing prior to installation of any surfaces that will not be accessible after installation.

1.8 MAINTENANCE

A. Extra Materials - Provide painting materials in Manufacturer's original containers and with original labels in each color used. Provide one (1) gallon of each finish coat. Label each can with color name, mixture instructions, date, and anticipated shelf life.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Materials used for any painting system shall be from single manufacturer unless approved otherwise in writing by painting system manufacturer. Include such approvals in Product Data submittal.

B. Linseed oil, shellac, turpentine, and other painting materials shall be pure, be compatible with other coating materials, bear identifying labels on containers, and be of highest quality of an approved manufacturer listed in MPI manuals. Tinting color shall be best grade of type recommended by Manufacturer of paint or stain used on Project.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Instructions to applicator to begin painting and coating work will indicate that substrates to receive painting and coating materials have been previously inspected as part of work of other

Sections and are complete and ready for application of painting and coating systems.

B. Before beginning work of this Section, examine, and test surfaces to be painted or coated for adhesion of painting and coating systems. Report in writing to Contracting Officer of conditions that will adversely affect adhesion of painting and coating work. Do not apply painting and coating systems until such adverse conditions are corrected by party responsible for adverse condition.

C. Report defects in substrates that become apparent after application of primer or first finish coat to Contracting Officer in writing and do not proceed with further work on defective substrate until such defects are corrected by party responsible for defect.

3.2 PREPARATION

A. Protection

1. Remove rags and waste used in painting operations from building each night. Take every precaution to avoid danger of fire.

2. Protect other finish work and adjacent materials during painting. Do not splatter, drip, or paint surfaces not intended to be painted. These items will not be spelled out in detail but pay special attention to the following:

a. Do not paint finish copper, bronze, chromium plate, nickel, anodized aluminum, or monel metal except as explicitly specified.

B. Surface Preparation

1. Prepare surfaces in accordance with MPI requirements and requirements of

Manufacturer for each painting system specified, unless instructed differently in Contract

Documents. Bring conflicts to the attention of the Contracting Officer in writing.

2. Surfaces to be painted shall be clean and free of loose dirt. Clean and dust surfaces before painting or finishing.

3. Do not perform exterior painting while surface is damp, unless recommended by

Manufacturer, nor during rainy or frosty weather. Interior surfaces shall be dry before painting. Moisture content of materials to be painted shall be within tolerances acceptable to Paint Manufacturer.

4. Degrease per SSPC-SP1 to remove all oils, grease, and foreign matter.

5. Sand metal face to create surface profile.

3.3 APPLICATION

A. Paint or finish complete all surfaces to be painted or coated as described in Contract

Documents, including but not limited to following items.

1. Paint electrical items that require field painting as indicated in Contract Documents. These include but are not limited to:

a. Electrical panel, meter enclosures and disconnect enclosures. Also includes risers and conduit. This includes all new exterior metal services. There is not painting of the interior required.

B. Paint two coats of polyamide surface tolerant epoxy

1. 5-10 DFT per coat

C. Spread materials smoothly and evenly. Apply coats to not less than wet and dry film thicknesses and at spreading rates for specified products as recommended by Manufacturer.

Touch up suction spots after application of first finish coat.

D. Paint shall be thoroughly dry and surfaces clean before applying succeeding coats.

E. Use fine sandpaper between coats as necessary to produce even, smooth surfaces.

F. Make edges of paint adjoining other materials or colors clean, sharp, and without overlapping.

G. Finished work shall be a “Properly Painted Surface” as defined in this Section.

3.4 ADJUSTMENT

A. Correct deficiencies in workmanship required to leave surfaces in conformance with “Properly

Painted Surface” as defined in this Section. Correction of “Latent Damage” and “Damage

Caused by Others,” as defined in this Section, is not included in work of this Section.

3.5 CLEANING

A. As work proceeds and upon completion of work of any painting Section, remove paint spots from floors, walls, glass, or other surfaces and leave work clean, orderly, and in acceptable condition.

