B08_Att_02_Replace_Spine_Trail_Culvert_Div_1_Specs_4-25-24.pdf

PDF 376 KB Posted

Attached to
GOGA-REPLACE CULVERT AT SPINE TRAIL Federal contract opportunity
Solicitation number
140P8624Q0052
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document contains Division 01 construction specifications for a federal contract opportunity to remove a storm-damaged culvert and replace the culvert and culvert stream crossing at Golden Gate National Recreation Area in San Mateo County, California.

The key details are:

  • The project involves removing the existing damaged corrugated metal culvert pipe, replacing it with a new culvert, reconstructing the access crossing, and constructing two concrete headwalls at the inlet and outlet of the culvert.
  • The contractor must prepare and submit an Under-an-Acre Pollution Prevention Plan (UPPP) detailing pollution prevention measures for the less-than-one-acre project site.
  • The contractor is responsible for all quality control, site inspections, and maintenance of temporary erosion and pollution control measures during construction.
  • Mobilization, demolition, grading, culvert installation, and site restoration work is included in the contract.
  • The federal agency involved is the National Park Service Pacific West Region.

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOLDEN GATE NATURAL RECREATION

AREA

PMIS No. 334583

Replace Spine Trail Culvert Crossing

Division 01

CONSTRUCTION SPECIFICATIONS

NATIONAL PARK SERVICE

PACIFIC WEST REGION

April 25, 2024

GOGA - 334583 TOC - 1

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS NO. OF PAGES

Part 1 – Summary of Work (Section 01 11 00) Part 1A – Definition of Contract Line Items (Section 01 27 00) Part 2 – Work Restrictions (Section 01 11 40) Part 3 – Project Management (Section 01 31 00) Part 4 – Submittal Procedures (Section 01 33 23) Part 5 – Safety Requirements (Section 01 35 23) Part 6 – Quality Requirements (Section 01 40 00) Part 7 – Temporary Facilities and Controls (Section 01 50 00) Part 8 – Under an Acre Pollution Prevention (Section 01 57 23) Part 9 – Imported Soil (Section 01 67 01) Part 10 – Mobilization / Demobilization (Section 01 71 13) Part 11 – Execution (Section 01 73 40) Part 12 – Closeout Procedures (Section 01 77 00) Part 13 – Soil Management (Section 01 89 31)

DIVISION 01

GENERAL REQUIREMENTS

GOGA – 334583 Division 1 Specifications - 1

DIVISION 01 PROJECT SPECIFICATIONS

GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK (SECTION 01 11 00)

1.1 WORK COVERED BY CONTRACT DOCUMENTS

A. General: All work outlined below will be performed under a single contract.

B. Project Location: This project is located at one location in the Golden Gate National Recreation Area.

1. The Spine Trail culvert is located at coordinates 37.52900, -122.49760

C. Project Background: A series of storms impacted the state of California in December of 2022.

The excessive rainfall from these storms caused high flows in San Vicente Creek in San Mateo County California. The high flows over topped a culvert crossing in the creek and washed out the fill material over the culvert and damaged the culvert pipe. The culvert served as a crossing over the creek for Spine Ridge Trail, a much-used hiking trail that is part of the Rancho Corral de Tierra section of the Golden Gate National Recreation Area. The culvert also serves as the only access to several buildings used by the Ember Ridge Equestrian Center, a leaseholder of the Golden Gate National Recreation Area.

D. Project Scope of Work: The scope of this task is to remove the existing damaged corrugated metal culvert pipe (CMP), replace them with a new CMP, reconstruct the access crossing, and construct two concrete headwalls at the inlet and outlet of the culvert to protect the crossing.

E. Environmental protection: Work shall include protection of the natural environment with all means necessary, including measures required by the Government and Contractor’s best management practices. To minimize environmental impact, construction activity shall be limited to a small allowable work area and shall require submittal of an Under an acre Pollution Prevention Plan (UPPP) and adherence to the plan.

The work is being conducted under permits from the State of California Water Board. All work activities must conform to the permit requirements. The contractor is required to submit a work plan to NPS for approval. The work plan shall provide details of how the contractor plans to adhere to the permit requirements.

1.2 REFERENCE DOCUMENTS / REPORTS

A. General: The following reference documents / reports are attached or available upon request to supplement the information in the specifications:

1. NPS Forms (RFI, CM-16, and QC Daily Report)

2. Site Location Map

3. Park Regulations

GOGA – 334583 Division 1 Specifications - 2

1.3 GOVERNMENT-FURNISHED ITEMS

A. The Government is not providing any Government furnished items.

1.4 PUBLIC / STAFF USE OF THE SITE

A. General: The project site will be open to the public and/or staff during construction. The contractor shall at all times conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer’s Representative (COR).

1.5 CONTRACTOR USE OF SITE

A. General: Limit use of the site during the construction period to the project area limits.

B. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

C. Site Access: The contractor shall access the project site as provided at the preconstruction meeting. Do not drive vehicles off road or access non-project areas without permission from the

COR.

D. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until 5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires prior approval from the COR.

E. Staging and Storage: Confine the storage of equipment and materials to the staging / lay-down / storage areas as established at the preconstruction meeting.

F. Waste Management: Construction debris and stormwater generated by the work shall be fully contained and controlled at all times so as to not run off into the surrounding natural environment. An UPPP detailing the plan shall be developed and submitted for approval before any work begins.

G. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or Park Dispatch at the first available opportunity at (702) 293-8998.

H. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation.

Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

PART 1A – DEFINITION OF CONTRACT LINE ITEMS (SECTION 01 27 00)

1A.1 Contract Line Item 1 – Mobilization/Demobilization

GOGA – 334583 Division 1 Specifications - 3

A. See Part 8A – Section 01 71 13 for details of this item.

1A.2 Contract Line Item 2 – Remove the damaged Spine Trail culvert and remains of the existing culvert crossing, furnish, and install new CMP culvert, furnish and install concrete head walls at the inlet and outlet of the culvert, furnish and install fill material, and furnish and install asphalt pavement matching the existing trail pavement. All work and materials shall conform to the Federal Highway Lands specifications and drawings. This item includes submittals, environmental protection, construction services to demolish, load, haul and dispose of demolition debris, and closeout procedures needed to perform the work as described in the construction documents.

A. See SOW for work details of this item.

B. Measurement for payment will be compliance with the construction documents and permit requirements and certification by the COR. No measurement will be made of quantities for payment. Payment shall be by lump sum. Lump sum price for this bid item shall be considered as including all labor, equipment, materials, and incidentals to complete the specified work.

PART 2 – WORK RESTRICTIONS (SECTION 01 11 40)

2.1 WORK RESTRICTIONS

A. General: The Contractor must comply with the following work restrictions:

B. Contractor personnel shall comply with all Federal and State laws and regulations, including the Golden Gate National Recreation Area Superintendent’s Compendium. Any exception must be specifically justified and approved in writing by the Contracting Officer (CO). The Superintendent’s Compendium can be found at this internet address:

https://www.nps.gov/goga/learn/management/upload/508_2020-GOGA-Compendium-signed.pdf.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the COR.

D. Vehicles / Heavy Equipment:

1. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations may result in a citation being issued to the driver.

2. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.

3. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.

GOGA – 334583 Division 1 Specifications - 4

4. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

5. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the COR of spills.

6. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.

7. Slow Vehicles: The Contractor is to notify the COR of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.

8. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the Park road corridor. Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the COR of oversized vehicles, scheduled dates, and estimated arrival times at the park entrance; and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.

9. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11). No loads heavier than the current load rating for park roads and bridges will be permitted.

10. Water and Wastewater Systems: The Contractor is not authorized to open/close valves, operate pumps and/or de-energize the water or wastewater system; a NPS Utility Systems Repairer/Operator (USRO) must do this or be onsite to observe.

11. Water: If Contractor wishes to use water provided by NPS, Contractor is to install NPS approved backflow preventer and meter at NPS specified location. Contractor will be billed monthly at rate of $65 per 1,000 gallons not to exceed 10,000 gallons per day. Prior to using water, agreement between NPS and contractor must be signed. Billings are sent electronically via email, thus additional information from contractor is point of contact information to send billings and finally company tax ID number.

E. Resource Protection:

1. General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:

GOGA – 334583 Division 1 Specifications - 5

2. Preservation of Natural Features: Prevent damage to natural surroundings. Do not attach ropes, wires, guy lines, cables, or chains to trees or vegetation. Restore damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.

3. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles (especially the tires), equipment, tools, supplies, and materials prior to packing / loading. The Park requires and will perform inspections to prevent transport of non-native species PRIOR to arriving at the park entrance. Contact the Equipment Inspector at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.

4. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and watch for animals on or alongside road or at the jobsite. Contact Park Dispatch at (415) 561-5505 immediately if animal is hit or injured or will not move off the road.

The following measures are required to minimize disturbance to endangered wildlife:

a. Work shall be conducted to ensure the work area is cleaned up at the end of each work shift so that loose tools, debris, and materials are not left out in a manner that could present a hazard to a listed species.

b. Noise and vibrations of equipment shall be kept to a minimum when working in the vicinity of a listed species.

c. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.

d. Tarps shall be used to contain all paint chips and building debris from exterior surfaces that may fall to the ground.

e. Ensure loose nails and screws do not make it to the ground when working on exterior surfaces as these can be detrimental to listed species.

5. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment.

Archaeological resources are found above and below ground and underwater. The Contractor’s Project Superintendent, or designee, will observe all ground-disturbing activities in archaeological sensitive areas. If the Contractor discovers resources, the Contractor shall stop work or relocate to a non-sensitive area and contact the COR immediately. The Park may also have an Archaeological Monitor at the jobsite who is authorized to stop work upon discovery of archaeological resources. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.

