B08_Attachment 0002_SEPM_QASP_22Dec2022 Final.docx

DOCX document 38 KB Posted

Attached to
W15P7T-23-R-0004 - PEO C3T - Systems Engineering and Program Management (SEPM) Support Services
Solicitation number
SEPM-W15P7T-23-R-0004
Issued by

About this file

This document outlines a Quality Assurance Surveillance Plan (QASP) for contract W15P7T-23-R-0004 to provide Systems Engineering and Program Management (SEPM) Support Services to the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground. The contractor shall provide support services across the total life cycle of Mission Command systems, including system engineering, network engineering, architecture development, interoperability engineering, information assurance, technology transition, testing, fielding, training, cybersecurity, business management, information management, and public affairs. Performance will be monitored through methods such as direct observation, periodic inspections of monthly reports, user surveys, validated complaints, and inspections of all deliverables to ensure they meet standards for timeliness, accuracy, and quality at least 90% of the time.

View the file

Other files

File Type Posted
B08_Attachment 0008_Draft Task Order W15P7T-23-R-0004 20 July 2023.docx DOCX document
B08_Attachment 0015_W15P7T-23-R-0004 SEPM RFP QA.xlsx XLSX spreadsheet
B08_Attachment 0009_W15P7T-23-R-0004 RFP Instructions Amendment 001.pdf PDF
B08_Attachment 0005_SEPM Cost Price Template 20 July 2023.xlsx XLSX spreadsheet
B08_Attachment 0001_SEPM IDIQ PWS 17 July 2023.pdf PDF
B08_W15P7T-23-R-0004 Solicitation Document 20 July 2023.pdf PDF
B08_Attachment 0005_SEPM Cost Price Template.xlsx XLSX spreadsheet
B08_Attachment 0012_Draft RFP QA Sheet.xlsx XLSX spreadsheet
B08_Attachment 0006_SEPM LCAT Descriptions and LOE.xlsx XLSX spreadsheet
B08_Attachment 0013_8a Small Business Certification Template.pdf PDF
B08_Attachment 0007_SEPM TO PWS 23 June 2023.docx DOCX document
B08_Attachment 0003_DD254 SEPM W15P7T23R0004.pdf PDF
B08_Attachment 0011_SAM Sample.pdf PDF
B08_Attachment 0009_W15P7T-23-R-0004 RFP Instructions 30 June 2023.pdf PDF
B08_W15P7T-23-R-0004 Solicitation Document.pdf PDF
B08_Attachment 0003_W15P7T23R0004 SCIAddendum_DD254_FY23.pdf PDF
B08_Attachment 0001_SEPM IDIQ PWS 23 June 2023.pdf PDF
B08_Attachment 0014_W15P7T-23-R-0004 SEPM RFP QA Template.xlsx XLSX spreadsheet
B08_Attachment 0004_GFP Attachment W15P7T23R0004.pdf PDF
B08_Attachment 0008_Draft Task Order W15P7T-23-R-0004.docx DOCX document
B08_Attachment 0010_Past Performance Questionnaire.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

As of 12/16/2022 Quality Assurance Surveillance Plan (QASP)

1. Contract (W15P7T-23-R-0004): System Engineering and Program Support (SEPM)

2. Work Requirements:

· 1 - Management Transition In (Staffing) and Transition Out Plan

· 2 - Program Management Support

· 3 - Technical Engineering Support

· 4 - Readiness Management Support

· 5 - Business and Operations Management Support

· 6 – Public Affairs Support

· 7 – Information Management Support

3. Primary Method of Surveillance:

The Contracting Officer’s Representative (COR) will conduct informal periodic inspections in accordance with performance standards for items 1-5 and random sampling for item 6 in the table below. The COR will also conduct Customer Satisfaction Surveys on a quarterly basis, or as needed. The Government will conduct unscheduled inspections in response to validated customer complaints received.

4. Scope of Performance:

The Contractor shall provide support in a diverse range of support services that span the total life cycle of Mission Command systems, to include System of Systems Engineering and Integration, Network Engineering, Architecture Development, Interoperability Engineering, Information Assurance, Technology Transition/Insertion, Testing, Fielding, Training, Cybersecurity, Business Management, Information Management, and Public Affairs. All must be planned and executed in coordination with multiple units and organizations, with special consideration for the US Army war-fighting mission and the current operations tempo (OPTEMPO) of US Army warfighting units as they undergo exercises and training events, deployment, operations, redeployment and reset. Program Executive Office, Command, Control and Communications Tactical (PEO C3T) must also support a series of Army, Joint, and Combined experiments, demonstrations and exercises that will help define the concepts, requirements, doctrine, and equipment for the continued digitization and transformation of the Army.

The Government may require surge support during the base or any option period, and surge modifications will be within the scope of the contract and provide increased support for the defined task areas of this PWS. Surge support over the life of the contract will not exceed 5% of the contractor’s total proposed cost/price for the base and all option periods, excluding any six-month extension of services pursuant to FAR 52.217-8.

5. Performance Standards: The Performance Standards Summary Matrix below, includes performance standards. The Government must use these standards to determine contractor performance and must compare contractor performance to the Acceptable Quality Level (AQL).