Remove debris caused by work of paint Sections from premises.

3.6 PAINT COLOR SCHEDULE

A. Number and placement of interior and exterior paint colors and gloss levels shall be Color Level

II from MPI Manual, PDCA P3-93 as modified in paragraph 1, following.

1. Paint to match existing buildings. Color is believed to be Presidio White, but field samples must be approved prior to painting.

END OF SECTION

GOGA 332727, 332740, 332735 Electrical General Requirements

SECTION 26 00 00

ELECTRICAL GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. All electrical work shall be performed by, or under the direct supervision of an electrician licensed in the state of California.

GOGA 332727, 332740, 332735 Common Work Results for Electrical

SECTION 26 05 00

COMMON WORK RESULTS FOR ELECTRICAL

PART 1 – GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Electrical equipment coordination and installation.

2. Sleeves for raceways and cables.

3. Sleeve seals.

4. Grout.

5. Common electrical installation requirements.

1.3 DEFINITIONS

A. EPDM: Ethylene-propylene-diene terpolymer rubber.

B. NBR: Acrylonitrile-butadiene rubber.

1.4 SUBMITTALS

A. Product Data: For sleeve seals.

1.5 COORDINATION

A. Coordinate arrangement, mounting, and support of electrical equipment:

1. To allow maximum possible headroom unless specific mounting heights that reduce headroom are indicated.

2. To provide for ease of disconnecting the equipment with minimum interference to other installations.

3. To allow right of way for piping and conduit installed at required slope.

4. So connecting raceways, cables, wireways, cable trays, and busways will be clear of obstructions and of the working and access space of other equipment.

GOGA 332727, 332740, 332735 Common Work Results for Electrical

PART 2 - EXECUTION

2.1 COMMON REQUIREMENTS FOR ELECTRICAL INSTALLATION

A. Comply with NECA 1.

B. Measure indicated mounting heights to bottom of unit for suspended items and to center of unit for wall-mounting items.

C. Headroom Maintenance: If mounting heights or other location criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom consistent with these requirements.

2.2 SLEEVE INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Electrical penetrations occur when raceways, cables, wireways, cable trays, or busways penetrate concrete slabs, concrete or masonry walls, or fire-rated floor and wall assemblies.

B. Interior Penetrations of Non-Fire-Rated Walls and Floors: Seal annular space between sleeve and raceway or cable, using joint sealant appropriate for size, depth, and location of joint.

C. Roof-Penetration Sleeves: Seal penetration of individual raceways and cables in coordination with roofing work.

332727, 332740, 332735 LV Electrical Cables and Conductors

SECTION 26 05 19

LOW VOLTAGE ELECTRICAL POWER CONDUCTORS & CABLES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Building wires and cables rated 600 V and less.

2. Connectors, splices, and terminations rated 600 V and less.

3. Sleeves and sleeve seals for cables.

1.3 DEFINITIONS

A. EPDM: Ethylene-propylene-diene terpolymer rubber.

B. NBR: Acrylonitrile-butadiene rubber.

1.4 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Field quality-control test reports.

1.5 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

B. Comply with NFPA 70.

PART 2 - PRODUCTS

2.1 CONDUCTORS AND CABLES

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

B. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Alcan Products Corporation; Alcan Cable Division.

2. American Insulated Wire Corp.; a Leviton Company.

3. General Cable Corporation.

4. Senator Wire & Cable Company.

5. Southwire Company.

C. Copper Conductors: Comply with NEMA WC 70.

D. Conductor Insulation: Comply with NEMA WC 70 for Types THW, THHN-THWN and

XHHW.

2.2 CONNECTORS AND SPLICES

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

B. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. AFC Cable Systems, Inc.

2. Hubbell Power Systems, Inc.

3. O-Z/Gedney; EGS Electrical Group LLC.

4. 3M; Electrical Products Division.

5. Tyco Electronics Corp.

C. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated.