GOGA – 334583 Division 1 Specifications - 6

6. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the COR.

PART 3 – PROJECT MANAGEMENT (SECTION 01 31 00)

3.1 SUBMITTALS

A. Division 01 Submittal Documents: The following documents shall be submitted a minimum of one week prior to the Preconstruction Meeting. If all of these documents have not been received one week prior to the scheduled Preconstruction Meeting date, the meeting will be cancelled and the Notice to Proceed (NTP) will not be issued. Work shall not commence until written Notice to Proceed has been issued.

1. Letter designating the Project Superintendent.

2. Construction Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final inspection date, and other major milestones.

Provide updates to baseline schedule as needed / requested during construction.

3. Schedule of Values (SOV) – Submit a schedule of values with a breakdown of component work activities for which progress payments will be requested. The total costs for the component work activities shall equal the total contract price.

4. Site Specific Safety Plan (SSSP) – provide a Site Specific Safety Plan that will ensure that the procedures, methods and materials used in this removal and installation are compliant with OSHA and Park standards and best practices for employee and site safety. This plan must include name of responsible on-site supervisor, first-aid procedures, outline of each phase of the work, and the hazards associated with each major phase, methods proposed to ensure property protection and safety of the public and planning for potential emergency situations. See Section 01 35 23 of these specifications for requirements of this plan.

5. Licenses and Certificates – Provide a copy of all active California Contractor Licenses and Certifications.

6. A list of Subcontractors for this project.

7. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

B. SOW Submittal Documents: The following documents shall be submitted to the COR prior to construction start. If these documents have not been received and approved by the NPS prior to construction, the construction start date may be delayed.

1. Demolition Plan.

2. Disposal Plan.

GOGA – 334583 Division 1 Specifications - 7

3. Under an Acre Pollution Prevention Plan.

3.2 PRECONSTRUCTION MEETING

A. Preconstruction Meeting: Before the start of construction, the COR will arrange for a preconstruction meeting either on site or via teleconference. The meeting agenda will include the following topics:

1. NPS Roles & Responsibilities

2. Key Contractor Personnel

3. Coordination with Subcontractors

4. Correspondence & Submittal Procedures

5. Submittals

a. Status of Division 01 Submittals

b. Schedule & SOV

c. Safety & Accident Prevention Plan

d. Storm Water Pollution Prevention Plan

e. Status of SOW Submittals

6. Park Rules & Regulations

7. Work Hours and Weekend, Holiday, and Night Work

8. Project Information

a. Park Access & Vehicle Reporting

b. Jobsite Access & Parking

c. Staging, Storage, and Lay Down Area(s)

d. Temporary Facilities & Controls

e. Jobsite Restrictions

f. Resource Protection

g. Weather, Climate, Environmental Conditions

h. Reference Documents

i. Other Contracts / Ongoing Work

9. Labor Standards Provisions

10. Labor Interviews

11. Payroll Reports

12. Payments to the Contractor

13. Change Orders / Modifications

14. Progress Meetings

15. QC Daily Reports

16. Inspections

17. Acceptance and Rejection of Work

18. Closeout Procedures & Submittals

19. Contract Period of Performance

20. Notice to Proceed

3.3 REQUESTS FOR INFORMATION (RFIs)

A. General: On discovery of the need for additional information or interpretation of the Contract Documents, the Contractor shall prepare and submit a RFI form available at https://www.nps.gov/dscw/con_rfi217.htm or may use the Contractor’s own form that at a minimum contains the same information.

GOGA – 334583 Division 1 Specifications - 8

1. COR will only respond to RFIs submitted by the Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. RFI Form: Include a detailed, legible description of the subject or item needing information or interpretation on the RFI Form with:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, if applicable.

6. Photographs or sketches if applicable.

7. Contractor's suggested resolution. If the Contractor's suggested resolution impacts the contract time or the contract sum, Contractor shall state impact in the RFI.

C. Response to the RFI: The COR will review each RFI, determine the action required, and respond accordingly.

PART 4 – SUBMITTAL PROCEDURES (SECTION 01 33 23)

4.1 SUBMITTAL PROCEDURES

A. CM-16 Transmittal Form: All submittals shall be transmitted using National Park Service CM- 16 form available at https://www.nps.gov/dscw/upload/TransmittalForm-CM16_10-7- 20_v508_101420.pdf. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Complete all applicable fields, sign the form, and attach all supporting documentation.

PART 5 – SAFETY REQUIREMENTS (SECTION 01 35 23)

5.1 SAFETY REQUIREMENTS

A. First Aid Equipment: Provide adequate first aid equipment for all contract employees and the hazards associated with the types of ongoing construction work at the site.

B. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.

C. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.

D. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

Store hazardous materials in accordance with manufacturers and OSHA recommendations.

Maintain MSDS onsite for each chemical used on the jobsite. Immediately report all spills of hazardous materials to the COR.

GOGA – 334583 Division 1 Specifications - 9

E. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite.

Topics need to coincide with work scheduled for the week.

F. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.

G. Emergency Reporting: In the event of an emergency medical incident, the Contractor shall Dial 911 as needed. The Contractor shall also contact Park Dispatch at (415) 561-4700 for any medical emergency, traffic accident, or personal injury occurring within the Park. Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.

H. SITE SPECIFIC SAFETY PLAN (SSSP) - This plan should be submitted as part of the preconstruction submittal. This plan will be reviewed and approved by the park safety officer.

A. The following information is intended to serve as a guide to help identify what information should be included in a Site Specific Safety Plan for contracted work. The list is not all inclusive as each project is unique and certain aspects of work may require additional attention to address specific details. Submitted safety plans should be provided with satisfactory time for NPS Safety Officer review, and in advance of scheduling preparatory phase meetings or commencement of work.

1. Safety plans should be specific to the job task and scope, not generic or boilerplate by nature. The Contractor should tailor the safety plan to the job.

2. The safety plan should have a signature page identifying the name, title, phone number and signature of the following: The plan preparer, the company representative authorized to approve the plan, the Project Manager/Superintendent, and the Project Safety Professional. On this page, the NPS Point of Contact should also be identified.

(With smaller companies, one individual might assume responsibility for multiple of these roles.)

3. Safety plans should include a brief description of the project and what work they will be performing and include a map of the general work location.

4. If subcontractors and suppliers will be used on site, the contractor should develop a section where these individuals or groups are identified, the means for controlling and coordinating with subcontractors and suppliers and address the safety responsibilities of the subcontractors and suppliers.

5. Safety plans should identify requirements of reporting workplace accidents both internally and to the NPS, who will conduct accident investigations, procedures for investigating, and how they will be reported.

6. The contractor should provide a list of major work tasks or job phases and submit a Job Hazard Analysis (JHA) or Phase Hazard Analysis (AHA) for each major task or phase. A JHA or PHA is a breakdown of the task or phase in major steps, identifying what hazards or safety exposures are present, then what measures will be in place to control these identified concerns. Guidance on developing JHA’s and forms are available at https://www.nps.gov/subjects/policy/upload/RM- 50B_Chp11_Job_Hazard_Analyses-508.pdf.

GOGA – 334583 Division 1 Specifications - 10

7. The contractor should provide an overview of policies and procedures regarding employee noncompliance with safety requirements and holding personnel accountable for safety.

8. Some projects or phases within the project, such as trenching and excavation, demolition, lead and asbestos remediation, etc. require further planning or separate specific plans within themselves; and they may also need to include a designated competent person to oversee the work. Should this situation arise, these additional aspects or items will also need to be addressed or attached with the plan; competent person(s) will need to be identified along with documentation or evidence detailing their competency and/or their skill level.

9. The contractor should list mandatory training topics to be covered which are applicable to this project, such as excavation, fall protection, scaffolding, hazard communication, confined space, respiratory protection, and personal protective equipment as examples. With training identified, the contractor should then develop a section for each and provide an overview as to how they will carry out these safety aspects. Additionally, the contractor should provide any requirements for periodic training, such as daily/weekly tailgate training occurrences.

10. The contractor should identify the name(s) of the individual(s) responsible for maintaining training records. Actual certifications such as: First Aid/CPR, lead/asbestos worker, scaffolding, fall protection, etc. applicable to the project should be included as attachments or made available for review.

11. The contractor should develop a section in the submitted safety plan addressing requirements for site safety inspections, including but not limited to: inspection frequency, name(s) of individuals who are responsible for conducting safety inspections, procedures for performing inspections, documentation and recording of corrective action requirements. Additionally, this section should also provide details on any external inspections/certifications which may be required.

12. The contractor should include a section on sanitation addressing jobsite housekeeping, toilet facility requirements, hand washing requirements, drinking water availability, and any other requirements that may be applicable to this project.

13. If machinery and mechanized equipment will be used on site, the contractor should develop a section in the site safety plan to include, but not limited to, identifying a competent person who will inspect all equipment prior to it being brought on site, identifying who will perform daily inspections of the equipment, training requirements for use of equipment, seat belt requirements, personnel qualifications for operating the equipment, safe operating instructions, parking and overnight storing requirements, guarding and safety devices.

14. The safety plan should include a section on Personnel Protective Equipment (PPE).

The contractor should provide an overview explaining the requirements and responsibilities for each employee to wear the appropriate PPE in all operations where there is an exposure to hazardous conditions, or where the need for using such equipment to reduce the hazards to the employees is required. Details in this section should include, but may not be limited to outlining procedures (who, when, how) for conducting the hazard analysis to determine PPE needs, assessment or certification of PPE to be used, the care, treatment and proper storage of PPE, etc.

15. The contractor should fully identify or address how they will protect the public during the contract work. Often pedestrian, traffic control and/or signage are key issues on

GOGA – 334583 Division 1 Specifications - 11 project sites. Depending on the project and site, sometimes a formal Traffic Management Plan is needed. Details on traffic control may be required or attached to the submittal and available for review.

