About this file

This document is a Bid Schedule for a federal solicitation to replace a culvert and culvert stream crossing on the Spine Trail at Golden Gate National Recreation Area in California. The solicitation number is 140P8624Q0052.

The key details are:

  • The National Park Service (NPS) at Golden Gate National Recreation Area requires services to remove a storm-damaged culvert and replace it.
  • The contract includes a base line item for the culvert replacement work as well as an option line item for mobilization/demobilization.
  • Pricing is requested on a lump sum basis. Offerors must submit pricing for the base and option line items.
  • The government reserves the right to exercise any or none of the options.
  • Pricing will be evaluated to determine best value to the government. Offerors are encouraged to submit alternate proposals that could result in cost savings.
  • The period for exercising options is 180 calendar days from the date of award.
  • The contracting agency is the Department of the Interior, National Park Service, Pacific West Region.

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

CONTRACT PRICE BID SCHEDULE
SOLICITATION NUMBER: 140P8624Q0052
PMIS: GOGA - 334583
DEVELOPED AREA: Rancho Corral de Tierra
PROJECT TITLE: Replace Spine Trail Culvert Crossing

Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the correted amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgement of the Contracting Officer to offer the best value to the Government.

In addition to the offer that confirms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identify why the acceptance of the alternate proposal would be advantageous to the Government. See FAR Clause 52.215-1, Instruction to Offerors - Competitive Acquisition - Alternative II and DSC-36 Clause (Instruction for submission of Offers and Other Information) in Section L of the Solicitation.

CONTRACT LINE ITEM NUMBER (CLIN)CONTRACT LINE ITEM (CLI) TITLEQUANTITYUNIT OF MEASUREUNIT PRICETOTAL PRICE
1Mobilization / Demobilization1Lump SumXXXXXXXXXXXX$
2Remove existing Spine Trail Culvert and Replace Culvert and Crossing w/Headwalls1Lump SumXXXXXXXXXXXX$
TOTAL PROPOSED PRICE (contract Line Item Numbers 1 - 2)$
Contract Line Item descriptions are in Section 01 27 00 of the project specifications.