2.3 SLEEVES FOR CABLES

A. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, galvanized steel, plain ends.

B. Cast-Iron Pipe Sleeves: Cast or fabricated "wall pipe," equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless otherwise indicated.

2.4 SLEEVE SEALS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

B. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

C. Basis-of-Design Product: Subject to compliance with requirements, provide the product indicated on Drawings or a comparable product by one of the following:

1. Advance Products & Systems, Inc.

2. Calpico, Inc.

3. Metraflex Co.

4. Pipeline Seal and Insulator, Inc.

D. Description: Modular sealing device, designed for field assembly, to fill annular space between sleeve and cable.

1. Sealing Elements: EPDM interlocking links shaped to fit surface of cable or conduit.

Include type and number required for material and size of raceway or cable.

2. Pressure Plates: Stainless steel. Include two for each sealing element.

3. Connecting Bolts and Nuts: Stainless steel of length required to secure pressure plates to sealing elements. Include one for each sealing element.

PART 3 - EXECUTION

3.1 CONDUCTOR MATERIAL APPLICATIONS

A. Feeders: Copper. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

B. Branch Circuits: Copper. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

3.2 CONDUCTOR INSULATION AND MULTI-CONDUCTOR CABLE APPLICATIONS AND

WIRING METHODS

A. Service Entrance: Type THHN-THWN, single conductors in raceway.

B. Exposed Feeders: Type THHN-THWN, single conductors in raceway.

C. Feeders Concealed in Ceilings, Walls, Partitions, and Crawlspaces: Type THHN-THWN, single conductors in raceway.

3.3 INSTALLATION OF CONDUCTORS AND CABLES

A. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.

B. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway.

C. Support cables according to Division 26 Section "Hangers & Supports for Electrical Systems."

D. Identify and color-code conductors and cables according to Division 26 Section "Identification for Electrical Systems."

3.4 CONNECTIONS

A. Tighten electrical connectors and terminals according to manufacturer's published torque tightening values. If manufacturer's torque values are not indicated, use those specified in UL

486A and UL 486B.

B. Make splices and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than un-spliced conductors.

3.5 SLEEVE INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Coordinate sleeve selection and application with selection and application of penetration.

B. Roof-Penetration Sleeves: Seal penetration of individual cables with flexible boot-type flashing units applied in coordination with roofing work.

C. Aboveground Exterior-Wall Penetrations: Seal penetrations using sleeves and mechanical sleeve seals.

3.6 SLEEVE-SEAL INSTALLATION

A. Install to seal exterior-wall penetrations.

B. Use type and number of sealing elements recommended by manufacturer for cable material and size. Position cable in center of sleeve. Assemble mechanical sleeve seals and install in annular space between cable and sleeve.

332727, 332740, 332735 Grounding and Bonding

SECTION 26 05 26

GROUNDING & BONDING FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes methods and materials for grounding systems and equipment.

1.3 SUBMITTALS

A. Product Data: For each type of product indicated.

1.4 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

B. Comply with UL 467 for grounding and bonding materials and equipment.

PART 2 - PRODUCTS

2.1 CONDUCTORS

A. Insulated Conductors: Copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.

B. Bare Copper Conductors:

1. Solid Conductors: ASTM B 3.

2. Stranded Conductors: ASTM B 8.

3. Tinned Conductors: ASTM B 33.

4. Bonding Conductor: Sized per NEC, stranded copper conductor.

5. Bonding Jumper: Copper tape, braided conductors, terminated with copper ferrules; 15/8 inches (41 mm) wide and 1/16 inch (1.6 mm) thick.

6. Tinned Bonding Jumper: Tinned-copper tape, braided conductors, terminated with copper ferrules; 1-5/8 inches (41 mm) wide and 1/16 inch (1.6 mm) thick.