16. The contractor should identify emergency contacts for the project and provide the name, phone number, map and driving directions from the worksite to the nearest hospital/emergency medical facility. The contractor should also address requirements for administering first aid, including training requirements and providing certifications of those who will administer first aid or CPR.

17. The contractor should include a section on fire protection and prevention. This section should include a list of the major workplace fire hazards specific to the project, potential ignition sources, the types of fire suppression equipment or systems appropriate to the control of fire, assignments of responsibilities for maintaining the equipment and systems, and personnel responsible for controlling the fuel source hazards.

18. If chemicals will be used or brought on site during this project, the contractor shall develop a section overviewing Hazard Communication, provide or make available documentation that employees have received Hazard Communication training, and shall attach or make available copies of Safety Data Sheets (SDS) for each hazardous material that will be onsite.

19. The contractor should develop a Contingency Plan for Severe Weather. The section should outline procedures addressing each potential severe weather event that is likely to occur at the project site, such as heavy rain, high winds, fires, slides, power outages, etc. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure for persons and property.

20. Should the contractor require a laydown area for materials, equipment, etc. a section detailing this aspect should be provided.

PART 6 – QUALITY REQUIREMENTS (SECTION 01 40 00)

6.1 QUALITY REQUIREMENTS

A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.

B. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The Contractor’s Quality Control Supervisor shall utilize the forms attached at the end of this Section. The submission frequency of the QC Daily Report to the COR will be determined at the preconstruction meeting.

PART 7 – TEMPORARY FACILITIES & CONTROLS (SECTION 01 50 00)

7.1 TEMPORARY FACILITIES & CONTROLS

A. General: The contractor will be allowed to set up temporary facilities and controls as outlined.

All temporary facilities and controls shall be removed from the site before final acceptance of the work.

GOGA – 334583 Division 1 Specifications - 12

B. Temporary Utilities: The following utilities / services are available for use at the project site:

1. Electrical Power Service: Electrical power is not available at the site. The contractor may use battery powered tools or furnish portable generators with proper fuel containment and emergency spill kits.

2. Water Service: Non-potable water service is not available at the site.

3. Sanitary Facilities: Restrooms are not available at the site.

4. Telephone Cellular Service: The project site has limited cellular service availability.

C. Temporary Office: The construction of temporary office buildings or installation of trailers will not be allowed in the park. If the contractor requires office space, the park will attempt to accommodate the contractor with an existing space for administrative work.

D. Temporary Enclosures: If necessary, the contractor shall construct an enclosure fence, barrier, or partition to prevent people and animals from entering the project site except by gates / doors.

E. Temporary Traffic Controls: If traffic flow is to be impeded, the contractor shall erect and maintain barricades, danger signals, and warning signs in accordance with the Manual on Uniform Traffic Control Devices (MUTCD), 2009 edition. The contractor shall provide adequate traffic control, including flaggers on either side of any work performed in the road.

Any workers on or near the road must wear highly visible, bright clothing. 0

PART 8 – UNDER AN ACRE POLLUTION PREVENTION (SECTION 01 57 23)

8.1 SUMMARY

A. NPS Standards and Guidelines require that water quality be protected at all times to ensure compliance with the Organic Act. The Contractor must prepare an Under-An-Acre Pollution Prevention Plan (UPPP) for each project resulting in less than 1 acre of soil disturbance or not otherwise subject to the requirements of the NPDES program.

B. The work of this section consists of implementing measures to limit sediment discharge and Temporary Storm Water Pollution during construction activities in conformance with NPS guidance for UPPPs.

8.2 DEFINITIONS

A. Environmental Pollution and Damage: The presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances; or degrade the utility of the environment for aesthetic, cultural, or historical purposes.

B. UPPP: Developed and implemented pollution prevention plan to protect the environment from pollutants on construction projects with less than one acre of disturbance in conformance with NPS guidelines.

8.3 SUBMITTALS

A. After contract award and before the pre-construction conference, prepare and submit:

GOGA – 334583 Division 1 Specifications - 13

1. A UPPP in conformance with NPS guidelines and adherence to all applicable construction storm water management practices.

B. Inspection Schedule: Submit schedule for inspection and monitoring of all pollution prevention measures.

C. Erosion Control Products: Submit manufacturer's product information and installation recommendations for silt fence, filter fabric, erosion control blanket, straw bales, wattles, and any other materials proposed for use on this project.

8.4 QUALITY ASSURANCE

A. The Contractor must prepare and submit a plan to the Contracting Officer’s Representative (COR) for review and concurrence.

B. Orientation Meeting: The Contractor is responsible for arranging and conducting Pollution Prevention meetings/briefings to inform all parties scheduled to be on-site during the project of the measures to be implemented for proper pollution prevention and control.

1. Installation of silt fences, straw bales, wattles storm, and other forms of pollution prevention controls must not begin until after this meeting has occurred.