Performance Standard
Acceptable Quality Level (AQL)
Method of Surveillance

And Frequency Applicable CDRL/PWS Reference

1. Management Transition In (Staffing) and Transition Out Plan

Prime must provide acceptable candidates within 30 calendar days of contract award and have that candidate on-boarded and fully functional within 60 days of notification.
Staffing requirements successfully satisfied within 60 days
N/A- Request for Proposal (RFP) Requirement
2. Provide Monthly Program Status and Financial reports
Performance occurs with no required re-performance or re-work at least 90% of the time. Problems that occur are minor and are resolved in a satisfactory manner.
COR to request feedback from Government Technical Points of Contacts on a montly basis or as needed.
Contract Data Requirements List (CDRL) B001, C001, C002
3. Training: All contractor employees must complete Mandatory Training Requirements within dates specified in PEO C3T Chief of Staff Memorandum dated 17 Nov 2021
Contract Employee list with Training certification maintained current.
COR to inspect and/or audit contractor’s files on a Quarterly basis or as needed by the Government
CDRL E001, PWS 1.15
4. Contractor Manpower Reporting (CMRA) will be done timely and completed correctly
Contractor shall comply with CMRA standards timely, 100% of the time.
COR conduct annual Contractor Manpower Reporting review of input into SAM.gov
PWS 4.1.5
5. Government Furnished Equipment Status
Contractor shall conduct, at a minimum, a 10% inventory of Government Furnished Equipment on a monthly basis and provide results to the COR no later than (NLT) 15th of the month.
COR must review inventory results, file findings and report discrepancies, if any, to the Contracting Officer NLT 30th of the month
CDRL D001
6. Manpower Information Retrieval and Reporting System (MIRARS) Reporting
Contractor shall comply with daily MIRARS reporting requirement 100% of the time.
COR will provide MIRARS reporting to the contractor monthly, who shall review and provide corrective action for discrepancies.
PWS 1.14
7. Staffing/Recruitment
Contractor shall fill vacant positions within 45 calendar days of requirement being identified, 100% of the time
Staffing requirements successfully satisfied within 45 days of identification.
N/A
8. Applicable Tasks/Subtasks/Reporting Requirements (i.e. Briefing materials, technical/business reports, studies and documentation, schedules, meetings, trip reports, white papers, etc., will be delivered on time, be correct, and be delivered in appropriate electronic media, in accordance with (IAW) Government Point of Contact (POC) guidance
Materials contain required information and are delivered on time at least 90% of the time. Revisions that occur are minor and are resolved in a satisfactory manner.
Technical Point of Contacts (TPOCs) to do 100% inspection of the materials when delivered, and report discrepancies to the COR within 3 businesses days. COR to conduct customer satisfaction surveys quarterly.
CDRLs A001, D002, F001

Table 5.1 Performance Standards and AQL

6. Mandatory or regulatory compliance items:

The contractor shall provide initial proof of compliance with regulatory and compliance items contained in the contract. The COR and the Contracting Officer (KO) will evaluate the initial submission and will conduct ad hoc reviews of the contractor's compliance throughout the remainder of the contract. The contractor shall monitor compliance as required by FAR 52.222-50, Combating Trafficking in Persons, and report any issues to the KO.

7. Acceptable Quality Level (AQL):

The AQL for this project is as provided in Table 5.1 above due to the critical support provided by mainframe operations.

8. Evaluation Method:

Various methods exist to monitor performance. The COR must use the surveillance methods listed below in the administration of this QASP.

Regardless of the surveillance method, the COR shall always contact the contractor's task manager or on-site representative when a defect is identified and inform the manager of the specifics of the problem. The COR, with assistance from the KS, shall be responsible for monitoring the contractor’s performance in meeting a specific performance standard/AQL.

a. DIRECT OBSERVATION. All applicable Tasks/Subtasks Will be performed through 100% surveillance. This will include the Management Transition In (Staffing) and Transition Out Plan.

b. PERIODIC INSPECTION. the Monthly Program Status and Financial reports will be 100% monitored on a monthly basis to ensure that it is complete, current and correct. Also to ensure that there is no differential between what is being reported in the monthly financials and the resulting invoice. If invoices are to be presented on a bi-weekly basis then the financial reports must coincide.

c. USER SURVEY. Random survey will be provided to the TPOCs not less than semi-annually to determine adequacy of support for all applicable performance aspects.

d. VALIDATED USER/CUSTOMER COMPLAINTS. Any complaints received in the surveys or independent of the surveys from the TPOC or related parties shall be investigated and validated within 90 days of receipt of the complaint.

e. 100% INSPECTION. Will be conducted on all deliverables identified in the PWS.

f. PROGRESS OR STATUS MEETINGS. Shall be held monthly to review the Monthly Status and Monthly Financial Reports and the associated invoice for the time period in question.

Surveillance results may be used as the basis for actions against the contractor up to and including termination.

9. Performance Reviews/Standards:

The COR shall meet with the contractor not less than monthly to assess performance and shall provide a written assessment of the determined contractor performance for each monthly period. It will be documented if the contractor exceeds, meets, or does not meet a given standard and acceptable quality level. The following ratings shall be used based upon the AQL shown in the performance standards table:

EXCEPTIONAL:
Performance significantly exceeds contract requirements to the Government’s benefit.
SATISFACTORY:
Performance meets contractual requirements.
UNSATISFACTORY:
Performance does not meet contractual requirements.

Enclosure 6, Page 1 of 2 Pages 17Jul2013/Version 2

SEPM, QASP

Page 1 of 3 Pages