C. Bare Grounding Conductor and Conductor Protector:

1. No. 4 AWG minimum, soft-drawn copper.

2. Conductor Protector: Stranded cable sheathing.

3. Cable protector must adhere to NEC E3603.4. (250.66)

2.2 CONNECTORS

A. Listed and labeled by a nationally recognized testing laboratory acceptable to authorities having jurisdiction for applications in which used, and for specific types, sizes, and combinations of conductors and other items connected.

B. Bolted Connectors for Conductors and Pipes: Copper or copper alloy, bolted pressure-type, with at least two (2) bolts.

1. Pipe Connectors: Clamp type, sized for pipe.

C. Welded Connectors: Exothermic-welding kits of types recommended by kit manufacturer for materials being joined and installation conditions.

2.3 GROUNDING ELECTRODES

A. Ground Rods: Copper-clad, Zinc-coated Stainless steel, sectional type; Size properly according the NEC E3603.4 (250.66)

PART 3 - EXECUTION

3.1 APPLICATIONS

A. Conductors: Install solid conductor for No. 18 AWG and smaller, and stranded conductors for

No. 16 AWG and larger, unless otherwise indicated.

B. Underground Grounding Conductors: Install bare copper conductor, No. 4 AWG minimum.

1. Bury at least two (2) inches (600 mm) below grade

C. Conductor Terminations and Connections:

1. Pipe and Equipment Grounding Conductor Terminations: Bolted connectors.

3.2 INSTALLATION

A. Grounding Conductors: Route along shortest and straightest paths possible, unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.

B. Ground Rods: Drive rods until tops are two (2) inches (50 mm) below final grade.

1. Interconnect ground rods with grounding electrode conductor below grade and as otherwise indicated. Make connections without exposing steel or damaging coating, if any.

2. For grounding electrode system, install at least two (2) rods spaced at least one (1) rod length from each other and located at least the same distance from other grounding electrodes, and connect to the service grounding electrode conductor.

C. Bonding Straps and Jumpers: Install in locations accessible for inspection and maintenance, except where routed through short lengths of conduit.

1. Bonding to Structure: Bond straps directly to basic structure, taking care not to penetrate any adjacent parts.

332727, 332740, 332735 RACEWAYS AND BOXES

SECTION 26 05 33

RACEWAY & BOXES FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes raceways, fittings, boxes, enclosures, and cabinets for electrical wiring.

1.3 DEFINITIONS

A. EMT: Electrical metallic tubing.

B. ENT: Electrical nonmetallic tubing.

C. FMC: Flexible metal conduit.

D. IMC: Intermediate metal conduit.

1.4 SUBMITTALS

A. Product Data: For surface raceways, wireways and fittings, hinged-cover enclosures, and cabinets.

B. Shop Drawings: For the following raceway components. Include plans, elevations, sections, details, and attachments to other work.

1.5 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

B. Comply with NFPA 70.

PART 2 - PRODUCTS

2.1 METAL CONDUIT AND TUBING

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. AFC Cable Systems, Inc.

2. Alflex Inc.

3. Allied Tube & Conduit; a Tyco International Ltd. Co.

4. Anamet Electrical, Inc.; Anaconda Metal Hose.

5. Electri-Flex Co.

6. Manhattan/CDT/Cole-Flex.

7. Maverick Tube Corporation.

8. O-Z Gedney; a unit of General Signal.

9. Wheatland Tube Company.

B. Rigid Steel Conduit: ANSI C80.1.

C. Aluminum Rigid Conduit: ANSI C80.5.

D. IMC: ANSI C80.6.

E. EMT: ANSI C80.3.

F. Fittings for Conduit (Including all Types), EMT, and Cable: NEMA FB 1; listed for type and size raceway with which used, and for application and environment in which installed.

1. Fittings for EMT: Steel, set-screw, or compression type.

2.2 METAL WIREWAYS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Cooper B-Line, Inc.

2. Hoffman.

3. Square D; Schneider Electric.

B. Description: Sheet metal sized and shaped as indicated, NEMA 250, Type 1, 12, 3R, unless otherwise indicated.

C. Fittings and Accessories: Include couplings, offsets, elbows, expansion joints, adapters, holddown straps, end caps, and other fittings to match and mate with wireways as required for complete system.