C. Pollution Prevention Manager: The Contractor must designate the Pollution Prevention Manager who will be responsible for the implementation, inspection, maintenance, and amendments to the approved plan.

1. The Pollution Prevention Manager must be familiar with UPPP procedures and Best Management Practices (BMPs) and must ensure that emergency procedures and the plan are updated as needed and available for inspection.

2. When changes in the approved plan are required, the Pollution Prevention Manager must prepare and certify an amendment and submit to the Contracting Officer for review and concurrence.

8.5 UNDER AN ACRE POLLUTION PREVENTION PLAN

A. Provide a UPPP which conforms to all NPS requirements and include the following information and forms:

1. Responsible Parties;

2. General Information: Project Scope, Project Details, Site Information, Spill Prevention, Well Water Discharges, and Precipitation Forecasts;

3. Standards and Constraints;

4. Project Scheduling;

5. Known Data on Soil and Fill;

6. Activities with the Potential to Generate Sediment;

7. Activities and Materials with the Potential to Pollute Storm Water;

8. Management and Reporting BMPs;

GOGA – 334583 Division 1 Specifications - 14

9. Waste Management BMPs;

10. Non-Storm Water Pollution Control BMPs;

11. Soil Stabilization BMPs;

12. Sediment Control BMPs;

13. Other Pollution Control BMPs;

14. References;

15. Preparer's Certification;

16. Appendices: Contact Information, Pollution Prevention Control Map or Sheet(s), Standard Installation Specifications for each BMP, and Blank forms.

8.6 ENVIRONMENTAL PROTECTION

A. Protection of Natural Resources: Comply with applicable regulations and these specifications.

Preserve the natural resources within the project boundaries and outside the limits of work performed under this Contract in their existing condition or restore to an equivalent or improved condition as approved by the COR.

B. Construction Zone: Arrange construction activities to minimize pollution (i.e., erosion, trash, etc.)

to the maximum practical extent.

1. Work zone is limited to the area described at the preconstruction meeting. A silt fence shall be installed around the work limits.

2. Clearing, excavation, and grading must be limited to those areas of the project site necessary for construction. Minimize the area exposed and unprotected.

3. Clearly mark and delineate the limits of work activities.

4. Equipment must not be allowed to operate outside the limits of work or to disturb existing vegetation.

5. Material must be stored away from locations where water is present to the greatest extent practicable.

6. All construction debris shall be contained and disposed of off the Park in a legal manner.

8.7 UNDER AN ACRE POLLUTION PREVENTION PLAN EXECUTION

A. Review and Acceptance: The Contractor and the COR will jointly review the draft Plan and agree to any needed revisions. The Contractor will incorporate all jointly agreed to revisions, and then sign and submit the final Plan to the COR. The final Plan will be the document enforced on the project.

1. The jointly agreed to Plan will describe and ensure implementation of the practices which will be used to reduce the pollutants in well water discharges and storm water discharges.

2. The Contractor must maintain a current copy of the Plan and all associated records and forms at the jobsite throughout the duration of the project.

GOGA – 334583 Division 1 Specifications - 15

3. The Plan must be available at all times for public inspection and for the inspection and use of the COR.

4. Concurrence by the COR to the jointly agreed to Plan will not relieve the Contractor of responsibility for compliance with other applicable environmental regulations.

B. Implementation: The Contractor must implement the Plan as required throughout the construction period and maintain all erosion control elements in proper working order.

1. Do not perform clearing and grubbing work until the Plan has been implemented.

8.8 SITE INSPECTIONS AND PLAN REVISIONS

A. Inspections: The Contractor and the COR (or authorized representative) will perform weekly inspections of the site.

1. The inspections will look at disturbed areas that have not been completely stabilized, areas used for storage of materials, locations where vehicles enter or exit the site, and all other erosion and sediment controls that are included in the Plan.

2. Inspections must be documented by the Contractor in their Contractor's Daily Quality Control Reports (CDQCR.)

3. Copies of the CDQCRs that include UPPP inspection information must be retained onsite in the Plan notebook throughout the construction period.

B. Plan Revisions: It may be necessary to revise the Plan during construction to make necessary improvements, revisions, or to respond to unforeseen conditions noted during construction or site inspections.

1. The Plan must specify the mechanism whereby revisions may be proposed by the Contractor or the COR.

2. The Contractor and the COR will jointly review each revision to the Plan before changes are incorporated and implemented. The Contractor will then provide a revised copy of the Plan to the COR.

3. Accepted modifications will be implemented within seven (7) calendar days following the date of the inspection when deficiencies or necessary corrections are first noted.

C. Negligence: Provide additional temporary erosion and pollution controls made necessary by Contractor's errors or negligence at no additional cost to the Government.

8.9 EROSION CONTROL MEASURES

A. Erosion control measures must consist of appropriate BMPs stream work and storm water discharges, including but not limited to silt fencing, barrier protectors, straw bales, wattles, temporary soil retention blankets, excelsior drainage filters, and sediment traps. Note: If straw bales are used locally purchased rice straw only is allowed to reduce chance of invasive species introduced to site.

