This document is a Contract Price Schedule related to Solicitation Number 140P8624R0022 for the Renewal of the Baker Beach Restroom Facility at Golden Gate National Recreation Area. The solicitation requires refurbishment of a heavily used public restroom facility.
The Contract Price Schedule lists the base line items, which include replacement of signs, windows, roofing, painting, flooring, fixtures, and carpentry work, with a total base price of $0. There are also numerous option line items for additional square footage of roof decking replacement, with unit prices per 100 square feet. The total price for all options is $0. Offerors are required to submit pricing for the base line items and all option line items. The solicitation also includes sample price schedules for Design-Bid-Build and Design-Build contract types.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule
| Contract Price Schedule | |
| National Park Service | |
| Solicitation Number: | 140P8624R0022 |
| PARK - PMIS: | GOGA 336617 |
| Developed Area: | Golden Gate National Recreation Area | |||||
| Project Title: | Renewal of Baker Beach Toilets | |||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | ||||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | ||||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | ||||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | ||||||
| govern. Round totals and extended prices to whole dollars. | ||||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Unit of Measure | Unit Price | Total Price | ||
| 1 | Signs Replacement | lump sum | ||||
| 2 | Window Screens and Skylights Replacment | lump sum | ||||
| 3 | Removal and Replacement of Roofing Shingles and Underlayment | lump sum | ||||
| 4 | Exterior Painting | lump sum | ||||
| 5 | Interior Painting | lump sum | ||||
| 6 | Interior Flooring | lump sum | ||||
| 7 | Restroom Fixtures | lump sum | ||||
| 8 | Carpentry | lump sum | ||||
| 9 | Selective Demolition of Restroom Fixtures | lump sum | ||||
| 10 | Rental Toilets | lump sum | ||||
| TOTAL BASE PRICE (Contract Line Item Number 1 through 10) ------------------------------------------------------------------------ | $0 | |||||
| OPTION ITEMS | ||||||
| 11 | T&G Roof Decking – 100sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 100 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 12 | T&G Roof Decking – 200sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 200 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 13 | T&G Roof Decking – 300sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 300 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 14 | T&G Roof Decking – 400sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 400 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 15 | T&G Roof Decking – 500sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 500 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 16 | T&G Roof Decking – 600sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 600 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 17 | T&G Roof Decking – 700sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 700 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 18 | T&G Roof Decking – 800sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 800 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| 19 | T&G Roof Decking – 936sqft | |||||
| Replacement of rotted tongue and groove roof decking comprised of 936 sq ft. Option will be bid per 100 sq ft to only replace decking in need of replacement and will include all materials and equipment required to complete the work. | LS | $0 | ||||
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 11) ----------------------------------------------------------- | $0 | |||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 11) -------------------------- | $0 | |||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Design-Bid-Build (DBB) Sample
| Contract Price Schedule - Design-Bid-Build (DBB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Old Faithful | ||||
| Project Title: | Johnstonian Visitors Center | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Visitors Center | 1 | Lump Sum | $0.00 | |
| 2 | Water Line | 400 | Lineal Feet | - 0 | |
| 3 | Sanitary Sewer Line | 200 | Lineal Feet | - 0 | |
| 4 | Rock Excavation | 150 | Cubic Yards | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 4) --------------------------------------------------------------------------------- | $0.00 | ||||
| 5 | OPTION A, Geothermal Wells | 1 | Lump Sum | - 0 | |
| 6 | OPTION B, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 5 and 6) ------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Design-Build (DB) Sample
| Contract Price Schedule - Design-Build (DB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Yosemite Valley | ||||
| Project Title: | Design and Build a New Structure | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Design | 1 | Lump Sum | $0.00 | |
| 2 | Construction | 1 | Lump Sum | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 and 2) --------------------------------------------------------------------------------------- | $0.00 | ||||
| 3 | OPTION A, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3) ---------------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 3) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
File details come from the government source that posted it. Updated .