D. Wireway Covers: Hinged type or Screw-cover type.

E. Finish: Manufacturer's standard enamel finish.

2.3 SURFACE RACEWAYS

A. Surface Metal Raceways: Galvanized steel with snap-on covers. Manufacturer's standard enamel finish in color selected by Architect.

1. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Thomas & Betts Corporation.

b. Walker Systems, Inc.; Wiremold Company (The).

c. Wiremold Company (The); Electrical Sales Division.

2.4 BOXES, ENCLOSURES, AND CABINETS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Cooper Crouse-Hinds; Div. of Cooper Industries, Inc.

2. Erickson Electrical Equipment Company.

3. Hoffman.

4. Hubbell Incorporated; Killark Electric Manufacturing Co. Division.

5. O-Z/Gedney; a unit of General Signal.

6. RACO; a Hubbell Company.

7. Robroy Industries, Inc.; Enclosure Division.

8. Scott Fetzer Co.; Adalet Division.

9. Spring City Electrical Manufacturing Company.

10. Thomas & Betts Corporation.

11. Walker Systems, Inc.; Wiremold Company (The).

12. Woodhead, Daniel Company; Woodhead Industries, Inc. Subsidiary. B. Sheet

Metal Outlet and Device Boxes: NEMA OS 1.

C. Cast-Metal Outlet and Device Boxes: NEMA FB 1, aluminum, Type FD, with gasketed cover.

D. Hinged-Cover Enclosures: NEMA 250, Type 1, with continuous-hinge cover with flush latch, unless otherwise indicated.

1. Metal Enclosures: Steel, finished inside and out with manufacturer's standard enamel.

PART 3 - EXECUTION

3.1 RACEWAY APPLICATION

A. Outdoors: Apply raceway products as specified below, unless otherwise indicated:

1. Exposed Conduit: Rigid conduit, IMC, RNC.

2. Concealed Conduit, Aboveground: Rigid conduit IMC, EMT.

3. Underground Conduit: Sch 80 -PVC, direct buried.

4. Boxes and Enclosures, Aboveground: NEMA 250, Type 3R, B. Comply with the following indoor applications, unless otherwise indicated:

1. Exposed, Not Subject to Physical Damage: MC

2. In-Wall: MC or NM.

3. Exposed and Subject to Severe Physical Damage: Rigid steel conduit, IMC.

4. Damp or Wet Locations: Rigid steel conduit, IMC.

5. C. Minimum Raceway Size: 3/4-inch (16-mm) trade size.

D. Raceway Fittings: Compatible with raceways and suitable for use and location.

1. Rigid and Intermediate Steel Conduit: Use threaded rigid steel conduit fittings, unless otherwise indicated.

E. Install nonferrous conduit or tubing for circuits operating above 60 Hz. Where aluminum raceways are installed for such circuits and pass through concrete, install in nonmetallic sleeve.

3.2 INSTALLATION

A. Comply with NECA 1 for installation requirements applicable to products specified in Part 2 except where requirements on Drawings or in this Article are stricter.

B. Complete raceway installation before starting conductor installation.

C. Install no more than the equivalent of three 90-degree bends in any conduit run.

D. Conceal conduit and EMT within finished walls, ceilings, and floors, unless otherwise indicated. Any home run junctions in mechanical rooms from the circuit panel to the attic may be surface mounted.

E. Threaded Conduit Joints, Exposed to Wet, Damp, Corrosive, or Outdoor Conditions: Apply listed compound to threads of raceway and fittings before making up joints. Follow compound manufacturer's written instructions.

F. Raceway Terminations at Locations Subject to Moisture or Vibration: Use insulating bushings to protect conductors, including conductors smaller than No. 4 AWG.

G. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not less than 200-lb (90-kg) tensile strength. Leave at least 12 inches (300 mm) of slack at each end of pull wire.