GOGA – 334583 Division 1 Specifications - 16

B. Erosion control measures must be used to contain discharges within the construction zone. A sufficient area should be established to allow the discharged water to infiltrate into the native soil in such a manner that does not result in erosion of the natural ground surface.

C. All opportunities to facilitate the surface water to percolate into the ground must also be considered, such as utilizing sprinkler heads to evenly distribute the water or utilizing a diffuser pipe manifold and adequate vegetated flow paths.

D. Earthen barriers (non-jurisdictional dams) or holding ponds will not be authorized.

E. Precipitation runoff must be directed around and away from all fuel containment, storage, and work areas within the construction site boundary.

F. Divert precipitation runoff away from the worksite.

G. Construction water used for dust control must have a controlled application rate to prevent sheet flow within the project area as well as out from the construction boundary and into other areas of the Park.

H. Furnish, install, maintain, and operate necessary control measures and other equipment necessary to prevent erosion as described in the approved UPPP.

8.10 MAINTENANCE OF TEMPORARY FACILITIES

A. Ensure erosion and sediment control features remain effective throughout the test well work.

Maintain these features as necessary and reconfigure to adapt to changing conditions.

B. Continuously monitor erosion and sediment control features during test well development and pumping test. Inspect these features before and after each significant precipitation event.

Promptly repair weakened, damaged, and lost erosion and sediment control features.

8.11 REPORTING

A. If a discharge occurs or if the project receives a written notice or order from any regulatory agency, the Contractor will immediately notify the COR and will file a written report to the AHJ within seven (7) days of the discharge event, notice, or order. Corrective measures must be implemented immediately following the discharge, notice, or order. The report to the AHJ must contain the following items at a minimum:

1. The date, time, location, nature of operation, and type of discharge, including the cause or nature of the notice or order.

2. The BMPs deployed before the discharge event, or prior to receiving the notice or order.

3. The date of deployment and type of BMPs deployed after the discharge event, or after receiving the notice or order, including additional BMPs installed or planned to reduce or prevent re-occurrence.

4. An implementation and maintenance schedule for any affected BMPs.

8.12 SEDIMENT DISPOSAL

GOGA – 334583 Division 1 Specifications - 17

A. Sediment resulting from stormwater processes removed from temporary sediment control features must be disposed on the site within previously disturbed area at the end of the project as part of the site restoration. Sediment must be dried out prior to use in site restoration. The locations the sediment is applied must not be in areas susceptible precipitation runoff.

B. Sediment resulting from construction processes shall be removed from the site and disposed of in an acceptable manner.

8.13 REMOVAL OF TEMPORARY POLLUTION CONTROL MEASURES

A. All temporary control measures shall be removed with permission of the COR within ten (10) working days after final acceptance of the project, and/or once grading is completed, and slopes have stabilized.

PART 9 – IMPORTED SOIL AND ROCK (SECTION 01 67 01)

PART 9.1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of sampling, testing and approval requirements for import soil, rock, and fill material.

1.2 RELATED WORK

A. Section 01 89 31 Soil Management

PART 9.2 - PRODUCTS

2.1 GENERAL

A. Import soil and fill material shall meet, but not be limited to, the following standards:

1. Shall be free of organic matter, trash, concrete rubble and other deleterious material.

2. Shall be uncontaminated by chemicals and other materials, as specified in 2.1.B.

B. Imported soil and fill material shall conform to the chemical requirements listed below. See

2.1.C for list of quarries producing materials that have already been tested and found to be within acceptable limits.