3.3 PROTECTION

A. Provide final protection and maintain conditions that ensure coatings, finishes, and cabinets are without damage or deterioration at time of Substantial Completion.

1. Repair damage to galvanized finishes with zinc-rich paint recommended by manufacturer.

332727. 332740, 332735 Panelboards and Meters

PANELBOARDS AND METERS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. general provisions of the Contract, including General and Supplementary Conditions and Division

01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Distribution panelboards.

2. Meter Cans

3. Group Metering

1.3 SUBMITTALS

A. Product Data: For each type of panelboard, switching and overcurrent protective device, transient voltage suppression device, accessory, and component indicated. Include dimensions and manufacturers' technical data on features, performance, electrical characteristics, ratings, and finishes.

B. Shop Drawings: For each panelboard and related equipment.

1. Include dimensioned plans, elevations, sections, and details. Show tabulations of installed devices, equipment features, and ratings.

2. Detail enclosure types and details for types other than NEMA 250, Type 1.

3. Detail bus configuration, current, and voltage ratings.

4. Short-circuit current rating of panelboards and overcurrent protective devices.

5. Include evidence of NRTL listing for series rating of installed devices.

6. Detail features, characteristics, ratings, and factory settings of individual overcurrent protective devices and auxiliary components.

7. Include wiring diagrams for power, signal, and control wiring.

C. Panelboard Schedules: For installation in panelboards. Submit final versions after load balancing.

1.4 QUALITY ASSURANCE

A. Source Limitations: Obtain panelboards, overcurrent protective devices, components, and accessories from single manufacturer.

B. Product Selection for Restricted Space: Drawings indicate maximum dimensions for panelboards including clearances between panelboards and adjacent surfaces and other items.

Comply with indicated maximum dimensions.

C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

D. Comply with NEMA PB 1.

E. Comply with NFPA 70.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Remove loose packing and flammable materials from inside panelboards

B. Handle and prepare panelboards for installation according to NECA 407.

1.6 PROJECT CONDITIONS

A. Environmental Limitations:

1. Rate equipment for continuous operation under the following conditions unless otherwise indicated:

a. Ambient Temperature: Not exceeding twenty-three (23) deg F (minus five (5) deg

C) to plus one hundred-four (104) deg F (plus forty (40) deg C).

b. Altitude: Not exceeding five hundred 500 meters

B. Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by the Government or others unless permitted under the following conditions:

1. Notify CO and COR no fewer than seven (7) days in advance of proposed interruption of electric service.

2. Do not proceed with interruption of electric service without COR’s written permission.

3. Do not interrupt electric service for more than one work day. Temporary provisions are required if permanent power is not reconnected by the end of the work day.

4. Comply with NFPA 70E.

1.7 COORDINATION

A. Coordinate layout and installation of panelboards and components with other construction that penetrates walls or is supported by them, including electrical and other types of equipment, raceways, piping, encumbrances to workspace clearance requirements, and adjacent surfaces.

Maintain required workspace clearances and required clearances for equipment access doors and panels.

1.8 WARRANTY

A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace transient voltage suppression devices that fail in materials or workmanship within specified warranty period.

1. Warranty Period: Five (5) years from date of Substantial Completion.

1.9 EXTRA MATERIALS N/A

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS FOR PANELBOARDS, METER MAINS, LOAD CENTERS

A. Enclosures: Surface-mounted cabinets. Match existing location per building.

1. Rated for environmental conditions at installed location.

a. Exterior Environment: NEMA 3R

b. Front: Secured to box with concealed trim clamps. For surface-mounted fronts, match box dimensions; for flush-mounted fronts, overlap box.

c. Interior Environment: NEMA 1

2. Hinged Front Cover: Entire front trim hinged to box and with standard door within hinged trim cover.

3. Skirt for Surface-Mounted Panelboards: Same gage and finish as panelboard front with flanges for attachment to panelboard, wall, and ceiling or floor.

4. Gutter Extension and Barrier: Same gage and finish as panelboard enclosure; integral with enclosure body. Arrange to isolate individual panel sections.

5. Integrated main breakers for each meter attached to meter enclosure and labeled accordingly.

6. Finishes:

a. Panels and Trim: Galvanized Steel. Exterior panels painted with two coats of

Polyamide Surface Tolerant Epoxy at 5-10 DFT/coat (coatings are a bid option).

b. Back Boxes: Galvanized steel

c. Fungus Proofing: Permanent fungicidal treatment for overcurrent protective devices and other components.

7. Directory Card: Inside panelboard door, mounted in transparent card holder.

8. B. Incoming Mains Location: Top and bottom.

a. Meter panels will be overhead but must have provisions for underground.

C. Phase, Neutral, and Ground Buses:

1. Material: Hard-drawn copper, ninety-eight (98) percent conductivity.

2. Equipment Ground Bus: Adequate for feeder and branch-circuit equipment grounding conductors; bonded to box.

3. Isolated Ground Bus: Adequate for branch-circuit isolated ground conductors; insulated from box.

4. Extra-Capacity Neutral Bus: Neutral bus rated two hundred (200) percent of phase bus and UL listed as suitable for nonlinear loads.

5. Split Bus: Vertical buses divided into individual vertical sections.

D. Conductor Connectors: Suitable for use with conductor material and sizes.

1. Material: Hard-drawn copper, ninety-eight (98) percent conductivity.

2. Main and Neutral Lugs: Mechanical type.

3. Ground Lugs and Bus-Configured Terminators: Mechanical type.

E. Future Devices: Mounting brackets, bus connections, filler plates, and necessary appurtenances required for future installation of devices.

F. Panelboard Short-Circuit Current Rating: Rated for series-connected system with integral or remote upstream overcurrent protective devices and labeled by an NRTL. Include size and type of allowable upstream and branch devices, listed and labeled for series-connected shortcircuit rating by an NRTL.

G. Panelboard Short-Circuit Current Rating: Fully rated to interrupt symmetrical short-circuit current available at terminals.

2.2 APPLIANCE, DISTRIBUTION, AND BRANCH CIRCUIT PANELBOARDS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton, Square D, GE, or Contracting Officer approved equal.

B. Panelboards: NEMA PB 1, power and feeder distribution type.

C. Doors: Secured with vault-type latch.

D. Mains: No main breaker required on the panel boards. Main breaker to be on exterior of the building.

E. Branch Overcurrent Protective Devices for Circuit-Breaker Frame Sizes Larger than 125 A: Bolt-on circuit breakers.

2.4 DISCONNECTING AND OVERCURRENT PROTECTIVE DEVICES

A. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings by the following:

1.To match the manufacture of the branch circuit panelboards.

B. Molded-Case Circuit Breaker (MCCB): Comply with UL 489, with series-connected rating to meet available fault currents.

1. GFCI Circuit Breakers: Single- and two-pole configurations with Class A ground-fault protection (6-mA trip).

2. Arc-Fault Circuit Interrupter (AFCI) Circuit Breakers: Comply with UL 1699; 120/240V, single-pole configuration.

2.5 GROUP MEETERING

2.5.1 Basis of Design: Eaton 1MP2204R, 200-amp vertical group meter main, 400-amp main copper buss, factory installed breakers. Surface mounted, overhead service.

1. Locations- See SOW-all duplexes.

2. Execution- Each meter shall feed independent, addressed units.

3. All meters shall have means of disconnect per NEC 230.71.

2.7 METER MAINS

1. Basis of Design: Eaton B-Line Product 2M2R.

2. Locations: Building numbers See SOW-all single-family buildings.

3. Execution- Meter mains shall replace existing meter main and shall feed interior panel.

4. All meters shall have means of disconnect per NEC 230.71.

2.8 DISTRBUTION PANELS

1. Basis of Design: Eaton Product CHP32L225X5. 225-amp 120/240V AC, 1 phase, plug on neutral, main lug load center, copper buss, 32-space/64-pole. NEMA 1-Indoors

2. Locations: Each mechanical room. Note: Excludes 816A. Existing interior panel at 816A is 200-amp. Only run new feeder for 816A.