CONSTITUENT LIMIT UNITS

Inorganic Chemical Constituents Antimony 5 mg/kg

Arsenic 5.4 mg/kg

Barium 20 mg/kg

Beryllium 10 mg/kg

GOGA – 334583 Division 1 Specifications - 18

Cadmium 0.8 mg/kg Chromium 40 mg/kg

Cobalt 21 mg/kg

Copper 49 mg/kg

Cyanide 2,500 mg/kg

Lead 160 mg/kg

Tetraethyl Lead 0.013 mg/kg

Mercury 0.4 mg/kg

Molybdenum 12 mg/kg Nickel 110 mg/kg

Selenium 0.5 mg/kg

Silver 2 mg/kg

Thalium 1 mg/kg

Vanadium 74 mg/kg

Zinc 60 mg/kg

Semi volatile Organic Compounds Acenaphthene 30 mg/kg

Acenaphthylene 30 mg/kg

Anthracene 30 mg/kg

Benzo(a)anthracene 0.46 mg/kg

Benzo(a)pyrene 0.046 mg/kg Benzo(b)fluoranthene 0.46 mg/kg

Benzo(g,h,i)perylene 30 mg/kg

Benzo(k)fluoranthene 4.6 mg/kg

Benzyl Alcohol 1 mg/kg

Chrysene 30 mg/kg

Dibenzo(a,h)anthracene 0.046 mg/kg Dibenzofuran 2200 mg/kg

Fluoranthene 30 mg/kg

Fluorene 30 mg/kg

Indeno(1,2,3-cd)pyrene 0.46 mg/kg

2-Methylnaphthalene 30 mg/kg

4-Methylphenol (p-Cresol) 50 mg/kg Naphthalene 30 mg/kg

GOGA – 334583 Division 1 Specifications - 19 n-Nitrosodiphenylamine 20 mg/kg

Pentachlorophenol 3 mg/kg

Phenanthrene 30 mg/kg

Phenol 30 mg/kg

Pyrene 30 mg/kg

Volatile Organic Compounds

Acetone 0.24 mg/kg

2-Butanone (MEK) 3.8 mg/kg Carbon disulfide 200 mg/kg

1,4-Dichlorobenzene 0.59 mg/kg p-isopropyltoluene(p-cymene) 130 mg/kg

Methylene chloride 0.076 mg/kg

1,2,3-Trichlorobenzene 15 mg/kg

1,2,4-Trichlorobenzene 15 mg/kg Trichlorofluoromethane 80 mg/kg

1,1,1-Trichloroethane 8 mg/kg

Polychlorinated Biphenyls (PCBs), Pesticides, Herbicides PCBs (Arochlor 1254) 0.033 mg/kg

Aldrin 0.0039 mg/kg alpha-BHC 0.062 mg/kg beta-BHC 0.062 mg/kg delta-BHC 0.062 mg/kg

Chlordane 0.009 mg/kg

2,4-D 0.025 mg/kg

Dicamba 0.01 mg/kg

4,4'-DDD 0.049 mg/kg 4,4'-DDE 0.098 mg/kg

4,4'-DDT 0.0082 mg/kg

Dieldrin 0.039 mg/kg

Endosulfan 1.1 mg/kg

Endosulfansulfate 1.1 mg/kg

Endrin 0.004 mg/kg

GOGA – 334583 Division 1 Specifications - 20

Endrinaldehyde 0.004 mg/kg

Endrinketone 0.004 mg/kg gamma-BHC (Lindane) 0.01 mg/kg

Heptachlor 0.017 mg/kg

Heptachlorepoxide 0.017 mg/kg

Isodrin 0.0039 mg/kg

GOGA – 334583 Division 1 Specifications - 21

MCPP 5 mg/kg

Methoxychlor 0.44 mg/kg

Petroleum Hydrocarbons and Constituents TPH (as diesel) 100 (a) mg/kg

TPH (as gasoline) 100 (a) mg/kg

TPH (as fuel oil/motor oil) 100 (a) mg/kg

Benzene 0.005 (a) mg/kg

Ethylbenzene 0.005 (a) mg/kg

Toluene 0.005 (a) mg/kg Total Xylenes 0.005 (a) mg/kg

Dioxins / Furans 2,3,7,8-TCDD 8.20E-06 mg/kg

NOTES: (a) From California Regional Water Quality Control Board, San Francisco Bay Region Order No. R2-2003-0080

C. Listed materials from the following quarries have been tested and are therefore accepted for use without further chemical testing:

SOURCE ADDRESS APPROVED MATERIAL

BoDean Mark West Quarry

4611 Porter Creek Road Santa Rosa, CA 95404

(707) 576-8205

All materials

Soil and Stony Point Rock Quarry

7171 Stony Point Road Cotati, CA 94931

(707) 795-1775

All materials

Dutra San Rafael Quarry 1000 Point San Pedro Road San Rafael, CA 94901

(415) 258-6876

Aggregate base rock (for use under structures and pavements only) Drain rock (greater than 3/4") Riprap

Graniterock A.R. Wilson Quarry

1900 Quarry Road Aromas, CA 95004

(831) 768-2300

Aggregate base rock Drain rock Riprap

Broadmoor Landscape Supply

1350 El Camino Real South San Francisco, CA 94080

(650) 761-1515

Soil (from Brisbane Quarry)

PART 9.3 - EXECUTION

GOGA – 334583 Division 1 Specifications - 22

3.1 GENERAL

A. Sampling Plan: A sampling plan will be prepared and submitted to the COR for approval prior to collection and testing of proposed import materials from quarries not on above pre-approved list.

B. The Contractor shall ensure that all environmental sampling work is conducted and supervised by individuals and/or a subcontract firm holding the appropriate and applicable technical and professional credentials and/or licenses required by the State of California as necessary.

C. The Contractor shall ensure that environmental sampling follows EPA, California and

American Society of Testing and Materials protocols and guidance.

D. Testing of potential import material shall be consistent with chemical testing requirements of the California Department of Toxic Substances Control, including the DTSC Fact Sheet, Information Advisory, Clean Imported Fill Material, October 2001.

PART 10 – MOBILIZATION / DEMOBILIZATION (SECTION 01 71 13)

10.1 MOBILIZATION / DEMOBILIZATION

A. General: The work under this section consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.

B. Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including…