3. Execution- Panels shall be flush mounted in the same location as the existing interior panel. In the case that panels are currently exterior mounted, panels shall be located at the place of the mechanical room junction box.

4. Any sheetrock removed for access shall be cleanly cut with a utility knife. Drywall shall be patched and finished to a Level 1 finish.

4. ACCESSORY COMPONENTS AND FEATURES

A. Accessory Set: Include tools and miscellaneous items required for overcurrent protective device test, inspection, maintenance, and operation.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Receive, inspect, handle, and store panelboards according to NECA 407.

B. Examine panelboards before installation. Reject panelboards that are damaged or rusted or have been subjected to water saturation.

C. Examine elements and surfaces to receive panelboards for compliance with installation tolerances and other conditions affecting performance of the Work.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. Install panelboards and accessories according to NECA 407.

B. Comply with mounting and anchoring requirements specified in Division 26.

C. Mount panelboard cabinet plumb and rigid without distortion of box. Mount recessed panelboards with fronts uniformly flush with wall finish and mating with back box.

D. Install overcurrent protective devices and controllers not already factory installed.

1. Set field-adjustable, circuit-breaker trip ranges.

E. Install filler plates in unused spaces.

F. Arrange conductors in gutters into groups and bundle and wrap with wire ties.

G. Comply with NECA 1.

3.3 IDENTIFICATION

A. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs complying with Division 26 Section 26 05 53 "Identification for Electrical Systems."

B. Create a directory to indicate installed circuit loads; incorporate the Government's final room designations. Obtain approval before installing. Use a computer or typewriter to create directory; handwritten directories are not acceptable.

C. Panelboard Nameplates: Label each panelboard with a nameplate complying with requirements for identification specified in Division 26 Section 26 05 53 "Identification for

Electrical Systems."

D. Device Nameplates: Label each branch circuit device in distribution panelboards with a nameplate complying with requirements for identification specified in Division 26 Section 26

05 53 "Identification for Electrical Systems."

3.4 FIELD QUALITY CONTROL

A. Acceptance Testing Preparation:

1. Test insulation resistance for each panelboard bus, component, connecting supply, feeder, and control circuit.

2. Test continuity of each circuit.

B. Panelboards will be considered defective if they do not pass tests and inspections.

3.5 ADJUSTING

A. Load Balancing: After Substantial Completion, but not more than sixty (60) days after Final

Acceptance, measure load balancing and make circuit changes.

1. Measure as directed during period of normal system loading.

2. Perform load-balancing circuit changes outside normal occupancy/working schedule of the facility and at time directed.

3. After circuit changes, recheck loads during normal load period. Record all load readings before and after changes and submit test records.

4. Tolerance: Difference exceeding twenty (20) percent between phase loads, within a panelboard, is not acceptable. Rebalance and recheck as necessary to meet this minimum requirement.

00 00 00 Cover
SECTION 09 90 00 Painting
GENERAL PAINTING & COATING REQUIREMENTS
Section 26 00 00 Electrical General Requirements
ELECTRICAL GENERAL REQUIREMENTS
SECTION 26 05 00 Common Work Results
COMMON WORK RESULTS FOR ELECTRICAL
SECTION 26 05 19
LOW VOLTAGE ELECTRICAL POWER CONDUCTORS & CABLES
SECTION 26 05 26 Grounding and Bonding
GROUNDING & BONDING FOR ELECTRICAL SYSTEMS
SECTION 26 05 33 Raceway and Boxes
RACEWAY & BOXES FOR ELECTRICAL SYSTEMS
SECTION 26 24 16 PANELBOARDS
PANELBOARDS AND METERS

File details come from the government source that posted it. Updated .